Tender Value
₹4.8 L
EMD Value
₹9,580
Closing Date
10 Jul 2026, 3:00 pm2d left
XEN PHE DIV REASI
XEN PHE DIV REASI
Restoration Re-construction of Different water supply of Pouni, Bhomag, Reasi and Arnas Block in Sub Division Reasi under SASCI.
2026_PHE_314466_1
ENIT NO. 25 OF 2026-27 DT. 03-07-2026
Open Tender
Civil Works
60 days
REASI
Please refer Tender documents.
2 documents required · 2 mandatory
₹200
XEN PHE DIV REASI
₹9,580
3 Jul 2026
3 Jul 2026
11 Jul 2026
3 Jul 2026
10 Jul 2026
3 Jul 2026
3 Jul 2026 - 4 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: All kinds of soil. | 80.08 | Cum | 479.3 | ₹38,382.34 |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: Ordinary Rock | 20.02 | Cum | 924.8 | ₹18,514.5 |
| 3 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil : | 10.96 | Cum | 592.9 | ₹6,498.18 |
| 4 | Earth work in bulk excavation by manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. Ordinary Rock : | 2.73 | Cum | 940.3 | ₹2,567.02 |
| 5 | Providing and fixing G.I. pipes complete with G.I. fittings excluding trenching and refilling etc. (external work) 50 mm dia. nominal bore (L) | 210 | Mtr | 532.8 | ₹1,11,888 |
| 6 | Providing, laying, fixing & jointing of ISI marked HDPE pipes as per ISI-4984-1995 casting along the trenches and laying the same in trenches to correct allignment and gradient, cutting, jointing & testing complete as per specifications. HDPE 50 mm PN-10 | 200 | Mtr | 140.2 | ₹28,040 |
| 7 | Providing, laying, fixing & jointing of ISI marked HDPE pipes as per ISI-4984-1995 casting along the trenches and laying the same in trenches to correct allignment and gradient, cutting, jointing & testing complete as per specifications. HDPE 40 mm PN-10 | 150 | Mtr | 99.8 | ₹14,970 |
| 8 | Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing Tee, including cutting and threading the pipe etc. complete 25 to 40 mm nominal bore | 5 | Each | 730.25 | ₹3,651.25 |
| 9 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. | 92.14 | Cum | 218.4 | ₹20,123.38 |
| 10 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 2.05 | Cum | 5,202.92 | ₹10,665.99 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.65 MB
BOQ_1018150.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid