Loading…
Loading…
Tender Value
₹35.9 L
EMD Value
₹35,880
Closing Date
18 Jul 2026, 5:00 pm5d left
Divisional Officer
RURAL WORKS DIVISION, TITILAGARH
SR L070-Salemurunga to Sanabanki road_Road_Renewal coat SDBC, WMM and Side shoulder reparing, 0.000 to 2.670 under Tureikela Block for the year 2026-27
2026_CERWI_134898_1
EETIG-ONLINE-02-2026-27
Open Tender
Civil Works - Roads
180 days
Balangir
2 documents required · 2 mandatory
₹6,000
₹35,880
Yes
9 Jul 2026
9 Jul 2026
20 Jul 2026
9 Jul 2026
18 Jul 2026
9 Jul 2026
9 Jul 2026 - 17 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting rank vegtable, grass, bushes, shrubs, saplings and trees girth up to 300mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable materials to be used or auctioned up to lead of 1000 mtr including removal and disposal of top organic soil not exceeding 150mm in thickness etc. compete as per direction of the Engineer-in-charge . | 6,820 | sqm | 8.63 | ₹58,856.6 |
| 2 | Cleaning the existing granular base/B.T. surface including removal of binding materials and other foreign materials with wire brushes etc. complete | 8,010 | sqm | 5.59 | ₹44,775.9 |
| 3 | Construction of embankment with materials obtained from borrowpits with all lead spreading , grading to required slope and compacting to meet the required table 300-2 | 66.75 | sqm | 402.99 | ₹26,899.58 |
| 4 | Wet Mix Macadam Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by ipper to site, laying in uniform layers with paver in sub-case / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
Unit-cum Takingoutput-225cum(495 tones) | 15.75 | cum | 2,361.8 | ₹37,198.35 |
| 5 | Providing and applying primer coat with bitumen emulsion on prepared surface of garanular base including clearing of road surface and spraying primer at the rate of 0.06kg sqm using mechanical means as per clause 502 of MORT&H specifiacations for Road & Bridge works (4th Revision) | 210 | sqm | 80.29 | ₹16,860.9 |
| 6 | Providing and applying Tack Coat with Bitumen Emulsion RS using bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom as per Clause 503 of MoSRT&H Specifications for Road & Bridge works (4th Revision) | 8,010 | sqm | 25.51 | ₹2,04,335.1 |
| 7 | Providing and laying semi-dense bituminous concrete with 100-120 TPH batch type HMP producing and average 75 tone per Hour using crushed aggregate specified grading, premix bituminous binder @ 4.5 to 5 per cent of mix and Filler, transporting the hot mix to works site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheel, vibratory and tandem rollers to achieve the desire compaction as per MoRTH specification clause No. 508 data book page-135. | 209.57 | cum | 14,328.95 | ₹30,02,918.05 |
| 8 | Providing and fixing of Informatory sign board . Lettering and printing arrows, border etc. will be painted with ready mixed synthetic enamel paint of superior quality in required shade and colour. All sections of framed posts and steel tube will be painted with primer and two coats of epoxy paint . (Direction Indicator Board) | 2 | nos | 2,381.1 | ₹4,762.2 |
| 9 | Earth work in excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring & bracing removal of stumps and other deleterious material and disposal up to a lead of 50mtr, dressing of sides and bottm and back filling in trenches with excavated suitable material. | 42.25 | cum | 282.89 | ₹11,952.1 |
| 10 | Filling sand in foundation in trenches as per drawing and technical specification clause 305.3.9 | 10.06 | cum | 816.17 | ₹8,210.67 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.25 MB
Tendernotice_2.pdf
PDF • 1.01 MB
BOQ_600364.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid