Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹82.8 LAccepted-AOC | L1 | Accepted-AOC Lowest Rate | |
| 2 | L2₹83.2 L+₹40,324.74 (0.49%)Rejected-Finance | L2 | Rejected-Finance Highest Rate |
Tender Value
₹83.9 L
EMD Value
₹83,900
Closing Date
2 Feb 2024, 3:00 pmClosed
Additional Collector (Dev)/Project Director
DRDA Office, 2nd Floor, New Collectorate, Thanjavur
Thanjavur District - Package No.08 - Strengthening / Improvements of 11 Road works in Kumbakonam Block under Peri- Urban Panchayats - 2023-2024.
2024_RDTN_409640_1
DIPR.80/Tender/2024
Open Tender
Civil Works - Roads
Item Rate
180 days
Kumbakonam
As per Tender document
9 documents required · 9 mandatory
₹0
₹83,900
DRDA Office, 2nd Floor, New Collectorate, Thanjavu
20 Feb 2024
13 Jan 2024
2 Feb 2024
13 Jan 2024
2 Feb 2024
13 Jan 2024
19 Jan 2024
Amount
Part.01.Upgradation of Kaveri Nagar Extension in Palavaithankattali Panchayat Km 0/0-0/090
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing & laying WBM Grade II to a compacted thickness of 75 mm thick using 1 cum of 63 mm - 11.2 mm IRC size HBG metal with 0.24 cum of US Gravel of blindage per 10 sqm including cost, conveyance charges for all materials , labour charges, stacking charges, spreading charges, hand packing to proper camber, watering with all leads, compacting with 80 to 100 kN power roller including hire & feul charges for power roller and all other tools and plants employed etc complete
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.02.Providing cement concrete Road at Balu Nagar Road in Palavaithankattali Panchayat.
Earth work excavation and depositing on bank with initial lead and lift in all classes of soil except hard rock requiring blasting including all labour charges etc., complete for SS 20B for Foundation
Sand filling with good river sand including cost and conveyance of all materials to site and all labour charges for filling etc.,complete.
Cement Concrete 1:4:8 using 40mm ISS HBG Metal including cost and conveyance of all materials to site and cost of labour and all other incidental charges etc.,complete.
Cement Concrete 1:3:6 using 20mm ISS HBG Metal including cost and conveyance of all materials to site and cost of labour and all other incidental charges etc.,complete.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical
Provission For Bitumen Pad SI No - 32 VP No : -53
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.03.Providing cement concrete Road at Claret Nagar Road in PalavaithankattalAi Panchayat.
Earth work excavation and depositing on bank with initial lead and lift in all classes of soil except hard rock requiring blasting including all labour charges etc., complete for SS 20B for Foundation
Sand filling with good river sand including cost and conveyance of all materials to site and all labour charges for filling etc.,complete.
Cement Concrete 1:4:8 using 40mm ISS HBG Metal including cost and conveyance of all materials to site and cost of labour and all other incidental charges etc.,complete.
Cement Concrete 1:3:6 using 20mm ISS HBG Metal including cost and conveyance of all materials to site and cost of labour and all other incidental charges etc.,complete.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical
Provission For Bitumen Pad SI No - 32 VP No : -53
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.04.Strengthening of UBS Nagar in Palavaithankattalai Panchayat Km 0/0-0/350
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.05.Strengthening of Kamatchi amman koil Bye pass Road in Palavaithankattali Panchayat Km 0/0-0/700
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.06.Strengthening of Karaikkal Road to Mullai Nagar Road in Palavaithankattalai Panchayat Km 0/0-0/190
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.07.Providing cement concrete Road at Pillaiyar Kovil South Bharathy Nagar Road in Palavaithankattali Panchayat.
Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical
Provission For Bitumen Pad SI No - 32 VP No : -53
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.8.Upgradation of Alagappa Nagar Road in Sakkotai Panchayat Km 0/00-0/170
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing & laying WBM Grade II to a compacted thickness of 75 mm thick using 1 cum of 63 mm - 11.2 mm IRC size HBG metal with 0.24 cum of US Gravel of blindage per 10 sqm including cost, conveyance charges for all materials , labour charges, stacking charges, spreading charges, hand packing to proper camber, watering with all leads, compacting with 80 to 100 kN power roller including hire & feul charges for power roller and all other tools and plants employed etc complete
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.9.Strengthening of Ice Factory Road in Sakkotai Panchayat Km 0/00-0/107
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.10.Strengthening of Raja Thottam Road in Sakkotai Panchayat Km 0/00-0/147
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Part.11.Strengthening of Kottai Kuturavu Road in Sakkotai Panchayat Km 0/00-0/325
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing mettaled surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer.
Applying tack coat over WBM surface (not treated with primer) using 4Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates as per special conditions appended herewith including conveyance of bituminous emulsion to actual work spot handling charges including labour charges for brushing, cleaning and preparing the surface for laying the tack coat and labour and machinery charges for applying the required quantity of bituminous emulsion including hire, fuel and running charges for all tools and plants employed for the work including all other incidental charges such as barricading and providing danger lights, flags etc., complete as per standard specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
K MANIKANNAN
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .