Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹1.0 CrAccepted-AOC GRAM GANDA KUNWAR PO AMODHA CHHAVNI DISTRICT BASTI UTTAR PRADESH | BASTI | BASTI | UTTAR PRADESH | 30300 | ₹1.0 Cr | L-1 | Accepted-AOC L-1 |
| 2 | L-2₹1.0 CrRejected-Finance | ₹1.0 Cr | L-2 | Rejected-Finance L-2 |
| 3 | L-3₹1.1 CrRejected-Finance | ₹1.1 Cr | L-3 | Rejected-Finance L-3 |
| 4 | L-4₹1.1 CrRejected-Finance | ₹1.1 Cr | L-4 | Rejected-Finance L-4 |
| 5 | L-5₹1.2 CrRejected-Finance 183 4 J K COLONY JAYMALU KANPUR NAGAR | ₹1.2 Cr | L-5 | Rejected-Finance L-5 |
| Sl No | Description | Qty | Unit | MAA GOMTI CONSTRUCTION L3 | M/s Parvez Trading Co. L5 | SUBHASH CHANDRA CONTRACTOR L4 | M/S AWADH CONSTRUCTION L2 | M/S GANESH DUTT SINGH CONTRACTOR L1 |
|---|---|---|---|---|---|---|---|---|
| 1.00 | Jungle clearence cutting heavy under growth and bushes upto 7.50cm diameter including removal. | 11,340 | M2 | 2.03 ₹23,020.2 | 3 ₹34,020 | 2.03 ₹23,020.2 | 5 ₹56,700 | 1.85 ₹20,979 Lowest |
| 2.00 | Dismentaling rainforcement concrete As per ID SOR S.No. 6.15 | 13.58 | M3 | 608.07 ₹8,257.59 | 638 ₹8,664.04 | 610.69 ₹8,293.17 | 504 ₹6,844.32 Lowest | 555.51 ₹7,543.83 |
| 3.00 | Earth work in excavation in foundation in all cost of labour material T&P etc. complete | 219.55 | M3 | 75.25 ₹16,521.14 | 79 ₹17,344.45 | 75.57 ₹16,591.39 | 72 ₹15,807.6 | 68.74 ₹15,091.87 Lowest |
| 4.00 | Dismentaling of Brick or Stone Masonary in lime or cement mortar complete as per direction of Engineer-in-charge. | 172.64 | M3 | 380.05 ₹65,611.83 | 400 ₹69,056 | 381.69 ₹65,894.96 | 360 ₹62,150.4 | 347.2 ₹59,940.61 Lowest |
| 5.00 | Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) | 300 | M | 1,808.05 ₹5,42,415 | 1,900 ₹5,70,000 | 1,815.86 ₹5,44,758 | 216 ₹64,800 Lowest | 1,651.79 ₹4,95,537 |
| 6.00 | Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter (only the nos. of extra bulbs are to be paid) | 100 | Each | 1,548.95 ₹1,54,895 | 1,625 ₹1,62,500 | 1,555.65 ₹1,55,565 | 72 ₹7,200 Lowest | 1,415.09 ₹1,41,509 |
| 7.00 | Laying Coarse Sand in filter under interlocking including all cost of labour material T&P etc. complete as per engineer-in-charge. | 156.14 | M3 | 2,056.87 ₹3,21,159.68 | 2,158 ₹3,36,950.12 | 2,065.75 ₹3,22,546.21 | 1,430 ₹2,23,280.2 Lowest | 1,879.11 ₹2,93,404.24 |
| 8.00 | C.C.1:3:6 cement sand & mortor including all cost of labour material T&P etc. complete. | 95.84 | M3 | 4,043.88 ₹3,87,565.46 | 4,335 ₹4,15,466.4 | 4,061.35 ₹3,89,239.78 | 4,670 ₹4,47,572.8 | 3,694.4 ₹3,54,071.3 Lowest |
| 9.00 | Laying Cement Concrete C.C. 1:2:4 (cement coarse sand and 19 mm stone grit mortar) in Flooring including all cost material labour T&P etc. complete | 150.87 | M3 | 4,815.26 ₹7,26,478.28 | 5,183 ₹7,81,959.21 | 4,836.06 ₹7,29,616.37 | 5,390 ₹8,13,189.3 | 4,700 ₹7,09,089 Lowest |
| 10.00 | Brick work Class 150 with (1:4) cement sand mortar including all cost of labour material T&P etc complete. As per direction of engineer-in-charge. | 170.11 | M3 | 5,200.02 ₹8,84,575.4 | 5,500 ₹9,35,605 | 5,222.49 ₹8,88,397.77 | 4,000 ₹6,80,440 Lowest | 5,000 ₹8,50,550 |
Tender Value
₹1.4 Cr
EMD Value
₹2.8 L
Closing Date
23 Jun 2026, 2:30 pmClosed
Supertending Engineer
Irrigation Work Circle Banda
Renovation of Arjun Inspection House under the control of Irrigation Division Mahoba in district Mahoba . (LOT-03)
2026_UPIDC_1160576_1
03/SE/2026-27 dt 08-06-2026
Open Tender
Civil Works
Item Wise
180 days
Mahoba
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,354
₹2.8 L
Irrigation Work Circle Banda
21 Aug 2026
17 Jun 2026
23 Jun 2026
17 Jun 2026
23 Jun 2026
17 Jun 2026
17 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Jungle clearence cutting heavy under growth and bushes upto 7.50cm diameter including removal. | 11,340 | M2 | 2.5 | ₹28,350 |
| 2 | Dismentaling rainforcement concrete As per ID SOR S.No. 6.15 | 13.58 | M3 | 750.7 | ₹10,194.51 |
| 3 | Earth work in excavation in foundation in all cost of labour material T&P etc. complete | 219.55 | M3 | 92.9 | ₹20,396.2 |
| 4 | Dismentaling of Brick or Stone Masonary in lime or cement mortar complete as per direction of Engineer-in-charge. | 172.64 | M3 | 469.2 | ₹81,002.69 |
| 5 | Boring with hydraulic piling rigs with power units, providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-25 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap) | 300 | M | 2,232.16 | ₹6,69,648 |
| 6 | Extra over single under ream for providing additional bulbs in under reamed piles, under specified diameter (only the nos. of extra bulbs are to be paid) | 100 | Each | 1,912.29 | ₹1,91,229 |
| 7 | Laying Coarse Sand in filter under interlocking including all cost of labour material T&P etc. complete as per engineer-in-charge. | 156.14 | M3 | 2,539.34 | ₹3,96,492.55 |
| 8 | C.C.1:3:6 cement sand & mortor including all cost of labour material T&P etc. complete. | 95.84 | M3 | 4,992.44 | ₹4,78,475.45 |
| 9 | Laying Cement Concrete C.C. 1:2:4 (cement coarse sand and 19 mm stone grit mortar) in Flooring including all cost material labour T&P etc. complete | 150.87 | M3 | 5,944.76 | ₹8,96,885.94 |
| 10 | Brick work Class 150 with (1:4) cement sand mortar including all cost of labour material T&P etc complete. As per direction of engineer-in-charge. | 170.11 | M3 | 6,419.78 | ₹10,92,068.78 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.69 MB
TD.pdf
Tender Documents • 2.39 MB
BOQ_2175109.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].