Tender Value
₹14 L
EMD Value
₹14,000
Closing Date
7 Mar 2024, 3:00 pmClosed
BLOCK DEVELOPMENT OFFICER
manamelkudi
Construction of New Anganwadi Building near PUES School at Keeranur Habitation in Manaloor Panchayat
2024_RDTN_434322_1
WORK 6 24-25 MANALOOR PANCHAYT
Open Tender
Civil Works
Item Rate
180 days
MANAMELKUDI
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹14,000
15 Mar 2024
2 Mar 2024
7 Mar 2024
2 Mar 2024
7 Mar 2024
2 Mar 2024
Amount
Construction New Anganwadi Building in PUES School near in Keeranur Manalur Panchayat
Earth work excavation in all classess soil with initinal lead and lift as per SS 20B etc complete.
Filling with course gravel including cost and conveyance to work site including all labour charges for filling etc complete
Filling with M sand including cost and conveyance of sand to work site including all labour charges for filling etc complete - rate for 1 cu.m
Cement concrete 1:4:8 mix using 40mm HBG metal including cost and conveyance of all materials to site including all labour charges for filling etc complete - rate for 10 cu.m
R.C.C. 1:1.5:3 mix using 20mm HBG metal including cost and conveyance of all materials to work site and all labour charges etc.complete - rate for 10 Cu.m
BRICK WORK in cement mortar 1:5 (One cement and five sand) using second class country bricks of size 23cm x 11cm x 7cm for the following including curing etc., complete complying with standard specifications.
Supplying, fabricating and placing in position mild steel/Ribbed tor steel rods for all RCC works including cost of steel and binding wire also in all floors, complete complying with standard specfication.
Centring for sides and soffits including cost and conveyance of all labour charges etc complete.
Special ceiling plastering with cement mortor 1:3 mix to 10mm thickness including cost and conveyance of all materials to site and all labour charges etc. complete rate for 10.00 sq.m
Plastering with cement mortor 1:5 mix 12mm thickness including cost of conveyance of all materials to work site and all labour charges etc. complete rate for 10.00 sq.miyarangam.'!B128
Weathering Course Concrete to 80 mm thickness (average) using 20mm size Brick jelly with slacked lime in the proportion 32:12:50 (No sand to be used) including cost and conveyance of all materials to
Pressed Tiles over the RCC roof slab in the proposition being brickjelly to lime 32:12:1/2 by volume and laid into a single layer and consolidate to required finished
Paving the floor with best quality Vetrified (Such as Morbonite) Tiles of size 600 x 600 x 8mm of approved colour, shade and quality laid in cement mortar 1:3 (one cement and three Sand) 20mm thick in all floors and the top pointed with the white cement mixed same colour pigments etc., complete complying with standard specification.
Providing granolethic floor finish in cement concrete 1:2:4 mix using 10-12mm ISS metal to 25mm thick including cost and conveyance of all materials to site and all labour charges for mixing, laying, curing etc complete
SUPPLY AND FIXING OF GLAZED TILES including cost and conveyance of all materials to site and all labour charges etc. complete
Cost and supply of steel door of size 0.75 x 2.10 m including cost and conveyance of all materials and all labour charges etc., complete.
Cost and supply of steel door of size 1.00 x 2.10 m including cost and conveyance of all materials and all labour charges etc., complete.
Cost and supply of steel door of size 1.10 x 2.10 m including cost and conveyance of all materials and all labour charges etc., complete.
Cost and supply of steel Window of size 1.20 x 1.30 m including cost and conveyance of all materials and all labour charges etc., complete.
Cost and supply of steel vendilator of size 0.90 x 0.45 m including cost and conveyance of all materials and all labour charges etc., complete.
Cost and supply of RCC Jolly of size 0.60 x 0.45 m including cost and conveyance of all materials and all labour charges etc., complete.
White washing two coats using shell lime including cost and conveyance of all materials to site and all labour charges etc comoplete
Distember two coats over one coat of primary coat including cleaning preparing the surface one coat of primer. For Inner and ceiling
Emulsion two coats with Exterior emulsion over one coat of primary coat including cleaning preparing the surface For Outer wall surface
Painting in two coats with Over the new Iron work such as Steel Doors,Windows,Ventilator etc., with best approved Synthetic enamal paint of approved colour over the existing priming
Painting Two coats ofBlack board painting with Black oxide paint with best approved first quality of synthetic enamel paint of approved colour over the existing priming coats, etc., complete
Wiring with 2 x 1.50 sqm ( 22/0.3 ) PVC insulated unsheathed single core Copper Conductor of 1100 v Grade in suitable PVC Rigid Pipe on wall and ceiling with PVC accesseries with TW Switch box with 5 A F . T . Switch with painting of suitable colour for Light Point and Fan Point
Wiring with 2x1.50 sqm PVC insulated unsheated Sc.alu Cable of conductor of 1100V grade insulated for open plug point .
Suplying and Fixing of 1200mm (48") AC ceiling fan complete with stepped Regulator as per standard specifications.
Supply and Fixing of 11 W CFL in the existing light point
Supply and fixing run off 2x1.50sqm PVC insulated Sc . Un sheated Sc conductor of 1100 v grade on 7/20 GI Bearer wire for Service Main
Supplying & Fixing in European Water Closet with "P" or "S" Trap with Double Flapped Seat and Seat Cover with Brass Hinges and 10 litre capacity PVC Low Level Flusing Tank with all internal fittings
Supplying & Fixing in position of Baby Water closet
Supplying & Fixing in position of Wash Basion
Provision for Rain 100mm Pvc Pipe etc.,complete
Supplying & fixing with cuddapah slabs 20-30mm thick for cup board thick and pointed with cement mortar 1:3 etc, complete
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
ABDUL SAMADU
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .