| 1 | L1₹4.8 LAccepted-AOC | ₹4.8 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹4.8 LRejected-Finance | ₹4.8 L | L2 | Rejected-Finance Quoted Higher than Estimate Rate |
| Sl No | Description | Qty | Unit | MS Constructions L1 | PRABAKARAN J L2 |
|---|---|---|---|---|---|
| 1.00Construction of Pump room , Pipe Line and motor speical for Adi Dravidar Kudiyiruppu ( Near Nallathanneer Kinaru ) at Sivanam Panchayat in Thellar Block Thiruvannamalai Dist Under PMAGY 2025-2026 | |||||
| 1.01 | Earth work excavation and despositing on bank with an initial lead and lift in all soil / ordinary soil as per SS 20B | 3.65 | cu.m | 263 ₹959.95 | 265 ₹967.25 |
| 1.02 | CC 1:4:8 using 40mm HBS jelly for foundation | 1.51 | cu.m | 5,403 ₹8,158.53 | 5,405 ₹8,161.55 |
| 1.03 | Earth filling in basement & sides of foundation with excavated earth including ramming and consolidation etc., complete | 1.8 | cu.m | 45 ₹81 | 49 ₹88.20 |
| 1.04 | Sand filling with river sand including watering etc., complete | 0.71 | cu.m | 386 ₹274.06 | 388 ₹275.48 |
| 1.05 | Brick work in CM 1:6 using best country bricks of size 8 3/4" x 4 1/4" x 2" | 9.5 | cu.m | 6,158 ₹58,501 | 6,159 ₹58,510.50 |
| 1.06 | RCC 1:1.5:3 using 20mm HBS including curring etc., complete for lintel and roof slab. | 1.62 | cu.m | 9,300 ₹15,066 | 9,305 ₹15,074.10 |
| 1.07 | Centering Charges for lintel and roof slab including structing. | 6.63 | sqm | 545 ₹3,613.35 | 547 ₹3,626.61 |
| 1.08 | Plastering the brick work with CM 1:5 12mm thick including curing etc., complete | 46.7 | sqm | 284 ₹13,262.80 | 285 ₹13,309.50 |
| 1.09 | Ceiling plastering in CM 1:3, 10mm thick including etc., complete. | 4 | sqm | 327 ₹1,308 | 328 ₹1,312 |
Tender Value
₹5.0 L
EMD Value
₹5,000
Closing Date
26 Dec 2025, 5:00 pmClosed
Block Development Officer
Block Development Office
Construction of Pump room , Pipe Line and motor speical for Adi Dravidar Kudiyiruppu ( Near Nallathanneer Kinaru ) at Sivanam Panchayat in Thellar Block Thiruvannamalai Dist Under PMAGY 2025-2026
2025_RDTN_632274_1
Roc. No. A19/3721/2025 Date. 08.12.2025 THE2
Open Tender
Civil Works - Others
90 days
Thellar
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹5,000
30 Dec 2025
15 Dec 2025
26 Dec 2025
15 Dec 2025
26 Dec 2025
15 Dec 2025
Amount
Construction of Pump room , Pipe Line and motor speical for Adi Dravidar Kudiyiruppu ( Near Nallathanneer Kinaru ) at Sivanam Panchayat in Thellar Block Thiruvannamalai Dist Under PMAGY 2025-2026
Earth work excavation and despositing on bank with an initial lead and lift in all soil / ordinary soil as per SS 20B
CC 1:4:8 using 40mm HBS jelly for foundation
Earth filling in basement & sides of foundation with excavated earth including ramming and consolidation etc., complete
Sand filling with river sand including watering etc., complete
Brick work in CM 1:6 using best country bricks of size 8 3/4" x 4 1/4" x 2"
RCC 1:1.5:3 using 20mm HBS including curring etc., complete for lintel and roof slab.
Centering Charges for lintel and roof slab including structing.
Plastering the brick work with CM 1:5 12mm thick including curing etc., complete
Ceiling plastering in CM 1:3, 10mm thick including etc., complete.
Granolithic floor finish in CC 1:2:4 mix using 10-12 mm ISS sine HBG metal including cost and conveyace of all materials and all labour charges, etc.
Supply and fixing of MS door (Single leaf) of sizes 0.90 x 2.10m in MS angle 50 x 50 x 4mm and MS flat 35 x 6mm with MS sheet of 18 gauge including ventilating arrangements using 20mm square MS rods with loking arrangements including cost of hold fast, two coats of approved enamel painting over one coat of red oxide.
Supply, fabricating and fixing in position of RTS rods including cost of steel and binding wire etc., complete.
Colour Washing with best Distempering two Coats in to primer coat and two coats with oil bound distember over cement plasterd surface ceiling and other new surface and including clearing,preparing the surface and etc.,complete.
Supplying and painting the walls with two coats of cement paint over one coat of cement primer as instructed by the departmental officers including preparation of surface curing, etc., complete in all floors complying with standard specifications (The colour and shade of the cement paint shall be got approved by the Executive Engineer before use of work).
Earth work excavation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized oulders and gravelly soil etc., complete for boxing as per IS 20B.
Refilling Excavated earth and all labour charges,etc,
Cost and Supply of 90mm 6Ksc PVC Pipe
Labour charges for fixing of 90 mm 6Ksc PVC Pipe including cost and conveyance
Providing Motor 50x50 Lpm
Panel Board
50mm HDPE Pipe
2.5 sqm Cable Wire
GST Amount for providing Service to Government Contract Works for the above Construction Works. {GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
PRABAKARAN J (BID ID -1546403)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.06 MB
Tenderdocument.pdf
Tender Documents • 0.31 MB
BOQ_756453.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid