Tender Value
Refer Docs
EMD Value
₹2.1 L
Closing Date
5 Oct 2026, 2:00 pm
General Manager (Zone-4) Agra
office of General Manager (Zone-4) House No A-121 Sector 13 Avas Vikas Colony Sikandra Agra
Construction of multipurpose sheed strore and dissemination center kisan kalyan kendra under rashtriya krishi vikas yojana at vikas khand eka district firozabad
2026_UPPRC_1189955_1
29/GM-4/UPPCL/2026-27/E TENDER DATE 22.09.2026
Open Tender
Civil Works - Buildings
Percentage
270 days
vikas khand Eka District Firozabad
Construction of multipurpose sheed strore and dissemination center kisan kalyan kendra under rashtriya krishi vikas yojana at vikas khand eka district firozabad
2 documents required · 2 mandatory
₹17,700
₹2.1 L
26 Sept 2026
26 Sept 2026
5 Oct 2026
26 Sept 2026
5 Oct 2026
26 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil. | 158.87 | Cum | 185.15 | ₹29,414.78 |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. | 111.21 | Cum | 139.42 | ₹15,504.9 |
| 3 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 5 km, also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc., complete. | 55.05 | Cum | 498.27 | ₹27,429.76 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources). | 42.14 | Cum | 4,845.39 | ₹2,04,184.73 |
| 5 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 41.08 | Cum | 1,510.63 | ₹62,056.68 |
| 6 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). LINTEL
GROUND FLOOR | 4.68 | Cum | 8,183.88 | ₹38,300.56 |
| 7 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). LINTEL
FIRST FLOOR | 1.99 | Cum | 8,183.88 | ₹16,285.92 |
| 8 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). SLAB
GROUND FLOOR | 41.91 | Cum | 8,183.88 | ₹3,42,986.41 |
| 9 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III)derived from natural sources : 3 graded stone aggregate 20 mm nominal sizederived from natural sources). SLAB
FIRST FLOOR | 17.98 | Cum | 8,183.88 | ₹1,47,146.16 |
| 10 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 5.33 | Cum | 6,434.25 | ₹34,294.55 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.97 MB
biddocum29.pdf
Tender Documents • 4.59 MB
BOQ_2242527.xls
BOQ • 0.64 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .