| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.9 LAccepted-Finance | L1 | Accepted-Finance OK | |
| 2 | L2₹10.0 L+₹8,671 (0.87%)Accepted-Finance | L2 | Accepted-Finance OK | |
| 3 | L3₹11.4 L+₹1.5 L (14.6%)Accepted-Finance 03 GOVIND PURAM EIDGHAH ROAD BIJNOR BIJNOR UTTAR PRADESH 246701 | BIJNOR | UTTAR PRADESH | 246701 | L3 | Accepted-Finance OK |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
18 Feb 2020, 3:00 pmClosed
SE ETC NOIDA
220 KV SUB STATION SECTOR-20 NOIDA
Construction of 33 kV Transfer Bus, 33 kV CT reorientation related works, installation of 33 kV Isolators and other associated works at 132 kV S/S Sector-66 under ETD-II Noida
2020_UPTCL_426272_1
E-T-78/ETCN/2019-20
Open Tender
Electrical Works
Item Rate
30 days
NOIDA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
EE ETD NOIDA
₹10,000
7 Mar 2020
21 Jan 2020
19 Feb 2020
21 Jan 2020
18 Feb 2020
21 Jan 2020
Amount
Dismentaling of following Main Structure From existing 33 KV Transfer Bus by opening/cutting Nuts and Bolts, proper stacking at site, work includes opening/cutting of earthing strip. ATM, AXM, CCM, CGM, ALP, BBL, CGM & other main or Aux. structure
Erection of following Main & Auxiliary Structure for 33 KV Transfer Bus & 132 Main Bus sectionisation
Sorting and stacking of structures
ATM, AXM, CCM, ALP, ABL, BBL, CGM & other main or Aux. structure
Erection of 33 kV Bus Isolators for 33 kV Transfer Bus Section.
Earthing of 132 kV, 33 kV Main, Auxiliary structure & equipments with MS flat 50X6 mm (MS flat of size50X6 mm shall be arranged by contractor at its own cost) as per UPPTCL norms.
Dismantalling of 132 KV CB (CGL make) by opening of all the 6 jumpers, by cutting earthing, opening of control cables termination. Dismantalling of all the three phase poles, operating mechanism etc safely
Preparation of Cable schedule for interconnection between Newly erected132 kV CB to control panel as per technical specification.
Shifting & Relocation of Control Cables from OLD location of 132 kV CB to NEW location of CB for each 132 KV Bay by opening of cable trenches and covering it back after shifting of cables
Erection of 132 KV Isolators
Safe Erection of 132 kV CB (CGL make or else) with both side Jumpers, termination of control cable as per cable schedule.
Opening, Cutting & Dismantalling of R,Y & B phase of 132 KV existing Main Bus Bar made of Tarantulla/Zebra conductor between bus sections below gantries, step-by-step during bus-bar replacement work including dismantling of all types of associated clamps, fittings & suspention string.
Dismantling of following existing jumpers from 132 kV main bus bar, and Jack Bus Bar by opening of all associated clamps, step-by-step during bus bar replacement work. Jumpers of ACSR Zebra/ Panther conductor of Transformer, Line or Bus-Coupler etc.
Stringing and proper sagging of new 132 KV Main Bus-Bar sections (R, Y & B) with Twin Zebra conductor the work includes fitting of tension clamps, hoisting of 70/120 KN disc insulators, tension fitting, spacers PG/C-wedge clamps etc. and cutting of conductor as required
Re-connecting of R, Y & B phase of 132 KV Main Bus Bar–I of Twin Zebra conductor between bus sections below gantries, step-by-step on 132 kV newly erected Bus section Isolators.
Re-connecting following new jumpers on different bays after fixing spacers, clamps as required. Connecting Jumpers of ACSR Twin Zebra conductor of Transformer bay, Line Bay and Bus-coupler bays by cutting in proper size.
Dismatling of four no. 33 KV existing Transfer Bus Bar Sections (R, Y & B ) of ACSR Panther conductor in front of 63 MVA T/F I & III to complete dismantling work including dismantling of all associated Tension Clamps, fittings & Disc Insulators etc.
Complete dismantling of existing 33 KV CT(s) different make after opening jumpers and cutting of earthing and opening of control cable termination including all associated works to complete the work satisfactorily.
Complete dismantling of existing 33 KV CT Junction Box(s) after removing its earthing and opening of control cable termination and all other associated works.
Complete erection of 33 KV CT(s) different make on newly erected ALP Structure along with all other associated works as per guidance of supervising engineer.
Installation of CT Junction box on newly erected ALP and its earthing with all other associated works.
Preparation of Cable schedule for interconnection between Newly erected 33 KV CT to Newly erected 33 KV CT Junction Box as per technical specification.
Shifting & Relocation of Control Cables from OLD CT Junction Box location to NEW CT Junction Box location for each 33 KV Bay by opening of cable trenches and covering it back after shifting of cables.
Laying of following size control cable between Newly erected 33 KV CT and Newly erected 33 KV CT Junction box.
2 x 2.5 Sqmm
4 x 2.5 Sqmm
6 x 2.5 Sqmm
10 x 2.5 Sqmm
Termination of Control Cables at newly erected 33 KV CT(s)-36 Nos and newly erected 33 KV CT Junction Box-12 Nos as per cable schedule along with providing and fixing of cable gland of appropriate size and providing and fixing of ferrules for each core of cable.
Fixing of Fired wedged type"C" connector (RPG make) suitable for Zebra to Zebra conector having 1250 Amp cpacity.
Supply of Bolted type tension fitting for Twin Zebra conductor without turn buckle for 132 KV main bus suitable for each disc stringing 10 Nos 70 KN disc insulator with hardware fitting D-shackle, D-socket, Ball Hook, Yoke Plate, d-clip, Tension clamp etc. as per technical specification.
Supply of Bolted type tension fitting for Twin Zebra conductor with turn buckle for 132 KV main bus suitable for each disc stringing 10 Nos 70 KN disc insulator with hardware fitting D-shackle, D-socket, Ball Hook, Yoke Plate, d-clip, Tension clamp etc. as per technical specification.
Supply of Fired wedged type"C" connector (RPG make) suitable for Zebra to Zebra conector having 1250 Amp cpacity.
M/S QUADRY CONTRACTOR AND SUPPLIAR
DEEP ENTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .