Tender Value
₹17.8 L
EMD Value
₹35,640
Closing Date
30 Sept 2026, 6:00 pm
Executive Engineer RRWD SMC
Executive Engineer RIGHT RIVER WORKS DIVISON REGAL LANE LAL CHOWK
Construction of separate rooms and washrooms adjacent to Daulatabad Masjid
2026_HAUDD_323989_21
NOTICE INVITING ETENDER No. 34 of 2026-2027 Dated 09.09.2026 RRWD SMC
Open Tender
Civil Works
Percentage
90 days
Daulatabad Masjid
Please refer Tender documents.
2 documents required · 2 mandatory
₹800
FA/CAO AC NO 0216010200000007
₹35,640
9 Sept 2026
9 Sept 2026
1 Oct 2026
10 Sept 2026
30 Sept 2026
10 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge In cement mortar | 8.31 | Cum | 1,458.45 | ₹12,119.72 |
| 2 | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m. (stacks of cleaned bricks shall be measured) from brick work in cement mortar | 3.32 | 1000 No | 4,944.1 | ₹16,414.41 |
| 3 | Demolishing R.C.C. work manually/by mechanical means including stacking of steel bars and disposal of un-serviceable material within 50 meters lead as per direction of Engineer-in-charge. | 1.57 | Cum | 2,516.85 | ₹3,951.45 |
| 4 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-in- charge 1:3:6 or richer mix (i/c equivalent design mix) | 2.71 | Cum | 1,725.2 | ₹4,675.29 |
| 5 | Dismantling wood work in frames, trusses, purlins and rafters upto 10 meters span and 5 meters height including stacking the material within 50 meters lead of sectional area 40 sqcm. and above. | 1.04 | Cum | 3,488.65 | ₹3,628.2 |
| 6 | Dismantling roofing including ridges, hips valleys and gutters etc., and stacking the material within 50 meters lead of G.S. Sheet | 80 | Cum | 125.35 | ₹10,028 |
| 7 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed all kinds of soil 50 meter beyond 1 m from cutting edge. | 40.5 | Cum | 479.3 | ₹19,411.65 |
| 8 | Providing & laying stone soiling including compacting, watering including all carriages of material complete | 19.77 | Cum | 850 | ₹16,804.5 |
| 9 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 10.73 | Cum | 5,202.9 | ₹55,827.12 |
| 10 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement: 1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) | 45.45 | Cum | 7,788.4 | ₹3,53,982.78 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.24 MB
BOQ_1092253.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .