| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | H1₹15.0 CrAdmitted-Finance | ₹15.0 Cr | H1 | Admitted-Finance |
| 2 | H2₹12.9 CrAdmitted-Finance | ₹12.9 Cr | H2 | Admitted-Finance |
| 3 | H3₹12.2 CrAdmitted-Finance | ₹12.2 Cr | H3 | Admitted-Finance |
| 4 | H4₹10.0 CrAdmitted-Finance | ₹10.0 Cr | H4 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Jal Instruments H3 | AJAY DIXIT H4 | SHIV BOREWELL COMPANY H2 | PANKAJ TIWARI H1 |
|---|---|---|---|---|---|---|---|
| 1.01 | 1. Design and build sewage treatment plant of installed capacity 3.0 MLD and all appurtenant structures and allied works;
2. Construction of RCC sump well along with providing and installing pumps and pumping main Comprising of DI-K-7 class pipe of 200mm & 250mm diameter having length of 200 m ,1700 M & 1200 m respectively from Sump well to STP for 3 no’s intermediate pumping stations.
3. Construction 3 Nos. of Interception Diversion Structure.
4. Hydrant, Sump well (Capacity 60KL), Providing, laying, Jointing & field testing of High-Density Polyethylene pipes, (HDPE) Dia 250mm, length 200 m for reuse & Plantation of Trees (Avenue Trees) and their Maintenance
5. Providing and laying of HT Feeder having the length 1.00kms of 33 KVA line for STP and length 4.0 KMs of 11 KVA line for Three Electrical Substation for Three IPS | 1 | nos | 6,10,23,540 ₹6,10,23,540 Lowest | 6,20,75,000 ₹6,20,75,000 | 6,65,43,715 ₹6,65,43,715 | 6,85,98,876 ₹6,85,98,876 |
| 1.02 | Operation and Maintenance Cost next 10 Years | 1 | nos | - | - | - | - |
| 1.03 | 1st Year | 1 | nos | 14,00,000 ₹14,00,000 | 13,30,000 ₹13,30,000 Lowest | 17,85,000 ₹17,85,000 | 20,88,100 ₹20,88,100 |
| 1.04 | 2nd Year | 1 | nos | 14,84,000 ₹14,84,000 | 13,86,600 ₹13,86,600 Lowest | 18,92,100 ₹18,92,100 | 22,13,386 ₹22,13,386 |
| 1.05 | 3rd Year | 1 | nos | 15,73,040 ₹15,73,040 | 14,28,848 ₹14,28,848 Lowest | 20,05,626 ₹20,05,626 | 23,46,189.35 ₹23,46,189.35 |
| 1.06 | 4th Year | 1 | nos | 16,67,422.4 ₹16,67,422.4 | 14,92,040 ₹14,92,040 Lowest | 21,25,964 ₹21,25,964 | 24,86,960.35 ₹24,86,960.35 |
| 1.07 | 5th Year | 1 | nos | 17,67,467.74 ₹17,67,467.74 | 15,61,101 ₹15,61,101 Lowest | 22,53,522 ₹22,53,522 | 26,36,177.8 ₹26,36,177.8 |
| 1.08 | 6th Year | 1 | nos | 18,73,515.81 ₹18,73,515.81 | 16,07,406 ₹16,07,406 Lowest | 23,88,733 ₹23,88,733 | 27,94,349 ₹27,94,349 |
| 1.09 | 7th Year | 1 | nos | 19,85,926.76 ₹19,85,926.76 | 16,22,406 ₹16,22,406 Lowest | 25,32,057 ₹25,32,057 | 29,62,009.75 ₹29,62,009.75 |
| 1.10 | 8th Year | 1 | nos | 21,05,082.36 ₹21,05,082.36 | 16,79,994 ₹16,79,994 Lowest | 26,83,980 ₹26,83,980 | 31,39,730.05 ₹31,39,730.05 |
Tender Value
₹7.0 Cr
EMD Value
₹3.5 L
Closing Date
1 May 2026, 5:30 pmClosed
CMO , NAGAR PARISHAD PRITHVIPUR
WARD NO 09 NEW BUS STAND TEHARKA ROAD PRITHVIPUR DISTRICT-NIWARI
INTERCEPTION and DIVERSION WORK FOR TAPPING NALLAH AND SETUP SEWAGE TREATMENT PLANT FOR USED WATER MANAGEMENT FOR PRITHVIPUR TOWN UNDER SBM 2.0
2026_UAD_494782_1
782/E-tender/pwd/pri/2026
Open Tender
Miscellaneous Works
Lump-sum
365 days
OFFICE OF NAGAR PARISHAD PRITHVIPUR
REFER TO TENDER DOCUMENT
3 documents required · 3 mandatory
₹20,000
₹3.5 L
OFFICE OF NAGAR PARISHAD PRITHVIPUR
16 Jul 2026
27 Mar 2026
4 May 2026
27 Mar 2026
1 May 2026
27 Mar 2026
25 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | 1. Design and build sewage treatment plant of installed capacity 3.0 MLD and all appurtenant structures and allied works;
2. Construction of RCC sump well along with providing and installing pumps and pumping main Comprising of DI-K-7 class pipe of 200mm & 250mm diameter having length of 200 m ,1700 M & 1200 m respectively from Sump well to STP for 3 no’s intermediate pumping stations.
3. Construction 3 Nos. of Interception Diversion Structure.
4. Hydrant, Sump well (Capacity 60KL), Providing, laying, Jointing & field testing of High-Density Polyethylene pipes, (HDPE) Dia 250mm, length 200 m for reuse & Plantation of Trees (Avenue Trees) and their Maintenance
5. Providing and laying of HT Feeder having the length 1.00kms of 33 KVA line for STP and length 4.0 KMs of 11 KVA line for Three Electrical Substation for Three IPS | - | nos | - | - |
| 1.02 | Operation and Maintenance Cost next 10 Years | - | nos | - | - |
| 1.03 | 1st Year | - | nos | - | - |
| 1.04 | 2nd Year | - | nos | - | - |
| 1.05 | 3rd Year | - | nos | - | - |
| 1.06 | 4th Year | - | nos | - | - |
| 1.07 | 5th Year | - | nos | - | - |
| 1.08 | 6th Year | - | nos | - | - |
| 1.09 | 7th Year | - | nos | - | - |
| 1.1 | 8th Year | - | nos | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.91 MB
TENDERDOCUMENT.pdf
Tender Documents • 2.47 MB
prithvipur.pdf
Other Document • 2.67 MB
BOQ_590389.xls
BOQ • 0.34 MB
DPR.pdf
Additional Documents • 27.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].