Deputy Chief Engineer
Operation Circle, HPSEBL Una
Tender for providing 11 KV HT Line to proposed 11 0.4 KV 100 KVA substation for SOP to 1 x 30 HP motor connection of Tubewell of Jal Shakti Vibhag at village Harwal (Lower Gondpur Banehra) under ESD HPSEBL Daulatpur Chowk. (T.S. No. 10 202627)
2026_HPSEB_138253_1
OCU/01/2026-27
Open Tender
Electrical Works
Village Harwal ED Gagret
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,180
₹17,919
6 Jul 2026
6 Jul 2026
14 Jul 2026
6 Jul 2026
13 Jul 2026
6 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | ERECTION PART of New 11 kV HT line | - | - | - | - |
| 2 | Erection of S.T Single Pole 9 Mtr. Long :- Digging of Pit, fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect. | 8 | No. | 6,033.34 | ₹48,266.72 |
| 3 | Erection of S.T Double pole Pole 9 Mtr. Long :- Digging of Pit, fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect. | 2 | Set | 12,628.36 | ₹25,256.72 |
| 4 | Erection of S.T Double pole Pole 11 Mtr. Long :- Digging of Pit, fixing of insulator, disc and drilling of holes in X-Arm , Bracing Set, Top Clamp, erection of pole, fixing of barbed wire and danger plate, filling of Pit, Alluminium Paint and ramming & painting of poles complete in all respect. | 1 | No. | 6,033.34 | ₹6,033.34 |
| 5 | Erection of HT Earthing Set.:- Fixing of earthing pipe of pit for coal earthing, fixing of G.I wire to system filling of pit and remaning work complete in all respect. | 9 | Nos | 1,780.62 | ₹16,025.58 |
| 6 | Erection of Stay Set HT:- Digging of Pit fixing of Stay Rod, filling of Pit, Nozeiling & Tightning complete in all respect. | 15 | Set | 2,338.76 | ₹35,081.4 |
| 7 | Stringing and sagging conductor:- Laying of conductor (ACSR 7/4.26 mm 100 mm²) stringing and sagging, binding with insulator complete in all respect. | 2.3 | P/w / P/Kms | 24,731.62 | ₹56,956.92 |
| 8 | Erection Part of 11/0.4 KV, 100KVA Transformer & bus Bar Str. | - | - | - | - |
| 9 | Erection of 11/0.4 KV , 100 KVA S/Stn :- Digging of Pit, Drilling of Holes In X Arms, Preparation of Platform Structure (Members Ci, Ai I.E. X0Arm & Knee Bracing Set), Erection of D Pole, Concreting 1:1.5:3 (1 cement : 1.5 coarse sand): 3 graded stone aggregate 20 mm nominal size), Erection of Platform, Erection of X0Arms, Drop0Out, Erection of 2 Nos Stay Set, Erection of Jumper, Digging of pit, Fixing of earth rod, clamp, earth wire and connecting to the structure, Earthing for 3 Nos Earths, Providing Charcoal and Salt for the earthing, Filling of the pit with material, Providing Earthing Conn. To G.O Switch, Lightning Arrestor Etc.& Poles, Providing earthting to the Transformer, LT Box, Meter Box etc, Barbed Wire & Painting. and Erection of 100 kVA Transformer, LT Box, MCCB Switch, Cable, service Cable and Energy Meter. Providing earthing connection to Transformer as per REC Board Standard complete in all respect , includes lifting, loading, unloading, all misc work required to complete the work in all respect. | 1 | No. | 77,052 | ₹77,052 |
| 10 | Erection for underneath DTR Structure:- Digging of Pit, Drilling of Holes In X Arms, Preparation of Platform Structure (Members Ci, Ai I.E. X0Arm & Knee Bracing Set), Erection of D Pole, Concreting 1:1.5:3 (1 cement : 1.5 coarse sand): 3 graded stone aggregate 20 mm nominal size), Erection of Platform, Erection of X0Arms, Erection of 2 Nos Stay Set, Erection of Jumper, Digging of pit, Fixing of earth rod, clamp, earth wire and connecting to the structure, Earthing for 3 Nos Earths, Providing Charcoal and Salt for the earthing, Filling of the pit with material, Providing Earthing Conn. To G.O Switch, Lightning Arrestor Etc.& Poles, Barbed Wire & Painting, includes lifting, loading, unloading, all misc work required to complete the work in all respect. | 1 | No. | 56,640 | ₹56,640 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.67 MB
Tendernotice_2.pdf
PDF • 2.34 MB
Tendernotice_3.pdf
PDF • 1.55 MB
Tendernotice_4.pdf
PDF • 4.07 MB
BOQ_204763.xls
BOQ • 0.44 MB
Download all tender documents and submit your bid