| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹28.6 LAccepted-AOC | ₹28.6 L | L1 | Accepted-AOC L1 |
| 2 | L2₹28.9 LRejected-Finance | ₹28.9 L | L2 | Rejected-Finance L2 |
| 3 | L3₹29.0 LRejected-Finance MU PO RAHIMPUR TA SANGAMNER DIST AHILYANAGAR | SANGAMNER | AHILYANAGAR | MAHARASHTRA | ₹29.0 L | L3 | Rejected-Finance L3 |
| 4 | Rejected-Technical | - | - | Rejected-Technical Reject |
| 5 | Rejected-Technical | - | - | Rejected-Technical Reject |
Tender Value
₹29.0 L
EMD Value
₹29,045
Closing Date
6 Apr 2026, 3:00 pmClosed
EE MI ZP AHILYANAGAR
EE MI ZP AHILYANAGAR
REPAIRS TO PERCOLATION TANK AT KHAMBE (Gaval tek) TAL-SANGAMNER DIST-AHILYANAGAR
2026_AHMED_1291292_1
ZP/MI/WORKS/27025841/2025-26
Open Tender
Civil Works
180 days
AHILYANAGAR
AS PER NIT
2 documents required · 2 mandatory
₹1,180
₹29,045
20 May 2026
30 Mar 2026
7 Apr 2026
30 Mar 2026
6 Apr 2026
30 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Item No.165: - Dismantling dry rubble stone pitching including stacking all materials with 15 m lead and all lifts etc complete as directed. | |||||
| 2 | Item No.1:- Excavation in all kinds of soil in including boulders up to 0.6 m diameter (0.113cum) for canal, seating of embankment, filter drains / catch water drains etc., and placing the excavated stuff neatly in dump area or for formation of service road / embankment including cost of all materials, machinery, labour, dressing bed and sides to required level and profile etc.completed with lead up to 15m and all lifts as directed | - | Cum | 1 | - |
| 3Desilting stream | |||||
| 4 | Item No.2:-Excavation in hard murum including boulders up to 0.6 m diameter (0.113cum) for canal,seating of embankment, filter drains / catch water drains etc., and placing the excavated stuff neatly in dump area or for formation of service road / embankment including cost of all materials, machinery, labour, dressing bed and sides to required level and profile etc., completed with all lead up to15m and all lifts as directed. | 0.32 | Cum | - | - |
| 5 | Item No.3:-Excavation in soft rock without blasting including boulders up to 0.6 m diameter ( 0.113cum) for canal,seating of embankment, filter drain / catch water drains etc.,and placing the excavated soft rock neatly in dump area or for formation of service road including cost of all materials, machinery, labour, dressing bed and sides to required level and profile etc. completed with lead up to15m and all lifts as directed. | 1 | Cum | 1 | ₹1 |
| 6 | Item No.10 B :- Providing hearting embankment using selected impervious soil from approved borrow areas (Government acquired land) in layers including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water etc., complete with lead up to1 km and all lifts as directed. | - | Cum | 1 | - |
| 7 | Item No.36D:- Providing and laying polythene film of 031 properly manufactured from 100% virgin granules confirming to I.S. 2508-1984 with 1.5 to 2.5 m. package in rolls/ as per specifications. D) Providing & Laying plastic film 500 micron HDPE Geomembrance confirming to IS:15351:2015 Type II as per specification including laying etc complete | 1 | Sqm | - | - |
| 8 | Item No.9A:- Providing cut off trench filling using selected impervious soil directly available from material of excavation including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water etc. complete with lead up to1 km for water and all lifts as directed. | 1 | Cum | 1 | ₹1 |
| 9 | Item No.9 B :- Providing cut off trench filling using selected impervious soil from approved borrow areas (Government acquired land) including cost of all materials, machinery, labour, all other operations such as collection of soil, spreading soil in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water etc. complete with lead up to1 km and all lifts as directed. | 0.32 | Cum | - | - |
| 10 | Item No.11A:- Providing casing embankment using selected pervious material available directly from excavation in layers including cost of all materials, machinery, labour, all other operations such as collection of material, spreading material in layer of specified thickness, sorting out, breaking clods, leveling, sectioning edges / sides, watering, compacting each layer to density control of not less than 95 percent or as stipulated using vibratory compactor including cost of water etc. complete with lead up to1 km and all lifts as directed. | 0.2 | Cum | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.65 MB
BOQ_2219686.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid