| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24.7 CrAccepted-AOC | ₹24.7 Cr | L1 | Accepted-AOC Quoted price is reasonable and justified |
| 2 | L2₹28.3 CrRejected-Finance | ₹28.3 Cr | L2 | Rejected-Finance Not the lowest bidder |
| 3 | Rejected-Technical | - | - | Rejected-Technical neither submitted Certificate from a Chartered Accountant confirming the status of JV w.r.to GST in compliance with relevant GST rules nor GST Registration Certificate of JV |
Tender Value
₹26.2 Cr
EMD Value
₹32.7 L
Closing Date
24 Jun 2022, 5:00 pmClosed
GM(EnM)/HOD, NCL
EnM Department, NCL, HQ, Panjreh Bhawan, Singrauli - 486889, MP
Planning, Design, Engineering, Construction, Supply, Erection, Installation and Commissioining of the complete Secondary Sizer plant on turnkey basis and Operation and Maintenance of plant for five years at Khadia CHP
2022_NCL_244335_1
NCL/SGR/EM/Tender/2022/117 dtd. 19.05.2022
Turnkey
Miscellaneous Works
2005 days
Khadia Project, NCL
Please refer Tender documents.
7 documents required · 7 mandatory
₹32.7 L
NCL HQ
21 Sept 2022
20 May 2022
25 Jun 2022
20 May 2022
24 Jun 2022
26 May 2022
20 May 2022 - 3 Jun 2022
25 May 2022
Amount
A. WORK & SERVICES
Detailed survey of the area, within the battery limits & submission of reports
Sub soil exploration, field and laboratory testing of samples & submission of reports
Design Engineering Cost
Preparation and submission of system engineering drawings as per system requirements
GA & detail engineering designs and drawings of all civil and structurals included in the system and scope of works
G.A. & detailed engineering designs and drawings including working and maintenance manuals of : i) all individual equipment ( Mechanical & Electricals) ii) Dust Control & Pressurisation system. iii) Fire-fighting system. iv) Chutes & Liners v) Communication system vi) Power Supply System vii)Illumination system. viii) Plant control system ix) Any other system/unit to match the scope of work & requirement
Documentation as per tender specification
B. CIVIL & STRUCTURAL WORKS
Earthwork in cutting in all types of soil and rock
Earthwork in filling
Sand filling
PCC at all levels as per system requirement
RCC (excluding reinforcement) at all levels as per system requirement
Supply, bending, binding and placing of Tor steel in position
Shuttering
Supply, fabrication and erection of structural steel at all levels as per system requirement
Iron profile sheeting at all levels including supply.
Dismantling of structural steel
Miscellaneous
C. PLANT & MACHINERY (SUPPLY)
C.(a) SUPPLY : MECHANICAL
a. EQUIPMEMT
Equipments involved in Secondary Sizing
Mechanical Equipment at Transfer house
Other mechanical equipment
Dust suppression system with piping & other accessories. Condition monitoring system, Safety & firefighting system , and other misc. equipment/utility for any more item required to complete the project
C.(b) SUPPLY : ELECTRICAL
ELECTRICAL
Power supply arrangement prposed 6.6 kV Switchboard No. 1-A comprising 1 no. of 6.6 kV Vacuum Circuit Breaker panel for Bus coupler, 6 of vacuum contactor panels complete with metering and protection system for HT loads and spare panels for other purposes, complete with metering and protection as required MCC at Existing Substation Comprising of Incomer MCCB as Buscoupler and Outgoing ACBs/MCCB/SFU/ Contactor as required. 415V,Aluminium Bus-duct as required. Fire Protection system.
Cables Power Cables Control & Signalling Cables Lighting Cables & wires Communication Cables
Earthing Plant Equipment Earthing Structures Earthing Earthing for Lightning Protection Tranformer neutral Earthing
Welding Sockets and 1 number of Electical Welding Set
Cable Trays, Cable Racks, Cable Trenches, Cable Voults etc.
Illumination System and Luminaires, Lighting poles & , Lighting DBs etc.
Exhaust Fan, insulating Mats etc.
Miscellaneous Equipment
C1. ERECTION, INSTALLATION & COMMISSIONING
1. Erection of mechanical equipment
2. Erection of electrical equipment
3. Erection of other plant and machining etc.
4. Trial run, and commissioning of the plant
C2 . OTHERS ITEM
1. Drinking water system consisting of tanks, pipes, valves, taps etc.
2. Plant cleaning system
3. Any other item left out for completion of the project
C3 . MAINTENANCE AND TRAINING
Operation of the plant for five years after commissiong
Maintenance of the plant for five year after commissiong
Training of the employer personnel as per tender document
Total impact of GST for the purpose of CTC
ARDEE ENGINEERING PRIVATE LIMITED
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid