Tender Value
₹34.7 Cr
EMD Value
₹85 L
Closing Date
5 Aug 2026, 5:00 pm
GM(CIVIL)
MAIN ADMIN BUILDING SECTOR 6 NOIDA
C/o Noida International Golf Course Balance work at Sector-151A Noida
2026_NOIDA_1171523_1
55/GM/SM(WC-10)/ET/26-27
Open Tender
Civil Works
Fixed-rate
365 days
NOIDA
REFER TO TENDER DOCUMENT
3 documents required · 3 mandatory
₹8,260
NOIDA
₹85 L
22 Jul 2026
22 Jul 2026
6 Aug 2026
22 Jul 2026
5 Aug 2026
22 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30cm in depth. 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50 and lift upto 1.5m, disposed earth to be levelled and neatly dressed.Depth upto 1.5m from existing ground level.The contractor has to detect different utilities like sewer line, water supply, electrical cable, telephone cable, gas pipe line etc. using utility detecting machine before start of excavation and shall start excavation only after getting permission of Engineer in Charge. All Kind of soil. | 2.61 | Cum | 136 | ₹354.96 |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 5,637.76 | Cum | 93 | ₹5,24,311.68 |
| 3 | Sand Filling in Plinth including Supply of Necessary Qty of Sand From a Dist. Not Exceding 8 Kms from The side of Work and including watering Dressing etc, labour & T&p Etc required for the proper completion of the work.saplings of gith up to 30cm major at a height of 1 mtr above ground level and removal of rubbish up to a dist. of 50 mtr outside the peri feri of area cleared. | 7.39 | Cum | 460 | ₹3,399.4 |
| 4 | Diluting and injecting chemical emulsion for POST- CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) :Along external wall where the apron is not provided using chemical emulsion @ 7.5 litres / sqm of the vertical surface of the substructure to a depth of 300mm including excavation channel along the wall & rodding etc. complete:With Chlorpyriphos/ Lindane E.C.20% with 1% concentration | 50.47 | Mtr. | 16.17 | ₹816.1 |
| 5 | Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone - III) : 6 graded stone aggregate 20 mm nominal size) over 75mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. | 464.4 | Sqm | 6,319.48 | ₹29,34,766.51 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level All works upto all levels: 1:3:6 (1 Cement : 3 coarse sand (zone- III): 6 graded stone aggregate 40 mm nominal size) | 20.99 | Cum | 6,066.29 | ₹1,27,331.43 |
| 7 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) | 92.61 | Cum | 5,746.88 | ₹5,32,218.56 |
| 8 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in- charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ less cement used as per design mix is payable/recoverable separately). All works above plinth level upto floor V level | 75.11 | Cum | 8,306.31 | ₹6,23,886.94 |
| 9 | Providing and laying in position machine batched and machine mixed design mix Providing M-35 grade concrete instead of M-25 grade BMC/ RMC. (Note : Cement content considered in M-35 is @ 350 kg/ cum) | 72.35 | Cum | 131.94 | ₹9,545.86 |
| 10 | Providing and laying in position machine batched and machine mixed design mix Providing M-40 grade concrete instead of M-25 grade BMC/ RMC.(Note : Cement content considered in M-40 is @ 360 kg/ cum) | 34.8 | Cum | 197.91 | ₹6,887.27 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.26 MB
BOQ_2199365.xls
BOQ • 5.77 MB
55TD.pdf
Tender Documents • 4.25 MB
C.xls
Additional Documents • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].