Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.4 LAccepted-AOC | ₹11.4 L | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹11.4 LRejected-AOC | ₹11.4 L | L2 | Rejected-AOC L2 Bidder |
| Sl No | Description | Qty | Unit | NIVIKASRI AND CO L1 | R K AGENCIES L2 |
|---|---|---|---|---|---|
| 1.00 | Clearing the Scrub jungle including all labour charges for burrying and burning etc., complete. | 192.24 | Sqm | 6 ₹1,153.44 | 7 ₹1,345.68 |
| 2.00 | Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS 20 A | 144.18 | Cum | 140 ₹20,185.20 | 141 ₹20,329.38 |
| 3.00 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS | 32.04 | Cum | 752 ₹24,094.08 | 752 ₹24,094.08 |
| 4.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m | 450.42 | sqm | 23 ₹10,359.66 | 24 ₹10,810.08 |
| 5.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 135.13 | Cum | 2,475 ₹3.3 L | 2,476 ₹3.3 L |
| 6.00 | Providing and laying of prime coat using Emulsion at the rate of SS-1 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 1,351.25 | Sqm | 85 ₹1.1 L | 85 ₹1.1 L |
| 7.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 1,351.25 | Sqm | 19 ₹25,673.75 | 19.81 ₹26,770.97 |
| 8.00 | Providing and laying open graded premix carpet of 20 mm compacted thick using 0.18cum of 13.20 mm IRC size HBG machine crushed chips and 0.09 cum of 11.20 mm IRC HBG machine crushed chips with 14.6 Kg of bitumen 60/70 for 10 sqm of premix carpet including laying of seal coat type ‘A’ over the premix carpet using 0.09 cum of 6.7mm IRC size HBG machine crushed chips with 9.8 Kg of bitumen 60/70 per 10 sqm including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling seperately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges etc., complete | 1,351.25 | Sqm | 318 ₹4.3 L | 318 ₹4.3 L |
| 9.00 | Provision for Name board. | 1 | nos | 3,200 ₹3,200 | 4,500 ₹4,500 |
| 10.00 | Photography Charges | 1 | nos | 500 ₹500 | 500 ₹500 |
Updated dates
Tender Value
Refer Docs
EMD Value
₹11,500
Closing Date
26 Dec 2025, 3:00 pmClosed
THE BLOCK DEVELOPMENT OFFICER BP
THE BLOCK DEVELOPMENT OFFICER BP UTHUKULI
BT Road
2025_RDTN_630717_1
TNRD_TPR_UKL_VIRUMANDAMPALAYAM
Open Tender
Civil Works - Buildings
Uthukuli
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹11,500
17 Apr 2026
11 Dec 2025
26 Dec 2025
11 Dec 2025
26 Dec 2025
11 Dec 2025
Amount
Clearing the Scrub jungle including all labour charges for burrying and burning etc., complete.
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS 20 A
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of SS-1 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying open graded premix carpet of 20 mm compacted thick using 0.18cum of 13.20 mm IRC size HBG machine crushed chips and 0.09 cum of 11.20 mm IRC HBG machine crushed chips with 14.6 Kg of bitumen 60/70 for 10 sqm of premix carpet including laying of seal coat type ‘A’ over the premix carpet using 0.09 cum of 6.7mm IRC size HBG machine crushed chips with 9.8 Kg of bitumen 60/70 per 10 sqm including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling seperately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges etc., complete
Provision for Name board.
Photography Charges
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
R K AGENCIES (BID ID -1546269)
stage.html
html • 0.04 MB
technical_754267.pdf
techsummary_754267.pdf
finance_754267.pdf
BOQ Comparative Chart
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.74 MB
tech1.pdf
Tender Documents • 0.27 MB
BOQ_754267.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid