| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
| 4 | Not Admitted-Fee/PreQual/Technical | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 5 | Not Admitted-Fee/PreQual/Technical 19 A DURGA BARI SADAR BAZAR MEERUT MEERUT MEERUT UTTAR PRADESH 250001 | MEERUT | UTTAR PRADESH | 250001 | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹23.6 L
EMD Value
₹24,000
Closing Date
20 May 2023, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC MEEEURT
130 D PAARESHAN BHAWAN VICTORIA PARK MEERUT
work of carriage erection of 132/33 KV 40 MVA T/F and Erection of New 132 KV Bays 02 Nos. (01 No. for 132/33 KV 40 MVA T/F and 01 No. for 132 KV Baraut-Nirpura line) and 33 KV Bay 01 No. for 132/33KV 40 MVA T/F at 132 KV S/S Baraut under ETD Baraut
2023_UPTCL_799967_1
T-02/23-24/ETC/MT
Open Tender
Electrical Works
Item Rate
60 days
BARAUT
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
SE ETC MEEERUT
₹24,000
17 Jul 2023
2 May 2023
22 May 2023
2 May 2023
20 May 2023
2 May 2023
Amount
Work for Carriage 40 MVA T/F from 132 KV S/S Chhaprauli to 132 KV S/S Baraut including loading at Chhaprauli end, unloading at Baraut end and erection work of this T/F at 132 KV S/S Baraut under ETD Baraut.
Shifting/ Dragging of oil filled 40 MVA T/F form existing place to near loading place including turning (if required) at 132 KV S/S Chhaprauli, distance up to 55 Mtr.
Loading of 40 MVA T/F main tank along with all accessories at 132 KV Chhaprauli making wooden sleeper platform, jacking the T/F tank up to trailer height, placing the rail under T/F tank and shifted upon trailer, removed the rail under the T/F tank and proper tightening the main tank with trailer bed with the help of steel rope turn buckle and all other accessociated work
Packing of HV/LV/Neutral bushing of 40 MVA 132/33 KV, T/F in empty crates (Packing Material will be provided by the contractor at his own cost)
Carriage of 40 MVA T/F tank from 132 KV Sub Station Chhaprauli to 132 KV S/S Baraut along with all accessories by Pvt. Truck/Trailer. Distnce about 25 Km.
Unloading of main tank of 40 MVA T/F loaded on Trailer, jacking the tank for placing the rail under the T/F tank and shifting it on wooden sleeper platform, Removing the rail from under the T/F tank, lowering the tank towards ground showly-showly and removing the wooden sleepers and unloading the various Transformer accessories of above 40 MVA T/F as like oil filled drums, bushing, conservator tank, cooling fan, RTCC panel etc. from Track/Trailer at 132 KV S/S Baraut and all other accessociated work to complete the job.
Shifting/ Dragging of oil filled 40 MVA T/F unloading place to plinth upto 20 mtrs distance including turning of T/F if required including all T&P and other works to complete the job satisfactory.
Additional shifting 1 Job for every 5 Mtr.
Complete erection of 40 MVA T/F by erection of main tank, radiator, conservator tank, bushings with its turrets (if available), connecting of all oil pipe line, erection of cooling fans, making control cables connection in marshalling box, bucholz relay etc. for completing the work, topup of T/F oil in main tank, radiators, conservator tank, including replacement of gas kit and all other associated works for completion of erection work.
Erection of RTCC panel of this 40 MVA T/F in control room at 132 KV S/S Baraut. fitting as per site requirement and its connections.
Electrical connection in marshalling box of 40 MVA T/F with laying of cables and termination in between RTCC panel, WTI, OTI buchhalz relay, cooling fans, OLTC, etc including prepartion of cable schedule from interconnection diagram with proper feruling as per drawing.
Earthing of main tank at 02 Point of 40 MVA T/F by using M.S. flat 50X6 & 75X10 mm size, its jointing with already laid earthmat preparing neutral bushing support for its earthing including all work.
Jumpering of 40 MVA T/F from HV/LV side cutting of conductor and tightening of conductor with connector.
Centrifuging of complete T/F oil in T/F by connecting centrifuging pipes, circulating the T/F oil through Private centrifuging machine provided by contractor at his own cost with BDV machine and PPM kit and taking the BDV & PPM value of the oil periodically till the required value is achieved.
After centrifuging of T/F oil arrangement to be made (oil sampling and providing to lab) for oil testing result from any NABL Lab/CPRI Lab Noida. 1. DGA 2. BDV 3. PPM
Making delta earthing for 40 MVA T/F with the help of 3 Mtr. long electrodes in the shape of triangle with 1.5 mtr. made by 40 mm M.S. rod and 75x10mm M.S. flat to be connected with earthmate grid as per technical specification.
Construction/Erection work of 132 KV Bays 02 Nos. (01 No for 132/33 KV, 40 MVA T/F and 01 No. for 132 KV Baraut-Nirpura line) and 33 KV Bay 01 No. for 132/33 KV, 40 MVA T/F at 132 KV S/S Baraut under ETD Baraut.
Carriage of structure/materials from Electy. fabrication unit Naini Prayagraj/other Substations To 132 KV S/S Baraut.
Sorting, counting, stacking mark wise and head loading of structure on truck/trailer at electy. Fabrication unit Naini Prayagraj (15 MT)
Safe carriage of loaded structure from electy. fabrication unit Naini Prayagraj To 132 KV S/S Baraut Distance approx. 750 km (15 MT X750 km=11250MT-KM)
Unloading of carriage structure from Truck/Trailer its Sorting, Counting and proper Stacking at the S/S premises as per direction of supervisioning engineer (15 MT)
Erection of following structure/equipments as per instruction of various equipments manuals and technical specifications including shifting of structures/ equipments from store to erection site including all other associated works including making holes, fixing of suitable cable glands, ferrules and electrical connection/termination as per cable schedule, for completion of erection work satisfactorily:-
Lattice type Auxiliary structures
Lattice type Main structures
132 Control and relay panel a. Transformer C&R Panel for 40MVA T/F b. 132 KV Bus coupler control panel c. 132 KV Double Feeder Control Panel d. 132 KV Distance Protection Relay Panel
145 KV SF-6 Circuit Breaker
145 KV C.Ts
145 KV Bus Isolator without earth blades
145 KV Line Isolator with earth blades
145 KV C.T./P.T. Junction box
145 KV Post Insulators
Gear box mechanism of 145 KV LSI, BSI & TI
36 KV Bus Isolator (2000 Amp)
36 KV VCB
36 KV CTs (800/400/1A)
36 KV CT Junction box
Metering cubicle, Main & check ABT Meters.
Stringing of new jack bus of single Zebra/Panther conductor all 3 phase between transfer bus to main bus and 40 MVA T/F CT to gantry aux bus of 36/24 mtr approx length, including Tightening of Jack bus with single Tension fitting of Zebra/Panther conductor with proper sagging and clamping each phase.
Jumpering of all equipments of 132 KV feeder bay with ACSR Panther conductor between Main & Transfer bus including all droppers with help of suitable clamps/fittings to be provided by department including hoisting of 120 KN/70KN disc insulator on each phase on 132 KV gantry with suspension clamps and required cutting and bending of conductors.
Dismentling of jumpers from exiting 132 KV Baraut-Nirpura line, Bay at 220 KV S/S Baraut and 40 MVA T/F IIIrd at 132 KV S/S Baraut.
Dismantling of ACSR Panther conductor of all Three phase of 132 KV Baraut-Nirpura line between tower No. 01 to 220 KV S/S Baraut gantry Aprox. Length 300 Meter including opening jumper at tension tower lower down with insulator strings at tower no. 01 to Gantry & cutting between tower no 01 & Gantry after stopping the conductor at tower no. 01.
Laying & stringing of ACSR Panther conductor from tower no. 01 to perposed 132 KV Bay gantry at 132 KV S/S Baraut Aprox. length 230 Meter of 132 KV Baraut-Nirpura line including work of laying, Sagging, jointing by using MS joint by compressor & hoisting in suspension clamp & tension fitting at tower 01.
Earthmat laying in extended 132 KV Switchyard.
Fabrication of 3M long 40mm diameter electrode with following MS Rod having 150mm long conical shape and then its piercing vertically inside the ground with top 50mm below ground level and its welding with earth mat excluding the cost of MS Bar.
Extension of MS Round Bar Earth Mat 40mm by digging of earth cutting, laying, welding and back filling of earth and doing all other associated work to complete the job satisfactorily excluding cost of MS Round Bar.
Cutting, straightening & laying of following MS flat 750 mm below inside ground and above ground of 75mm x 10mm, 50 mm x 6 mm size and 25 mm x 6 mm size MS Flats for earthing of main auxiliary structures, equipment and cable trenches including welding with main earthmat and with the object to be earthed excavation of trenches its back filling painting and all other associated work to complete the earthing work satisfactorily as per technical specification.
Earthing of main structures with 75 mm x 10 mm size MS Flat.
Earthing of aux structures with 50 mm x 6 mm size MS Flat.
Earthing of trenches with 25 mm x 6 mm size MS Flat.
Prepartion of cable schedule from Interconnection diagram as per drawings to complete job including C.B., C.T., Isolators, control and relay panel with main CB and Transfer bus coupler etc. & submission of same in hard bound sets of 03 copies to the department for following bays.1. 132 KV Transformer bay - 01 No.2. 132 KV Line bay - 01 No.3. 132 KV Bus coupler bay - 01 No.4. 33 KV Transformer bay - 01 No.
Laying of following size of control cables in the cable trenches and relay panels in control room to various equipments, junction boxes, etc. in switchyard as per cable schedule its saddling with 25X3mm size including carriage of cable drums from stores to work site and shifting back to store with all other associated works to complete the job satisfactorily as per technical specifications:-
Laying of 2X2.5 sqmm size control cable
Laying of 4X2.5 sqmm size control cable
Laying of 6X2.5 sqmm size control cable
Shifting wireing of 132 KV Bus coupler C&R panel from existing bay to 132 KV Nirpura bay that will become spare after shifting of Nirpura line from 220 KV S/S Baraut to 132 Kv S/S Baraut, including opening the termination from both end of existing Nirpura bay and removing all the cables between contorl room to yard. Make new termination for Bus coupler bay at 220 KV S/S Baraut.
Dismentling of following equipments with structure from exiting 132 KV Nirpura Bay for converting of 132 KV Nirpura bay to bus coupler bay at 220 KV S/S Baraut.
145 KV C.Ts
Shifting of all material site to store room
Delta earthing of 120 KV LA consisting of 06 nos. 3 Mtr long electrode its placing inside the ground and connecting all three electrodes with M.S. flat and connecting the same with main earthmat at two place required excluding cost of MS strip and MS roud bar for following bays. 1. 132 KV Transformer bay - 01 No. 2. 132 KV Line Bay - 01 No.
Fixing of new generation energy & environment friendly long aluminium outdoor beam street light with high power 120 watt LEDs. Including wiring from junction box to light fitting point and checking of healthyness of LED lights.
Installation of junction box of size 280x225x150 mm made of 16 SWG sheet with grey painting suitable for 2x4x6 C sq mm incoming cable and 2x4x6 C sq mm outgoing cable fitted with 03 Nos. HRC fuse link of 5 Amp. cable glands, nutral link, terminal block etc and fixing of junction box on columns with the help of 50x6 mm GI Clamp.
Supply Part
Bolted type single tension fitting for Single Panther conductor with turn buckle, D-shackle, D-socket, made from forged steel, Tension clamp made of aluminium alloy LM-6 as per technical specification duly type tested confirming to BIS: 2486 Part I. The UTS capacity of complete hardware fitting shall be minimum 70 KN.
Bolted type single tension fitting for Single Panther conductor without turn buckle, D-shackle, D-socket, made from forged steel, Tension clamp made of aluminium alloy LM-6 as per technical specification duly type tested confirming to BIS: 2486 Part I. The UTS capacity of complete hardware fitting shall be minimum 70 KN.
Single suspension fitting for Single Panther conductor complete with bell hook, Socket eye, suspension clamp etc. as per technical specification duly type tested confirming to BIS: 2486 Part I.The UTS capacity of complete hardware shall be minimum 70 KN.
132 KV BI-metallic CT clamp made of aluminium alloy LM-6. At middle side connecting Rod of 30 mm dia for 132 KV CT and both end side connecting ACSR Twin Zebra conductor with 150 mm spacing as per sample confirming to BIS: 5561 duly type tested.
132 KV BI-metallic universal type isolator clamp made of aluminium alloy LM-6. one side connecting plate for 132 KV isolator and other side connecting ACSR Twin Panther conductor as per sample confirming to BIS: 5561 duly type tested.
33 KV bus Isolator clamp for Twin Zebra bundle conductor made of aluminium alloy LM-6 one side connecting the twin zebra conductor another side connecting a plate of size 100x100x20mm with 4 nos. 12mm dia hole with HDG nut & bolts and washer as per technical Specification.
40 MVA Transformer clamp for Twin Zebra conductor made of Copper/Gun metal one side connecting the twin zebra conductor another side connecting a plate of size 100x100x20mm with 4 nos. 12mm dia hole with HDG nut & bolts and washer as per technical Specification.
33 KV CT clamp for Twin Zebra conductor made fo aluminium alloy LM-6 one side connecting the twin Zebra conductor another side the CT bushing rod 18mm Dia with HDG 10 mm nut & bolts and washer as per technical Specification.
T Connector clamp made of aluminium alloy LM-6 suitable to hold ACSR Zebra conductor at one end & other side for Panther conductor of 8 U bolted type as per sample confirming to BIS: 5561 duly type tested.
T Connector clamp made of aluminium alloy LM-6 suitable to hold ACSR Panther to Panther conductor of 8 U bolted type as per sample confirming to BIS: 5561 duly type tested.
132 KV BI-metallic CB clamp made of aluminium alloy LM-6 one side connecting plate for 132 KV breaker and other side connecting ACSR Twin Panther conductor as per sample confirming to BIS: 5561 duly type tested.
33 KV BI-metallic CB clamp made of aluminium alloy LM-6 . one side connecting plate for 33 KV breaker and other side connecting Twin Zebra conductor as per sample confirming to BIS: 5561 duly type tested.
PG Clamp 4 Bolted type made of aluminium alloy LM-6 suitable for ACSR Zebra to Panther complete with hot dip galvanized nuts, bolts spring & plain washer confirming to BIS: 5561 duly type tested.
PG Clamp 4 Bolted type made of aluminium alloy LM-6 suitable for ACSR Panther to Panther complete with hot dip galvanized nuts, bolts spring & plain washer confirming to BIS: 5561 duly type tested.
PG Clamp 4 Bolted type made of aluminium alloy LM-6 suitable for Zebra to Zebra complete with hot dip galvanized nuts, bolts spring & plain washer confirming to BIS: 5561 duly type tested.
Hot dip galvanized Cable tray 18SWG having weight 75mm as per technical specification.
Hot dip galvanized Cable tray 18SWG having width 100mm as per technical specification.
Flexible copper bond made of electroyte copper rope of size 37/7/0.457 having hength 750mm tinned copper lug shall be pressed jointed both end of copper bond as per technical specification.
132 KV BI-metallic Post Insulator clamp made of aluminium alloy LM-6 .suitable to hold ACSR Twin Panther conductor as per sample confirming to BIS: 5561 duly type tested.
33 KV BI-metallic Post Insulator clamp made of aluminium alloy LM-6 .suitable to hold ACSR Twin zebra conductor as per sample confirming to BIS: 5561 duly type tested.
Providing of new generation energy & environment friendly long aluminium outdoor beam street light with high power 120 watt LEDs as light source & exclusively designed polycarbonate cover along with electronic driver complete fitting suitable for 220 Volt AC input supply of CGL/Havells/ Surya/Philips/Bajaj etc.
Supply of junction box of size 280x225x150 mm made of 16 SWG sheet with grey painting fitted with 03 Nos. HRC fuse link of 5 Amp. cable glands, neutral link, terminal block etc.
Compresor type single tension fitting sutable for ACSR Panther conductor with jumper cone.
Vibretion damper for ACSR Panther conductor.
Galvanized U Bolted 20mm dia with double nut and washer.
Perfect Power Transformer Associates
SATKAR TRADERS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .