| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.0 LAccepted-AOC | ₹16.0 L | L1 | Accepted-AOC ok |
| 2 | L2₹16.1 LRejected-AOC | ₹16.1 L | L2 | Rejected-AOC raject |
| Sl No | Description | Qty | Unit | M/S. BKS INFRAS L1 | M/S. GPS BUILDEERS L2 |
|---|---|---|---|---|---|
| 1.001.Providing CC road at Amirtha nagar in Nadukuthagai Panchayat | |||||
| 2.00 | Earth work excavasion in all soil includind all cost and conveancy charges | 18.9 | cum | 140 ₹2,646 Lowest | 150 ₹2,835 |
| 3.00 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 | 86.36 | ` | 2,874 ₹2,48,199 Lowest | 2,900 ₹2,50,444 |
| 4.00 | Cement Concrete 1:4:8 using 40mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 81.69 | cum | 5,984 ₹4,88,833 Lowest | 6,000 ₹4,90,140 |
| 5.00 | Cement Concrete 1:3:6 using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 33.81 | cum | 6,245 ₹2,11,143 Lowest | 6,245 ₹2,11,143 Lowest |
| 6.00 | Cement Concrete 1:2:4 using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 51.82 | cum | 6,785 ₹3,51,599 Lowest | 6,785 ₹3,51,599 Lowest |
| 7.00 | Cost towards supply centering with planks including all cost and conveyance charges | 294 | sqm | 176 ₹51,744 Lowest | 176 ₹51,744 Lowest |
| 8.00 | Supply of Bitumen pads including cost and conveyance of all materials to site and all labour charges etc. complete. | 12.95 | sqm | 250 ₹3,238 Lowest | 250 ₹3,238 Lowest |
| 9.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | GST Amount | 2,44,332.36 ₹2,44,332.36 Lowest | 2,45,005.74 ₹2,45,005.74 |
Tender Value
₹16.1 L
EMD Value
₹17,000
Closing Date
9 Mar 2026, 3:00 pmClosed
Block development Office VP
Poonamallee union
Providing CC road at Amurtha nagar in Nadukuthagai Panchayat
2026_RDTN_671228_1
14th Finance 01
Open Tender
Civil Works
Works
Poonamallee
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹17,000
Yes
Block development Office VP
6 Aug 2026
6 Mar 2026
9 Mar 2026
6 Mar 2026
9 Mar 2026
6 Mar 2026
6 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | 1.Providing CC road at Amirtha nagar in Nadukuthagai Panchayat | - | - | - | - |
| 2 | Earth work excavasion in all soil includind all cost and conveancy charges | 18.9 | cum | 131.89 | ₹2,492.72 |
| 3 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401 | 86.36 | ` | 2,900.96 | ₹2,50,526.91 |
| 4 | Cement Concrete 1:4:8 using 40mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 81.69 | cum | 5,810.88 | ₹4,74,690.79 |
| 5 | Cement Concrete 1:3:6 using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 33.81 | cum | 5,712.55 | ₹1,93,141.32 |
| 6 | Cement Concrete 1:2:4 using 20mm HBG metal including cost and conveyance of all materials to site and all labour charges etc. complete | 51.82 | cum | 7,121 | ₹3,69,010.22 |
| 7 | Cost towards supply centering with planks including all cost and conveyance charges | 294 | sqm | 136.88 | ₹40,242.72 |
| 8 | Supply of Bitumen pads including cost and conveyance of all materials to site and all labour charges etc. complete. | 12.95 | sqm | 234.3 | ₹3,034.19 |
| 9 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | GST Amount | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_806684.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.77 MB
Tenderdocument.pdf
Tender Documents • 0.94 MB
BOQ_806684.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].