| 1 | L1₹18.1 LAccepted-Finance V P O JAWALAMUKHI TEHSIL JAWALAMUKHI DISTT KANGRA HP | KANGRA | HIMACHAL PRADESH | 176001 | L1 | Accepted-Finance Accepted | |
| 2 | L2₹19.0 L+₹81,950 (4.52%)Rejected-Finance | L2 | Rejected-Finance Rejected |
Tender Value
₹19.8 L
EMD Value
₹37,200
Closing Date
19 Dec 2020, 11:00 amClosed
Executive Engineer
Jal Shakti Division Solan
Providing consultancy services for preparation of detailed project report for Providing Irrigation Scheme to University of Horticulture and Forestry Nauni in Tehsil and District Solan HP
2020_HPIPH_43187_1
JSDS-T.A.-NIT/20- 18598-18697 dated 11.12.2020
Open Tender
Civil Works - Others
Item Rate
90 days
Nauni Distt. Solan H.P.
Please refer to the tender documents
6 documents required · 6 mandatory
₹400
₹37,200
Yes
8 Aug 2023
12 Dec 2020
19 Dec 2020
12 Dec 2020
19 Dec 2020
12 Dec 2020
12 Dec 2020 - 19 Dec 2020
Amount
Preparation of detailed project report (DPR) for Providing irrigation scheme to University of Horticulture and Forestry Nauni which include on detailed survey, Preparation Shajra Plan and revenue record, Contour Plan, marking of proposal on plan, preparation of L-section of Rising Main and distribution system, detailed hydraulic design, design calculations of all civil/mechanical/ electrical/Eloctronic component, structural design, cost estimations complete for an Area of about 550 Hect.Submission of catchment area detailed calculation using G.I.S. technology and detailed calculations of volumetric contents using the rainfall data.Preparation and submission of digitized revenue record of the entire University area. Approval of Detailed project report from different agencies etc. including prepration of working estimate, tender document, agreement, NIT, Schedule of quantity etc. required for tenders and approval thereof from the competent authority & investigation including the detailed study of all related parameters given in the following check list.
Check List:-The Report shall be presented covering the following parameters.
i) Check list as per CWC (MOWR) PMKSY latest guideline minor irrigation requirement.
ii) Introduction
iii)Salient features
iv)Physical features
v) General Investigations (Social, Climate, Geological, Population & other details.
vi) Design features.
vii) Crop water requirement & meteorological (Irrigation planning).
Viii)Design of all components of the project i.e R/Main, Pumping machinery and distribution system etc..
ix) Construction Material & Construction Programme.
x) Envioronmental & ecological studies:- The rates are exluding of Engironment Impact Assessment (EIA) or Environment and ecological studies and clearance from concerned departments.
xi) Pre & post irrigation crop budget.
xii) Financial resources
xiii) Estimates.
xiv) Revenues
xv) Benefit cost ratio and financial return
Following data needs to be collected from various department.
a)Meteorological data in catchment area of source and command area of project from meteorological department
b) Soil surveys pre and post project cropping pattern/budget from state agriculture department
c) Ground water potential in command and area from ground water organization of GWO/CGWB.
d) Soil investigation survey has to be got conducted for assertaining Bearing Capacity of soil for construction of various civil structures.
e) Geological investigation from state geologist/any other agency in respect of DAM, and water conductor system as per prevailing norms.
Detailed Project Report (DPR) should contains the followings
Volume-I
i)History
ii) Salient features
iii) Physical features
iv) General Investigations (Social, Climate, Geological, Population & other details.
v) Hydrological studies & water resources. The old discharge data of source available with the concerned department shall be used for designing the scheme instead of setting new discharge site .
vi) Pre & post irrigation crop budget.
vii) Crop water requirement & meteorological (Irrigation planning).
viii) Design features.
ix)Design of main components of the project. Keeping in view all the external forces including wind, land slide, earth quake etc.
x) Construction Material & Construction Programme.
xi) Environment & ecological studies and clearance from concerned department
xii) Benefit cost ratio and financial return
xiii) Revenue record
XiV) The proposal should include complete automation of the project with provision of all modern equipment and material is to be used for construction of the project. The Detailed Project Report should include the long term for operation and maintenance of the project.
Drawings. :-
i) Key plan on 100 m grid and contour plan ( C.I =2.0m) on the scale 1:15000 (Detailed Topographical survey & contour plan (C.I = 1.0m) on 30mx30m grid at the scale 1:1000 Surveyed and prepared with the help of DGPS & shall be presented in auto CAD as Soft copy along with prints.
ii). L-section & X- section of R/main, G/main, distribution lines, Minor and Sub minor lines and Pucca field Channel & Kaccha Field channel etc. complete.
iii). Design & Drawing of all relates works such as pump houses, collection tanks, outlets,protection works etc..
iv). Marking of Alignment of R/mains, Gravity mains and distribution system, pump houses, collection tanks, outlets,protection works etc. on Shajra plan.
v). Any item required in addition to above for preparation of Detailed Project Report (DPR).
Volume-2
i)General Abstract of Cost.
ii)Sub head wise abstract of cost & detail of measurements.
iii) Basic rates of material & labour
iv) carriage of material by mechanical transport & mannual
v) Analysis of rates
MINHAS TECHNO-ECONOMICAL CONSULTANCY PRIVATE LIMITED
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .