| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.0 LAccepted-Finance | L1 | Accepted-Finance QUALIFIED | |
| 2 | L2₹2.3 L+₹35,330 (17.8%)Accepted-Finance | L2 | Accepted-Finance QUALIFIED | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹2 L
EMD Value
₹2,000
Closing Date
20 Dec 2021, 11:00 amClosed
SE EDC III BULANDSHAHR
EDC III BULANDSHAHR
TO INCREASE CAPACITY TRANSFORMER AND CONSTRUCTION OF HT LT LINE BY INVITING RUNNING E TENDER UNDER EDD JAHANGIRABAD.
2021_PVVNL_652497_1
T-75/EDC-III/B/2021-2022
Open Tender
Electrical Works
Lump-sum
90 days
BULANDSHAHR
TO INCREASE CAPACITY TRANSFORMER AND CONSTRUCTION OF HT LT LINE BY INVITING RUNNING E TENDER UNDER EDD JAHANGIRABAD.
2 documents required · 2 mandatory
₹1,180
ICICI BANK
₹2,000
30 Dec 2021
7 Dec 2021
20 Dec 2021
7 Dec 2021
20 Dec 2021
7 Dec 2021
Amount
fo|qr forj.k [k.M&tgkWxhjkckn {ks=kUrxZr ifjorZd {kerko`f) ,oa rRlEcU/kh ,p0Vh0@,y0Vh0 fuekZ.k lEcU/kh dk;ZA
Carriage of fallowings from ESC BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, required ccompletion of work, distance about to 0 to 70 Km. approx.
Carriage of All line Material from store to j.e store Sub-station as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire, M.S. Channel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Carriage of PCC Pole 8.5 mtr long.
Carriage of 25 KVA Transformer
Carriage of 63 KVA Transformer
Erection of Single support including complete H.T./L.T. fittings as per RESPO manual and as per direction of Engineer incharge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Erection of Double support including complete H.T./L.T. fittings as per RESPO manual and as per direction of Engineer incharge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Single support shall be grouted with cement, sand and birck ballast/stone ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of Cement, Sand, Brick Ballast/Stone Ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Grouting of Double pole support shall be grouted with cement, sand and birck ballast/stone ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of Cement, Sand, Brick Ballast/Stone Ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
Mounting of 25 KVA Transformer
Mounting of 63 KVA Transformer
Fixing of Stay rod with Stay wire in proper way with Nozelling.
Grouting of Stays Rods.
Fixing of Earthing Rod complete
Laying, sagging. Stringing and binding and jumpering of ACSR Weisal, rabbit, dog newly erected poles as per RESPO manual and as per direction of Supervising Engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
ACSR weasal conductor
The following material is required tobe supplied by the contractor.
Holding clamp.
Double pole Clamp.
LT Clamp
Bolts & nut off size.
F clamp
Stay clamp
Stay Insulator
Fabrication of Angle and Channel with drilling hole.
Above work shall be done as per UPPCL/RESPO Rules.
NEHA ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .