| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 CrAccepted-AOC NO 15 II CROSS THILAGAR NAGAR PUDUCHERRY 605 009 | PONDICHERRY | PUDUCHERRY | 605009 | ₹2.4 Cr | L1 | Accepted-AOC Lowest |
| 2 | L2₹2.5 Cr+₹9.5 L (4.02%)Rejected-Finance | ₹2.5 Cr+₹9.5 L (4.02%) | L2 | Rejected-Finance Not Lowest |
| 3 | L3₹2.6 Cr+₹19.1 L (8.10%)Rejected-Finance NO 14 PILLAIYAR KOIL STREET KURUMAMPET PUDUCHERRY 605 009 | PUDUCHERRY | PUDUCHERRY | PUDUCHERRY | 605009 | ₹2.6 Cr+₹19.1 L (8.10%) | L3 | Rejected-Finance Not Lowest |
| 4 | L4₹2.6 Cr+₹20.4 L (8.63%)Rejected-Finance NO 12 13 6TH CROSS STREET THIRU NAGAR MOOLAKULAM PUDUCHERRY 605 010 | PUDUCHERRY | PUDUCHERRY | PUDUCHERRY | 605010 | ₹2.6 Cr+₹20.4 L (8.63%) | L4 | Rejected-Finance Not Lowest |
Tender Value
₹2.3 Cr
EMD Value
₹4.5 L
Closing Date
13 Jun 2022, 4:00 pmClosed
The Executive Engineer, ID., PWD., Puducherry.
O/o The Executive Engineer, ID., PWD., Puducherry.
Package 7. Sub work. 4 Construction of RCC box culvert across Pallavoikkal between new Bye pass P.97 and P.98 Railway culvert Near Olandai Tank, Puducherry.
2022_PWDC2_10398_1
12/PW/IRRN/2022-2023
Open Tender
Civil Works
Item Rate
150 days
Puducherry
Please Refer Tender Documents
3 documents required · 3 mandatory
₹1,575
₹4.5 L
12 Aug 2022
31 May 2022
14 Jun 2022
31 May 2022
13 Jun 2022
31 May 2022
Amount
Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead - nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
Earth work in excavation by mechanical means (Hydraulic excavation) / manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as 10sqm on plan) including pumping out any type of water or liquid mud due to stagnation /flowing/seepage and also working in unhygenic and in or under foul / slush condition in or under water and / or liquid mud including getting out and disposal of excavated earth, slush / mud all leads upto 50m and lift upto 1.5m depth below or above ground level / Bed level etc., - complete all as directed by the Engineer-in-charge. - All kinds of soil.
Extra for every additional lift of 1.5m or part there of in excavation / banking excavated or stacked materials - all kinds of soil
Supplying and filling with quary dust in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth consolidating each deposited layers by ramming and watering etc. complete. The rate includes all lead and lift, pumping out any type of water or liquid mud due to stagnation /flowing/seepage and also working in or under foul/slush condition in or under water and / or liquid mud etc., complete all as directed by the Engineer-in-charge
Extra for providing and mixing ordinary portland cement 43 grade of approved brand and manufacture in quarry rubbish/ stone dust at the rate of 3 bags of cement per cum of quarry rubbish / stone dust mixing in a mechanical mixer. The rate is inclusive of all lead and lift etc., complete all as directed by the Engineer in charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40mm nominal size)
Reinforced Cement Concrete in open foundation complete as per drawing and technical specifications - RCC Grade M35 with a minimum cement content of 422 kg / cum - Using Concrete Mixer and electric gen set including the cost of labour, material, formwork and overhead charges.
Reinforced Cement Concrete in substructure complete as per drawing and technical specification -RCC Grade M35 with a minimum cement content 422 kg / cum for height upto 5m - Using concrete mixer (Formwork-10%).
Steel reinforcement for R.C.C. works including bending, binding and placing in position - Thermo Mechanical Treated Bars (TISCON / VIZAG / IISCO / SAIL/JSW) Fe - 415 or more
Making of bundwall with HDPE cement bags filled with stone dust/quary rubbish for discharge regulation, breach closing/diversion arrangement. The rate includes head load the cost of empty HDPE bags, cost of stone dust, labour charges for filling the bags and placing in position of its purpose working in or under foul / slush condition, in or under water and / or liquid mud including pumping out water as required all as directed by the Engineer-in-charge.
Providing and filling in foundation trenches and at the back of abutments, wing walls etc. and below pipe bed in layers not exceeding 150mm thick including watering and compacting including all lead and lifts. - Good local sand free from earth.
Providing and fixing prmoulded bitumen joint filler, for expansion joints including the cost of sealing compound and priming coat - 25 mm wide.
Providing , laying and jointing UPVC pipe of 250 mm dia (0.6Mpa) conforming to IS specification 4985 and ISI marked including transportation to site lowering to the trenches laying in proper grade and alignment and placing position for discharge through the drain during construction period as directed by the Engineer-in-charge.
M/S RDG CONSTRUTION
GUNASEKARAN
S.R.NEELAMEGAM
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .