| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹49.0 LAccepted-AOC 6 14 ADAIKALAPURAM VANNIKONENTHAL MANUR TALUK TIRUNELVELI DISTRICT | TIRUNELVELI | TAMIL NADU | 627001 | ₹49.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹49.5 LRejected-Finance | ₹49.5 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | PALRAJ CONTRACTOR L1 | MR.S. GANESHMOORTHI L2 |
|---|---|---|---|---|---|
| 1.001) Construction of Retaining wall at Achampatty Mangammal salai in Achampatty panchayat in Manur Panchayat union. | |||||
| 2.00 | EARTHWORK EXCAVATION for foundation in hard soil and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed.(Hard Soil ) For core wall | 191.7 | Cum | 263.78 ₹50,566.63 | 266.42 ₹51,072.71 |
| 3.00 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete | 47.93 | Cum | 5,233.4 ₹2.5 L | 5,285.73 ₹2.5 L |
| 4.00 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. Up to Basement | 575.1 | Sqm | 547 ₹3.1 L | 552.98 ₹3.2 L |
| 5.00 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete | 265.98 | Cum | 5,503.4 ₹14.6 L | 5,558.43 ₹14.8 L |
| 6.002) Construction of Retaining wall at Moovirunthali to Paneeroothu road in Sundankurichi Panchayat of Manur Panchayat Union | |||||
| 7.00 | EARTHWORK EXCAVATION for foundation in hard soil and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed.(Hard Soil ) For core wall | 188.1 | Cum | 263.78 ₹49,617.02 | 266.42 ₹50,113.60 |
| 8.00 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete | 47.03 | Cum | 5,344.82 ₹2.5 L | 5,398.27 ₹2.5 L |
| 9.00 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. Up to Basement | 564.3 | Sqm | 547 ₹3.1 L | 552.98 ₹3.1 L |
| 10.00 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete | 260.99 | Cum | 5,614.82 ₹14.7 L | 5,670.97 ₹14.8 L |
Tender Value
₹49.7 L
EMD Value
₹50,000
Closing Date
5 Feb 2026, 3:00 pmClosed
Project Director
DRDA, Tirunelveli
Construction of Retaining wall 2 nos in Achampatty and Sundankurichi panchayat
2026_RDTN_648368_2
A10/3938216/2025
Open Tender
Civil Works
90 days
Tirunelveli District
As per pre-qualification
5 documents required · 5 mandatory
₹0
₹50,000
11 May 2026
29 Jan 2026
5 Feb 2026
29 Jan 2026
5 Feb 2026
30 Jan 2026
1) Construction of Retaining wall at Achampatty Mangammal salai in Achampatty panchayat in Manur Panchayat union.
EARTHWORK EXCAVATION for foundation in hard soil and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed.(Hard Soil ) For core wall
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. Up to Basement
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete
2) Construction of Retaining wall at Moovirunthali to Paneeroothu road in Sundankurichi Panchayat of Manur Panchayat Union
EARTHWORK EXCAVATION for foundation in hard soil and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed.(Hard Soil ) For core wall
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete
Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. Up to Basement
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing ,laying, compacting and curing etc complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.72 MB
BOQ_777351.xls
BOQ • 0.33 MB
Technicalbid02.pdf
Tender Documents • 0.47 MB
Pricebid02.pdf
Additional Documents • 0.47 MB
Download all tender documents and submit your bid