Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹92.1 L
EMD Value
₹1.8 L
Closing Date
21 Oct 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Superintending Engineer
SE CMU office NITW
Proposed Rate Contract for Routine Maintenance Works for Hostel areas for a period of twelve months in which the tasks will be performed on a piece-meal basis as and when required throughout the duration of the agreement at NIT Warangal
2026_NITW_928301_1
17/NITW/CMUNIT/CIVIL/26-27
Open Tender
Civil Works
Works
365 days
NIT WARANGAL
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,180
The Director
₹1.8 L
30 Sept 2026
30 Sept 2026
22 Oct 2026
30 Sept 2026
21 Oct 2026
30 Sept 2026
30 Sept 2026 - 7 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge: All kinds of soil | 200 | sqm | 126.34 | ₹25,268 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge. All kinds of soil | 200 | cum | 172.71 | ₹34,542 |
| 3 | Surface dressing of the ground including removing vegetation and inequalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m. All kinds of soil | 500 | sqm | 33.23 | ₹16,615 |
| 4 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar | 10 | cum | 2,004.57 | ₹20,045.7 |
| 5 | Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge 50mm average thickness | 200 | sqm | 249.43 | ₹49,886 |
| 6 | Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge 25mmaveragethickness | 200 | sqm | 123.33 | ₹24,666 |
| 7 | Providing, mixing and applying bonding coat of approved adhesive on chipped portion of RCC as per specifications and direction of Engineer-In-charge complete in all respect. SBR Polymer (@10% of cement weight) modified cementitious bond coat @ 2.2 kg cement per sqm of surface area mixed with specified proportion of approved polymer | 200 | sqm | 137.39 | ₹27,478 |
| 8 | Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. 12 mm average thickness | 300 | sqm | 378.16 | ₹1,13,448 |
| 9 | Providing, mixing and applying SBR polymer (of approved make) modified Cement mortar in proportion of 1:4 (1 cement: 4 graded coarse sand with polymer minimum 2% by wt. of cement used) as per specifications and directions of Engineer-in-charge. 25 mm average thicknessin2 layers. | 300 | sqm | 571.49 | ₹1,71,447 |
| 10 | Dismantling doors, windows and clerestory windows (steel or wood) shutter including chowkhats, architrave, holdfasts etc. complete and stacking within 50 metres lead. Of area 3 sq. metres and below. | 30 | Each | 357.29 | ₹10,718.7 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.76 MB
Tendernotice_2.pdf
PDF • 0.13 MB
tenderdocratecontractforhostels.pdf
Tender Documents • 0.74 MB
niet.pdf
Additional Documents • 0.11 MB
BOQ_975553.xls
BOQ • 0.54 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .