| 1 | L1₹31.7 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹34.2 L+₹2.5 L (7.81%)Rejected-AOC PERAMBALUR | TAMIL NADU | 621101 | L2 | Rejected-AOC L2 |
Tender Value
₹31.7 L
EMD Value
₹33,000
Closing Date
4 May 2023, 3:00 pmClosed
Project Director
Collectorate DRDA Perambalur
Renewal and 5 year Maintenance of the Road from Anukkur BT road to Vadakkumadavi road KM 0/0-1/600 under MGSMT 2022-2023 in Perambalur Block of Perambalur District Package No.TN11-12
2023_RDTN_303624_1
DIPR/2142/TENDER/2023
Open Tender
Civil Works - Roads
Item Rate
180 days
DRDA
As per Tender Document
4 documents required · 4 mandatory
₹0
₹33,000
DRDA,Perambalur
12 Jul 2023
18 Apr 2023
4 May 2023
18 Apr 2023
4 May 2023
25 Apr 2023
25 Apr 2023
Amount
Clearing the Scrub jungle including all labour charges for burrying and burning etc.,KM0/0-1/600
Earth work excavation depositing on bank with initial lead of 0 metre and lift of 2 metre as per SS20A including breaking cods, sectioning ,ramming etc complete as directed by the departmental officers for formation (SI.No.60/P16) KM 0/000 - 1/600
Collection and supply of Stone Dust from approved quarry an average 1KM Mixed with existing earth including cost and conveyance of all materials to site all labour charges etc KM 0/0-1/0
Providing and laying TACK COAT using Rapid Setting bitumen grade Grade I at the rate of 3.00kg/10sqm over the Prime coat preparatory to another bituminous construction over it as per MORT& H Specifications No 503 KM 0/000 - 1/600.
Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 KM 0/000 - 1/600.(USING PLASTIC WASTE)
Provision for KM Stone etc complete
Provision for HM Stoneetc complete
Road Marking with Hot Applied thermoplastic compound with reflectorising Glass beeds on bituminous surface providing and laying of hot applied thermoplastic compound 2.5mm thick including reflecctorising Glass beeds at 250gms per sqm area ,thickness of 2.50mm is exclusive of surface applied glass beeds as per IRC 35 . The finished surface to level uniform and free from streeks and holes extra complete as per MORTH specification no 803.KM 0/000 - 0/610
Provision for Name Board Cum Citizen Board
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
PANNEERSELVAM
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .