SPECIAL CONDITIONS OF TENDER
BPCL BAITALPUR DEPOT:-
1. Completion time of this work is 12 months from the date of LOI.
Site Restriction: The entire works are to be carried out in BPCL BAITALPUR
Depot, DEORIA. The contractor will have to follow the timings of BPCL and must
work under restricted conditions & as per availability at the site. The normal
working hour of site is 09.00 Hrs to 17.00 Hrs on Monday to Saturday except
holidays. Working beyond above normal working hours / holidays / Sundays are to
be with prior permission of Engineer in Charge and relevant location officers.
Contractor is required to plan his work within the normal working hours & days
and accordingly he must mobilize the resources to complete the job within the
scheduled time. However, all efforts will be made by BPCL to give extended
working time beyond normal working time of 9.00 to 17.00 hrs to help the
contractor for early completion of the work. No additional payment / charges shall
be payable for such works. Not getting permission for working on holidays /
Sundays or beyond normal working hours will not be considered as reason for
delay in work/extra payment. The contractor and his personnel must obey all rules
and regulations of the plant. Trained and experienced supervisors / engineers are
required to be present at the work spot always. The tenderer must visit the sites
and familiarize him with location, operating /working conditions as well as any
other local factors which could influence the working before quoting for the job.
His quote should take care of any such restrictions; conditions etc and any claim
afterwards will not be entertained. The contractor shall confirm himself fully of the
conditions under which the work is to be executed and shall satisfy himself of all
existing local working conditions, limitations, Central Govt., State Govt. and local
body rules and regulations etc. complete. Vendor shall confirm himself fully of the
conditions under which the work is to be executed and shall satisfy himself of all
existing local working conditions, limitations, Central Govt., State Govt. and local
body rules and regulations etc. complete.
2. Billing: Billing will be done as per joint measurement done by Engineer in Charge
and Vendor. Running account bill shall be raised preferably monthly or on
mutually agreed period. However, running account bills are to be preferably for a
minimum value of 25% for contract value in case of Contract Value less than
Lakhs and 10 % of contract value in case of Contract value more than 50 Lakhs
except for Pre-final and final bills. However, Engineer in charge may release
payment at any stage/ for any value considering the work requirement The
payment will be released by Electronic Fund transfer to Vendor’s bank Account
after necessary deductions like Retention Amount , Income Tax ,WCT etc and
other statutory deductions as applicable and as per GCC.
3. Payment terms shall be as per Standard Payment terms of BPCL.
4. Other conditions:
I. Adherence to fulfillment of the conditions relevant to the Job as stipulated in latest
editions of OISD 192 (SAFETY PRACTICES DURING CONSTRUCTION), OISD
GDN – 105(WORK PERMIT SYSTEM) , OISD 207 (CONTRACTOR SAFETY ) by
the contractor. The conditions have though been elaborated in the General
Conditions of Tender, however the conditions of above referred OISD std. will
supersede in case of any inadequacy.
Contractor shall compulsorily impart training as per OISD 154 to all its
employees to be deployed at site before start of job
Confined space entry should have valid permit.
Job safety plan should be prepared by contractor & approved by BPCL.
Contractor supervisor should be selected who possesses job knowledge and
ii. The party should provide all workmen with necessary boiler suit, yellow color
safety helmets, safety harnesses, safety shoes and other standard safety
equipments irrespective of nature of job. Provision of necessary safety
equipments for working at height shall be in vendor’s scope of work. No extra
payment shall be made for this. Any delay on account of nonadherence to safety
norms, rules and regulations of plant as well as obtaining work permits from the
plant shall not be accounted for the delay in completion of job.
iii. Electricity, potable water required for construction must be arranged by the vendor
at his own cost. Also, water storage arrangement shall be made by vendor at
BPCL designated place only.
iv. Vendor should comply with all rules and regulations as per EPF/ESIC, minimum
wages act, workmens compensation act, Labour laws (Central) and other statutory
regulations etc. complete as applicable. He should produce and submit necessary
documents as proof of compliance.
v. All the parts like the tender schedule, Technical Specification, Special Conditions
of Tender, General Conditions of tender etc are to be read together and shall be
supplementary to each other. In case of any contradiction between provision of
GCC and SCC, provisions in SCC shall overrule that in GCC only to the extent of
contradiction. Similarly in case of any contradiction between provisions in
Technical specification and SCC, provisions in SCC will overrule that in Technical
Specification only to the extent of contradiction. SCC and Technical specification
are supplementary to Schedule. Hence in case of any contradiction to schedule,
the same has to be brought to the notice of Engineer in Charge and his decision
shall be final and will be binding on vendor. No claim will be entertained on account
of any such changes.
vii. Engineer –in-charge shall have right to take possession of or use any completed or
partially completed work or part of work. Such possession or use shall not be
deemed to be an acceptance of any work completed in accordance with the
Contract Agreement.
viii. Site clearance- Vendor has to clear all unwanted materials, equipments etc to be
cleared off immediately from site. He is required to get necessary clearance for
Engineer in charge of ‘having cleared the site satisfactorily’ before submission of
5. Receipt & storage of material at Site: Vendor is required to make his own
arrangement for unloading and storage of materials at site. Vendor is required
to inform BPCL prior to dispatch of materials and his representative is required to
be available for receipt and unloading of materials at site. Security / safety &
safekeeping of material, supplied by vendor, will remain sole responsibility of
vendor till entire completed facility is handed over to BPCL by vendor.
6. Contractors Scope of Supply of Materials: Contractor shall supply at their cost
all materials required for completing the job as per schedule of quantity and
specifications and conditions. All materials supplied by contractor shall be as per
the relevant IS code / mfg. Recommendation, BPCL standard and as advised by
the Engineer in Charge. Technical specification of items to be supplied by
contractor need to be attached with the offer.
7. QC & QAP: All materials are to be as per specification and as directed by
Engineer in charge. Necessary tests are to be carried out and recorded as per the
approved QAP and shall be available at site at all times for inspection. The rates
offered shall be inclusive of charges for all such tests.
8. The successful vendor has to arrange and submit to plant the proper POLICE
VERIFICATION DOCUMENTS of all the labors, site in charges, supervisors,
welders, grinders, civil workmen and all associated workmen who will be coming
inside the installation for carrying out related jobs. Delay because of
noncompliance of police verification shall be accounted on the part of vendor.
9. For carrying out the jobs inside the plant the vendor has to arrange for electricity
(sufficient nos. of acoustic DG sets only along with their valid fitness certificate),
working water, associated tools, tackles, manpower, machinery of his own and no
extra payment will be made to vendor on account of the same.
10. For arranging the electricity, vendor to note that only Acoustic Proof, box type DG
sets will be allowed inside the plant premises. Vendor to also note that proper GI
plate type earthing system as per IS 3043 (LATEST) must be provided by the
vendor for DG set and no extra payment will be done for the same. There should
be two nos. earthing system connected in a grid at a location as instructed by
BPCL site in-charge
11. All the scrap, cut pieces, pipeline etc coming out of work area cleaning will have to
be shifted by the vendor to a location inside or outside the plant premises as per
the instruction of BPCL site in-charge and no extra payment will be done for the
12. Contact Persons:
SR NAME OF ADDRESS OF LOCATION CONTACT
1 BPCL BHARAT PETROLEUM Mr. VINAY KUMAR
BAITALPUR OIL CORPORATION LIMITED, MEENA
DEPOT, BAITALPUR OIL DEPOT,
DEORIA, U.P.- DEORIA, U.P.-274201
274201 (UTTAR PRADESH) Mr. DEEPAK RAJ
Mr. ROBIN TIRKEY
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
14035.pdf
pdf • 0.59 MB
BUDGETDOC_14035.pdf
pdf • 0.73 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .