| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.9 LAccepted-Finance | ₹5.9 L | L1 | Accepted-Finance approved |
| 2 | L2₹5.9 LRejected-Finance | ₹5.9 L | L2 | Rejected-Finance rejected |
| Sl No | Description | Qty | Unit | BALAMURUGAN PRABU L1 | MANI KANNAN L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc.,as per SS 20 A. TNDSS NO: 23 & 24 VI (S2) VI,VII 9,10 with standard specifications. | 52 | M3 | 197 ₹10,244 | 199 ₹10,348 |
| 2.00 | Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 17 | M3 | 6,255 ₹1.1 L | 6,557 ₹1.1 L |
| 3.00 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) For kerb wall | 254.5 | M2 | 575 ₹1.5 L | 576 ₹1.5 L |
| 4.00 | Plain Cement Concrete 1:2:4mix (One Cement, Two Fine Aggregate and Four Coarse Aggregate) Using 20mm ISS HBG metal including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 38.5 | M3 | 7,688 ₹3.0 L | 7,690 ₹3.0 L |
| 5.00 | Supplying and fabrication of steel and placing in position of TMT steel rods for RCC works as per design given including cost of steel and GI binding wire in all floors etc., complete complying with standard specification in TNDSS NO:97 V,VI (S6) VII (S6), VII-3. | 54 | KG | 92 ₹4,968 | 95 ₹5,130 |
| 6.00 | Reinforced Cement Concrete 1:1½:3 Mix (One Part of cement, one and half Part of M- Sand and three Part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc. Complete with std. Specifications. TNDSS NO: 30 V, VI (S3), VII-3. | 0.9 | M3 | 9,085 ₹8,176.50 | 9,086 ₹8,177.40 |
| 7.00 | Finishing the top of flooring with granothatic flooring with cement concrete 1:2:4 (one cement, two sand and four aggrigate) using 10 to 12mm stone chips – 25mm tk etc., Complete. | 74 | M2 | 191 ₹14,134 | 194 ₹14,356 |
Tender Value
₹7 L
EMD Value
₹7,000
Closing Date
12 Sept 2025, 3:00 pmClosed
Executive Officer
Nattarasankottai Townpanchayat
Construction of SWD theerthakulam near and ward no .8 kavichakravarthi kambar street extension in Nattarasankottai Town panchayat
2025_DTP_601108_2
044/2025/A1
Open Tender
Civil Works
Nattarasankottai Townpanchayat
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹7,000
Yes
16 Dec 2025
6 Sept 2025
12 Sept 2025
6 Sept 2025
12 Sept 2025
6 Sept 2025
Amount
Earth work excavation for foundation and depositing on bank with in the initial lead of 10m and a lift of 2m in hard stiff clay, stiff block cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders etc.,as per SS 20 A. TNDSS NO: 23 & 24 VI (S2) VI,VII 9,10 with standard specifications.
Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28).
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) For kerb wall
Plain Cement Concrete 1:2:4mix (One Cement, Two Fine Aggregate and Four Coarse Aggregate) Using 20mm ISS HBG metal including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28).
Supplying and fabrication of steel and placing in position of TMT steel rods for RCC works as per design given including cost of steel and GI binding wire in all floors etc., complete complying with standard specification in TNDSS NO:97 V,VI (S6) VII (S6), VII-3.
Reinforced Cement Concrete 1:1½:3 Mix (One Part of cement, one and half Part of M- Sand and three Part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc. Complete with std. Specifications. TNDSS NO: 30 V, VI (S3), VII-3.
Finishing the top of flooring with granothatic flooring with cement concrete 1:2:4 (one cement, two sand and four aggrigate) using 10 to 12mm stone chips – 25mm tk etc., Complete.
MANI KANNAN (BID ID -1452825)
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_718552.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid