Construction of Missing Link/ Non Patchable Road under Package No RJ-15-15/ML-NP/2026-27 (PWD DN Pilibanga) District Hanumangarh
2026_CEPWD_586065_1
SE/PWD/HMH/NIT11/2026-27
Open Tender
Civil Works
Percentage
EE PWD Pilibanga
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,000
EE PWD Pilibanga
₹7.5 L
Yes
SE PWD HMH
12 Aug 2026
12 Aug 2026
1 Sept 2026
12 Aug 2026
31 Aug 2026
12 Aug 2026
19 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Renewal of Road from Hardaswali to Dhandhusar Road km 5/500 to 11/500 | |||||
| 1.01 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 100 m, stacking serviceable and unserviceable materials separately as per MoRTH Specification Clause 202 By Mechanical Means Bituminous Courses & Grade improvement | 107.1 | Cum | 69 | ₹7,389.9 |
| 1.02 | Clearing and Grubbing Road Land.Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MoRTH Specification Clause 201.By Mechanical Means.In area of non-thorny jungle: for shoulder jungle clearance | 1.14 | Hect | 10,374 | ₹11,826.36 |
| 1.03 | Construction of embankment with approved materials deposited at site obtained from roadway cutting and excavation from drain and foundation or other structures graded and compacted to meet requirement of Tables 300-1 and 300-2 as per MoRTH Specification Clause 305.3 : Filling in outer part of Formation( Shoulder) | 2,856 | Cum | 33 | ₹94,248 |
| 1.04 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per MoRTH Specification Clause 301.3 | 2,856 | Cum | 25 | ₹71,400 |
| 1.05 | Providing laying spreading and compacting specified graded sand, gravel (crushed stone) as per Table 400-1,400-2 or any other course material as per design mix, as per CBR in sub base course including premixing the material at OMC in wet mix plant, carriage of mixed material spreading in uniform layers with motor grader F.E loader on a prepared base and compacting with vibratory roller to achieve desired density (as per I.S.2720) including all material, labor, machinery, lighting guarding, barricading and maintenance of diversion complete.[MoRTH specification : Clause 401]. By mechanical means.For Grading-VI Material : Grading improvement and Interlocking portion | 267.75 | Cum | 1,401 | ₹3,75,117.75 |
| 1.06 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401.For Grading III Material for Hard shoulder | 1,008 | Cum | 954 | ₹9,61,632 |
| 1.07 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening & binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 1 as per MoRTH Specification Clause 404.Using Crusher Broken Aggregate By Manual Mean : Grade improvement | 172.13 | Cum | 1,668 | ₹2,87,112.84 |
| 1.08 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per MoRTH Specification Clause 404. using Crusher borken aggregate By Manual Means : Grading improvement and Interlocking portion | 258.19 | Cum | 1,761 | ₹4,54,672.59 |
| 1.09 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base(WBM/WMM) including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per MoRTH Specification Clause 502 : Grade improvement | 2,677.5 | Sqm | 28 | ₹74,970 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.33 MB
Doc15-15.pdf
Tender Documents • 17.73 MB
BOQ_1041035.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].