| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹48.2 LAccepted-AOC | ₹48.2 L | L1 | Accepted-AOC Consistent as per the ITB in the SBD. |
| 2 | L2₹48.2 L+₹5,439.70 (0.11%)Rejected-Finance | ₹48.2 L+₹5,439.70 (0.11%) | L2 | Rejected-Finance Inconsistent |
| 3 | Rejected-Technical | - | - | Rejected-Technical EMD in physical form not submitted |
Tender Value
₹48.2 L
EMD Value
₹48,233
Closing Date
19 Dec 2022, 12:00 pmClosed
Executive Engineer
2nd floor of the office Building of Directorate of Hr. and Tech. Education, ESS-Sector, Itanagar
C/o Parking Shed at DNGC, Itanagar
2022_ARED_936_1
EDN(EW)/Plg-015/2021/47
Open Tender
Civil Works
Item Rate
240 days
Vivek Vihar
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,500
Divisional Accountant
₹48,233
Itanagar
31 May 2023
9 Dec 2022
19 Dec 2022
9 Dec 2022
19 Dec 2022
9 Dec 2022
12 Dec 2022
Amount
Parking Shed
Earth work in excavation in soils containing 50% or more of shingle or small size boulders upto 30 cm size including banking in20 cm layers and breaking clods, ramming and dressing upfor the purpose of making embankments or filling up ground depressions lead upto 50 m and lift upto 1.50 m
Reinforced concrete work in foundations, footings, bases of columns etc. and mass concrete excluding cost of centring, shuttering and reinforcement in : a) M20 (1 cement : 1.5 coarse sand : 3 stone aggregate 20 mm nominal size).
Reinforcement cement concrete work in columns, pillars, piers, abutments, post and struts etc up to floor two level including finishing and plastering the exposed surface with cement mortar 1 : 3 (1 cement : 3 fine sand) of thickness not exceeding 6 mm to give a smooth and even surface but exluding cost of centring, shuttering and reinforcement. a) M20 (1 cement : 1.5 coarse sand : 3 stone aggregate 20 mm nominal size).
Centring and shuttering including strutting, propping etc and removal of form work for- a) Column, pillars, posts and struts etc.
Reinforcement of RCC work including bending, binding and placing in position complete. b) Tar/TMT steel
Steel work riveted or bolted in built up sections, trusses and framed work including cutting, hoisting, fixing in position and applying a priming coat of red lead paint. b) In Tees, Angles, Flats and Channels
Providing and fixing Dyna roofing with all necessary fitting
Providing and laying cement concrete1:3:6 (1cement:3 coarses and:6 graded stone aggregate 40 mm nominal size) excluding the cost of centring an shuttering in: b) Walls including attached buttresses, pilasters and their caps and bases and string courses etc. up to floor two level.
Providing and laying in foundations and plinth cement concrete 1 : 5 : 10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) excluding the cost of centring and shuttering.
25 mm thick cement concrete flooring 1 : 2 : 4 (1 cement : 2 coarse sand : 4 graded stone aggregate 12.5 mm nominal size) finished with a floating coat of neat cement.
Approach Road
Re-filling excavated earth in foundations and plinth etc. in 15 cm layer including ramming and watering etc. complete.
Consolidation of sub-grade with road roller of 8 to 12 tonne capacity including making good the undulations etc. with earth or quarry spoils etc.and rerolling the sub grade.
Granular Sub-Base with Coarse Graded Material (Table:- 400- 2) (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401)
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)
M/S T.M.M.M.M. ENTERPRISE
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .