| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.6 CrAccepted-AOC CITY CHOWK RAJOURI JAMMU KASHMIR 185131 | RAJOURI | RAJOURI | JAMMU AND KASHMIR | 185131 | ₹13.6 Cr | L1 | Accepted-AOC Accepted |
| 2 | L2₹16.9 Cr+₹3.3 Cr (24.0%)Rejected-Finance LANE NO 3 UMERABAD NEAR CITY HOSPITAL BATHINDI JAMMU | JAMMU | JAMMU AND KASHMIR | 180001 | ₹16.9 Cr+₹3.3 Cr (24.0%) | L2 | Rejected-Finance REJECTED |
| 3 | L3₹16.9 Cr+₹3.3 Cr (24.0%)Rejected-Finance | ₹16.9 Cr+₹3.3 Cr (24.0%) | L3 | Rejected-Finance REJECTED |
Tender Value
₹19.7 Cr
EMD Value
₹39.3 L
Closing Date
25 Aug 2025, 5:00 pmClosed
Chief Engineer PMGSY (JKRRDA) Jammu
Office of The Chief Engineer PMGSY(JKRRDA) Jammu at 1st Floor, Mechanical Engineering Department (MED) Complex University Road Jammu
Construction and Maintenance of Road from L021-(Link Road) Buffliaz Mughal Road Km 7.700 to U Akhlor Patti, Package No. JK11-4034, PMGSY-IV, Batch-I of 2025-26, Block-Bufliaz, District Poonch. Length-7.000 Kms
2025_JKRRD_143679_1
JK114034
Open Tender
Civil Works - Roads
Percentage
540 days
Bufliaz
Please refer Tender documents.
8 documents required · 8 mandatory
₹20,000
₹39.3 L
Office of The Chief Engineer PMGSY (JKRRDA) Jammu
1 Apr 2026
4 Aug 2025
27 Aug 2025
4 Aug 2025
25 Aug 2025
6 Aug 2025
5 Aug 2025 - 6 Aug 2025
5 Aug 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth Work in Hilly Roads:- Excavation in all kinds of soil, Soft Rock & Hard Rock, by mechanical means including cutting and trimming of side slopes & disposing of Excavated earth with all lift and leads as directed for safe disposal of un-serviceable/surplus excavated material without damaging private/public property As per Technical specification clause 1603.1. and 1603.2 . | 1,60,049.11 | Cum | 222.42 | ₹3,55,98,123.05 |
| 2 | Excavation for Structures:- Earthwork in excavation for structures in all kinds of soil, soft and hard rock as per drawings and Technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposing of surplus, un-serviceable Excavated earth as directed at site for safe disposal of same without damaging private/public property, dressing of sides and bottom and backfilling in trenches with excavated suitable material including de watering if required. | 9,127.42 | Cum | 605.45 | ₹55,26,196.44 |
| 3 | Providing and laying of plain cement concrete of Grade M-10 in open foundations complete as per drawings and Technical specifications. Clause 802, 803, 1202 & 1203. including all leads, lifts and carriages of materials by MT complete. | 804.06 | Cum | 5,577.23 | ₹44,84,427.55 |
| 4 | Providing and laying of plain cement concrete of Grade M-15 in Foundation complete as per drawings & Technical specification Clauses 802, 804, 805, 806, 807, 1202 & 1204. Including cost of curing and form work, all leads, lifts and carriages of materials by MT complete. | 901.13 | Cum | 5,759.02 | ₹51,89,625.69 |
| 5 | Providing and laying of plain cement concrete of Grade M-15 in substructure complete as per drawings & Technical specification Clauses 802, 804, 805, 806, 807, 1202 & 1204. Including cost of curing and form work, all leads, lifts and carriages of materials by MT complete. | 875.29 | Cum | 6,159.36 | ₹53,91,226.21 |
| 6 | Providing and laying of plain Cement concrete of Grade M-20 in foundations complete as per drawings & Technical specification Clauses 802, 804, 805,806, 807, 1202 & 1204. Including cost of curing, form work , all leads, lifts and carriages of materials by MT complete. | 120.49 | Cum | 6,361.24 | ₹7,66,465.81 |
| 7 | Providing and laying of plain Cement concrete of Grade M-20 in Sub-Structure complete as per drawings & Technical specification Clauses 802, 804, 805,806, 807, 1202 & 1204. Including cost of curing, form work , all leads, lifts and carriages of materials by MT complete. | 104.75 | Cum | 6,802.92 | ₹7,12,605.87 |
| 8 | Providing and laying reinforced cement concrete of Grade M-25 in Foundation complete as per drawings & Technical specification Clauses 802, 804, 805, 806, 807, 1202, 1204, 1205.4 & 1205.5 . Including cost of curing ,and form work , all leads, lifts and carriages of materials by MT complete. | 1 | Cum | 7,145 | ₹7,137.86 |
| 9 | Providing and laying reinforced cement concrete of Grade M-25 in super structures complete as per drawings & Technical specification Clauses 802, 804, 805, 806, 807, 1202, 1204, 1205.4 & 1205.5 . Including cost of curing ,and form work , all leads, lifts and carriages of materials by MT complete. | 128.1 | Cum | 7,994.74 | ₹10,24,126.19 |
| 10 | Supplying , fitting and placing of HYSD bar reinforcement (Fe450 or above) for RCC work in foundation including bending, binding complete as per drawings & Technical specification Clauses 1002, 1005, 1010 and 1202 including cost of binding wire and also including, all leads , lifts, handling & re-handling and carriage of materials by MT complete. | - | MT | 92,094.29 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 9.23 MB
BOQ_222889.xls
BOQ • 0.26 MB
37BufliazMughalroadtoUAkhlorPatti.pdf
Tender Documents • 1.93 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .