| 1 | 1₹82.5 LAccepted-AOC | ₹82.5 L | 1 | Accepted-AOC The rate quoted by the bidder is less than put to tender value |
| 2 | 2₹83.6 LRejected-AOC | ₹83.6 L | 2 | Rejected-AOC The rate quoted by the bidder is higher than put to tender value |
| Sl No | Description | Qty | Unit | R.NIKESH L2 | Namshivaya sirpa kalaikudam L1 |
|---|---|---|---|---|---|
| 1.00 | Dismantling the existing damaged weathering course and machine pressed tiles from the moolavar sannathi etc., including removing all debris from the site of work. | 142 | cum | 59 ₹8,378 | 57 ₹8,094 |
| 2.00 | Labour charge for dismantling the existing damaged lime concrete from sannathi etc, including removing all debris from the site of work. | 64 | cum | 450 ₹28,800 | 442 ₹28,288 |
| 3.00 | Labour charge for removing the existing damaged brick work from moolavar sannathi including removing all debris from the site of work. | 29.5 | cum | 295 ₹8,702.50 | 288 ₹8,496 |
| 4.00Removing the undulated and dislodged stone lements like wall, thoon, bothiyal, pavukkal, uthiram, flooring from moolavar sannathi and stacking it for later use including cost and conveyance of labour, handling and etc., all complete complying with standard specification. | |||||
| 4.10 | Wall stones, pavukkal | 500 | sqm | 2,180 ₹10.9 L | 2,165 ₹10.8 L |
| 4.20 | Bothiyal, Uthiram | 2.9 | cum | 7,200 ₹20,880 | 7,106 ₹20,607.40 |
| 4.30 | Cut stone slabs | 15.2 | sqm | 678 ₹10,305.60 | 641 ₹9,743.20 |
| 5.00 | Labour charges for Pointing the Cut stone masonary work with lime mortar 1:1.5 (one part of lime and one point five part of sand) excluding cost of cut stone but including all labour charges, scaffolding etc.. complete with standard specifications.. | 496 | sqm | 318 ₹1.6 L | 309.5 ₹1.5 L |
| 6.00 | Supplying and filling in foundation and basement with filling sand in layers of 150mm thickness well watered rammed and consolidated complying with relevant ad specification including cost of supplying filling sand. | 17.4 | cum | 1,700 ₹29,580 | 1,692.5 ₹29,449.50 |
| 7.00Flooring with cut stone slab of size 600mmX600mm and other sizes suitable for site requirement not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and labour charges for paving and Pointing With lime mortar 1:1.5 (one part of lime and one point five part of sand) | |||||
Tender Value
₹82.5 L
EMD Value
₹51,500
Closing Date
28 Oct 2025, 2:00 pmClosed
Fit person /Executive officer
Arulmigu Ekambareswarar and Kandhappar Temple Thammanur Village, Walajabad Taluk, Kancheepuram District.
Repair and resetting of Moolavar Sannithi in Arulmigu Ekambareswarar and Kandhappar Temple, Thammanur Village, Walajabad Taluk, Kancheepuram District.
2025_HRCE_527297_2
01/2025
Open Tender
Civil Works - Others
300 days
Thammanur
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹51,500
Yes
8 May 2026
14 Oct 2025
28 Oct 2025
14 Oct 2025
28 Oct 2025
14 Oct 2025
Amount
Dismantling the existing damaged weathering course and machine pressed tiles from the moolavar sannathi etc., including removing all debris from the site of work.
Labour charge for dismantling the existing damaged lime concrete from sannathi etc, including removing all debris from the site of work.
Labour charge for removing the existing damaged brick work from moolavar sannathi including removing all debris from the site of work.
Removing the undulated and dislodged stone lements like wall, thoon, bothiyal, pavukkal, uthiram, flooring from moolavar sannathi and stacking it for later use including cost and conveyance of labour, handling and etc., all complete complying with standard specification.
Wall stones, pavukkal
Bothiyal, Uthiram
Cut stone slabs
Labour charges for Pointing the Cut stone masonary work with lime mortar 1:1.5 (one part of lime and one point five part of sand) excluding cost of cut stone but including all labour charges, scaffolding etc.. complete with standard specifications..
Supplying and filling in foundation and basement with filling sand in layers of 150mm thickness well watered rammed and consolidated complying with relevant ad specification including cost of supplying filling sand.
Flooring with cut stone slab of size 600mmX600mm and other sizes suitable for site requirement not less than 100mm thick with machine cut edges and top surface dressed as directed by the departmental officers including cost and conveyance of materials to site and labour charges for paving and Pointing With lime mortar 1:1.5 (one part of lime and one point five part of sand)
Single Line Dressing
Three Line Dressing
Refixing the removed stone elements like wall stones, pavukkal, uthiram,bothiyal, thoon and cut stone slab from moolavar sannathi including labour, handling and fixing etc., all complete complying with standard specification.
Wall stones, Thoon, uthiram, bothiyal andpavukkal
Refixing of cut stone slabs
Supplying new stones for missing and damaged portions of two leaf wall and parapet wall portions including cost and conveyence etc., all complete.
Temple structure upto 5 feet length
Dressing and fixing charges for new stones on damaged, severely damaged, fallen, undulated and of two leaf walls, parapet walls & other portions including labour and all complete.
Wall stones - (Ulvari)
Filling of core wall of two leaf stone wall dismantling and re-fixing portion with brick work in lime mortar 1:2 (one part of lime and two part of sand) using Country bricks size 8 -3/4"x4 1/4"x2 3/4" including cost and conveyance of all materials and labour charges and all other incidental charges etc complete complying with standard specification.
Weathering course concrete with broken jelly 20mm size and pure slaked lime over moolavar pavukkal the proportion being 32:12.5 for required depth of 80mm for giving required slope and thickness of roof on required, well beaten with wooden beater etc, complete with standard specifications
Finishing the top of roof with one course of machine pressed tiles 20cmx 20cmx20mm of approved quality laid in lime mortar 1:1.5 (one part of lime and one point five part of sand), 12mm thick mixed with water proofing compound two percent by weight of cement used etc, complete with standard specificarons.
Scaffolding charges for Vimanans and gopurams with casurina posts coconut or plam trees wherever necessary for main, form work and providing with Non Flamable Shaded coverings, providing ladder arrangements, country wood plant for working, inspection etc, complete hire charges only for erection, maintenance and removing the same on completion of the work) sq.ft.
Vimanam/Gopuram upto 15 feet height
Vimanam/ Gopuram upto 25 feet height
Brick masonry lime mortar 1:2 (one part of lime and two part of sand) using Second class ground moulded Chamber bricks size 9" x 43/8" x 23/4" including all varivargams, moulds, sthambams, mukapathrams, koodu, nasi and all ornamental brick work complete, all pancharams, agarais, karnakoodus, etc., forming core walls of Rajagopuram/ Vimanams complete including cost and conveyance of all materials including cement, all the labour charges including marking pathies shaping of the bricks, lifting of all the materials to required heights, curing and all extra for working in heights etc., complete 100 eft for vimanam/gopuram
Vimanam/Gopuram of height up to 15'0" (excluding kalkaram)
Vimanam / Gopuram of height up to 25’0”(excluding kalkaram)
Providing Vargapoochu over the corewalls of Vimanams/Gopurams, with lime mortar 1:1.5 (one part of lime and one point five part of sand) complete including shaping the mukhapathram, mahanasi, Koodu all ornamentals works to proper shape by embedding broken bricks of shaped/chiseled bricks, rough-plastering with lime mortar 1:1.5 and finishing with final ornamental plastering and nayam theervani including cost and conveyance of all materials, labour therefore, lifting of materials, all working in heights, curing with water etc.complete including all extra for folding and including clearing from the vimanams/gopurams 100sft superficial area. for kalkaram
Vimanam/gopuram of ht. Up to 15'0" excluding Kalkaram
Vimanam/gopuram of ht. Up to 25'0" excluding Kalkaram
Providing new sudhai vigrahams in the vimanams and Rajagopurams with Copper rod reinforcement of suitable dia with binding wires wherever necessary, shaping the core with broken bricks set in lime mortar 1:2 (one part of lime and two part of sand) finishing the same with lime mortar 1:2 (one part of lime and two part of sand) bringing to the correct shape (Lakshana) in conformist with silpa sastra inclusive of special ornaments, weapons, peedam etc., complete and providing lime mortar Nayam theervai wherever necessary. inclusive of cost and conveyance of all materials, such as cement broken bricks, and Copper rods. binding wire all labour for working in heights, curing lifting of materials etc., complete including Exterior Emulsion painting two coats over a primary coat (one vigraham is accountable with one head, 4 hands with weapons, ornamental costumes etc., as per prathima lakshans, Vigraham height is measurable from the crown top to the bottom of foot only If peetam is provided the rate with peetam may be adopted as detailed hereunder)
Sudhai size above 1'0" up to 2'6"
Sudhat size above 2'6" up to 3'6"
Painting two coat with approved water based Exterior Emulsion over the cement plastered wall surface, ceiling and other new surface including clearing preparing the surface curing in all floors including brushes etc., complete as per specification.
sub total
R.NIKESH (BID ID -1497029)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_733860.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.14 MB
conditionsthammanur.pdf
Tender Documents • 0.56 MB
BOQ_733860.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid