Tender Value
₹32.0 L
Closing Date
27 Dec 2021, 3:00 pmClosed
Chief Engineer, NRG
Office of Director NRG, WIP PB, BARC, Trombay, Mumbai 400 085
Procurement of raw material, fabrication inspection, testing and installation of SS 304L lining for different areas of ASWTF, Trombay
2021_BARC_660169_1
TDD/ASWTF/MECH/21/01/14361
Open Tender
Machineries/ Mechanical Engg Items
Works
210 days
ASWTF, BARC, Trombay, Mumbai
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
Exempted
TDD Conferance Room
22 Jun 2022
30 Nov 2021
29 Dec 2021
30 Nov 2021
27 Dec 2021
16 Dec 2021
30 Nov 2021 - 9 Dec 2021
10 Dec 2021
Amount
SS 304L Lining : Procurement of all material (other than FIM) including welding consumables, identification of all materials (FIM), taking delivery & transportation from storage point to work site, cleaning of all materials,fabrication , inspection, testing, erection for SS 304L 3 mm thick sheet lining of floor, wall, corner areas, sump etc., including inspection of walls,flooring and other areas to be lined for finish, chipping concrete surface, leveling, drying of surfaces to be lined, dimensional measurement, preperation of fabrication drawing prior to fabrication, forming, bending, shearing/cutting, edge preparation, grinding, erection of liner on Eps provided, complete welding by GTAW, inspection, testing (root & final DP, subsequently Vacuum Box Testing etc.) , removal & disposal of all temporary structures ,cleats , cleaning of liner surface, preparation & submission of all documents & as built drawings in soft (CD in pdf format) & hard copy etc. , as per technical specification and drawings.
CS Support & structures : Procurement of all material including welding consumables, fabrication, installation, inspection, testing, for structural supports made of Carbon steel Channel ISMC 100 and other CS supporting material. The job involves inspection of concrete surface, chipping, leveling, drying of surfaces, cleaning, preperation of fabrication drawing prior to fabrication, forming, bending, cutting, edge preparation, fabrication of box section from channels by full welding along the length, placing, installation of box section on Eps by welding, anchoring, fabrication and installation of other structures, EP plates, using CS anchor fasterners (wherever required), complete welding, inspection, testing ,painting of structure with two coat of epoxy primer and epoxy paint, removal & disposal of all temporary structures, cleats etc., as per technical specification and drawings.
Dismantling of structures : Dismantling of existing SS/MS/RCC structures by breaking, cutting, grinding, gas cutting, removal of cut members, handling, shifting to temporary area identified by EIC, cleaning of area, final shifting of scrap/debris for disposal to distance upto 2 KM by making vehicle arrangement and material handling equipments.
MULTITECH ENGINEERS
PLANT ENGINEERING PEOPLE
B.A.Engineers & Contractors
Jai Laxmi Enterprises
SSG ENTERPRISES
MRR ENGINEERS
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .