| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.3 LAccepted-AOC | ₹23.3 L | L1 | Accepted-AOC Lowest rate quoted |
| 2 | L2₹23.4 LRejected-AOC | ₹23.4 L | L2 | Rejected-AOC Highest rate quoted |
| 3 | Rejected-Technical | - | - | Rejected-Technical Highest rate Quoted |
| 4 | Rejected-Technical | - | - | Rejected-Technical Highest rate Quoted |
| Sl No | Description | Qty | Unit | subramaniancontractor L2 | SST AND CO L1 | S.Paramasivan L3 | MARITHANGAM L4 |
|---|---|---|---|---|---|---|---|
| 1.00Name of Work: Construction of Multipurpose Community Hall at Vadakkukaraseri Village in vadakuukaraseri panchayat in Karungulam Panchayat union of Thoothukudi District under NATURAL CALAMITIES -2025-26-pakageno-01 | |||||||
| 2.00 | Earthwork excavation and depsoiting on banks with an initial lead and lift in Hard soil etc, complte as per SS20B for foundation. | 75.3 | Cum | 250 ₹18,825 Lowest | 263 ₹19,803.9 | 255.87 ₹19,267.01 | 261 ₹19,653.3 |
| 3.00 | Collection and supply of Girtty gravel and filling into the foundation and basement including cost and conveyance of sand and labour charges etc, complete | 10.42 | Cum | 386 ₹4,022.12 | 1,500 ₹15,630 | 44.47 ₹463.38 Lowest | 403 ₹4,199.26 |
| 4.00 | Cement Concrete 1:4:8 mix, using 40mm ISS, HBG metal including cost and conveyance of materals and labour charges for laying, compacting, curing etc, complete. | 12.88 | Cum | 5,116 ₹65,894.08 Lowest | 6,066 ₹78,130.08 | 5,542.59 ₹71,388.56 | 5,337 ₹68,740.56 |
| 5.00Supply and erection of centering for sides and soffits of concrete works inclduing cost and conveyance of materials and labour charges etc, complete. | |||||||
| 6.00 | Below GL | 104.11 | Sqm | 520 ₹54,137.2 Lowest | 547 ₹56,948.17 | 531.08 ₹55,290.74 | 542 ₹56,427.62 |
| 7.00 | Above GL | 200.79 | Sqm | 1,039 ₹2,08,620.81 Lowest | 1,095 ₹2,19,865.05 | 1,062.15 ₹2,13,269.1 | 1,084 ₹2,17,656.36 |
| 8.00 | Supply and fabrication of steel including cost and conveyance of steel and labour charges for cutting, bending and placing in position etc, complete | 5.01 | MT | 87,285 ₹4,37,297.85 | 85,000 ₹4,25,850 Lowest | 89,298.34 ₹4,47,384.68 | 91,056 ₹4,56,190.56 |
| 9.00 | RCC 1:1.5:3 mix, using 20mm ISS, HBG metal including cost and conveyance of material and labour charges for laying, compacting, curing etc, complete. | 41.38 | Cum | 8,678 ₹3,59,095.64 | 8,500 ₹3,51,730 Lowest | 9,205.21 ₹3,80,911.59 | 9,053 ₹3,74,613.14 |
| 10.00 | Brickwork in CM 1:5 mix, using country bricks including cost and conveyance of materials and labour charges etc, complete | 30.99 | Cum | 5,785 ₹1,79,277.15 Lowest | 6,000 ₹1,85,940 | 5,987.34 ₹1,85,547.67 | 6,035 ₹1,87,024.65 |
Tender Value
₹25 L
EMD Value
₹25,000
Closing Date
24 Jun 2026, 3:00 pmClosed
BDO(BP) Karungulam
BDO(BP) Karungulam
Construction of Multipurpose Community Hall at Vadakkukaraseri Village in vadakuukaraseri panchayat in Karungulam Panchayat union of Thoothukudi District Nature calamities 2025-26 Package No.03
2026_RDTN_678514_1
BDO(BP)KGLM Lr.No.A3/417/2026 . Date.26.05.2026
Open Tender
Civil Works - Buildings
Item Rate
120 days
Karungulam union office Seydunganallur
technicalbid
3 documents required · 3 mandatory
₹0
₹25,000
Yes
21 Jul 2026
27 May 2026
24 Jun 2026
27 May 2026
24 Jun 2026
27 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Name of Work: Construction of Multipurpose Community Hall at Vadakkukaraseri Village in vadakuukaraseri panchayat in Karungulam Panchayat union of Thoothukudi District under NATURAL CALAMITIES -2025-26-pakageno-01 | - | - | - | - |
| 2 | Earthwork excavation and depsoiting on banks with an initial lead and lift in Hard soil etc, complte as per SS20B for foundation. | 75.3 | Cum | - | - |
| 3 | Collection and supply of Girtty gravel and filling into the foundation and basement including cost and conveyance of sand and labour charges etc, complete | 10.42 | Cum | - | - |
| 4 | Cement Concrete 1:4:8 mix, using 40mm ISS, HBG metal including cost and conveyance of materals and labour charges for laying, compacting, curing etc, complete. | 12.88 | Cum | - | - |
| 5 | Supply and erection of centering for sides and soffits of concrete works inclduing cost and conveyance of materials and labour charges etc, complete. | - | - | - | - |
| 6 | Below GL | 104.11 | Sqm | - | - |
| 7 | Above GL | 200.79 | Sqm | - | - |
| 8 | Supply and fabrication of steel including cost and conveyance of steel and labour charges for cutting, bending and placing in position etc, complete | 5.01 | MT | - | - |
| 9 | RCC 1:1.5:3 mix, using 20mm ISS, HBG metal including cost and conveyance of material and labour charges for laying, compacting, curing etc, complete. | 41.38 | Cum | - | - |
| 10 | Brickwork in CM 1:5 mix, using country bricks including cost and conveyance of materials and labour charges etc, complete | 30.99 | Cum | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_815190.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.85 MB
Tendernotice_2.pdf
PDF • 0.74 MB
technicalbid.pdf
Tender Documents • 0.72 MB
BOQ_815190.xls
BOQ • 0.25 MB
tendernotice.pdf
Additional Documents • 0.84 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].