| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.5 LAccepted-AOC 609 702 | NAGAPATTINAM | TAMIL NADU | 609702 | ₹7.5 L | L1 | Accepted-AOC Accept |
| 2 | L2₹7.5 LRejected-AOC | ₹7.5 L | L2 | Rejected-AOC Reject |
| 3 | Not Admitted-Fee/PreQual/Technical NAGAKUDAIYAN PANCHAYAT VEDARANIAM TAMIL NADU | - | - | Not Admitted-Fee/PreQual/Technical Others-Reason should not showned |
| Sl No | Description | Qty | Unit | V.SANGEETHA L2 | JEEVE CONSTRUCTION L1 |
|---|---|---|---|---|---|
| 1.00 | Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size etc., complete. | 21.84 | Cum | 270 ₹5,896.80 | 263 ₹5,743.92 |
| 2.00 | Cement mortar 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum | 5.46 | Cum | 7,000 ₹38,220 | 6,901 ₹37,679.46 |
| 3.00 | Cement mortar 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to worksite and all labour charges etc., complete. | 38.22 | Cum | 7,700 ₹2.9 L | 7,687 ₹2.9 L |
| 4.00 | Brick work using country bricks of size 8 3/4"x4 1/4"x2 3/4" in cement mortar 1:5 including curing neat finishing etc., complete complying with standard specification | 13 | Cum | 6,400 ₹83,200 | 6,397 ₹83,161 |
| 5.00 | Supply and erections, centering and shuttering charges including cost and conveyance with standard Specification for Below sill level | 125.94 | Sqm | 550 ₹69,267 | 547 ₹68,889.18 |
| 6.00 | Cement concrete 1:11/2:3 using 20mm guage hard broken granite stone jelly for all RCC items of works exclhuding cost of Reinforcement grill and fabricating charges etc., complete. | 2.18 | Cum | 10,300 ₹22,454 | 10,206 ₹22,249.08 |
| 7.00 | Supplying, fabricating and placing in position mild Steel/ Ribbed tor Steel grills for all RCC works as per design given including cost of steel etc., complete. | 0.33 | MT | 91,950 ₹30,343.50 | 91,917 ₹30,332.61 |
| 8.00 | Plastering with Cm 1:5-12mm thick in all floors including curring etc., complete. Complying with standard specification and as directed by the departmental officers | 159.35 | Sqm | 310 ₹49,398.50 | 300 ₹47,805 |
| 9.00 | Painting two coats of newly plastered wall surface with ready mixed Plastic emulsion paint of first class quality and of approved colour over a priming coat including through scrapping, clean removal of dirt etc., complete. | 159.35 | Sqm | 280 ₹44,618 | 262 ₹41,749.70 |
| 10.00 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} 18% for other than Earth Quantity | 1 | GST Amount (in Rupees) | 1,14,785 ₹1.1 L | 1,13,653 ₹1.1 L |
Tender Value
₹7.5 L
EMD Value
₹7,520
Closing Date
25 Feb 2026, 4:00 pmClosed
Block Development Officer(BP),Vedaranyam
Block Development Office, Vedaranyam
Construction Of compound wall at Panchayat Union office campus South and East GF -2025-26
2026_RDTN_663631_2
RD-NGP/498/2025-A2
Open Tender
Civil Works
Works
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹7,520
27 Feb 2026
21 Feb 2026
25 Feb 2026
21 Feb 2026
25 Feb 2026
21 Feb 2026
21 Feb 2026 - 25 Feb 2026
Earthwork Excavation in Hard Soil - Earthwork excavating and depositing with in initial lead of 10m and lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size etc., complete.
Cement mortar 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum
Cement mortar 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to worksite and all labour charges etc., complete.
Brick work using country bricks of size 8 3/4"x4 1/4"x2 3/4" in cement mortar 1:5 including curing neat finishing etc., complete complying with standard specification
Supply and erections, centering and shuttering charges including cost and conveyance with standard Specification for Below sill level
Cement concrete 1:11/2:3 using 20mm guage hard broken granite stone jelly for all RCC items of works exclhuding cost of Reinforcement grill and fabricating charges etc., complete.
Supplying, fabricating and placing in position mild Steel/ Ribbed tor Steel grills for all RCC works as per design given including cost of steel etc., complete.
Plastering with Cm 1:5-12mm thick in all floors including curring etc., complete. Complying with standard specification and as directed by the departmental officers
Painting two coats of newly plastered wall surface with ready mixed Plastic emulsion paint of first class quality and of approved colour over a priming coat including through scrapping, clean removal of dirt etc., complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} 18% for other than Earth Quantity
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 10.91 MB
BOQ_796769.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid