Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹76.1 L
EMD Value
₹2.3 L
Closing Date
26 Oct 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
CE
Ghaziabad Nagar Nigam
Road improvement work from SBI Bank to SJ-19 in Shastri Nagar under Kavi Nagar Zone area.
2026_DOLBU_1194229_87
133/Nirman/2026-27 Date 28.09.2026
Open Tender
Civil Works
Percentage
CE
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,391
₹2.3 L
8 Oct 2026
8 Oct 2026
26 Oct 2026
8 Oct 2026
26 Oct 2026
8 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling reinforced cement concrete or reinforced brick work including stacking of materials as directed by the Engineer-in- charge within a distance of 60 metre (200 feet). PWD SOR 2022 17.3 | 31.33 | CUM | 1,340 | ₹41,978.45 |
| 2 | Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M. and lead upto 30 M. and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplusearth as directed by the Engineer-in-charge upto a distance of 30 M. from the foundation trenches. (Where machine can not reach/move).PWD SOR 2022 4.1.1 | 200 | CUM | 110 | ₹22,000 |
| 3 | Desposal of refused material/malwa distance up to 8 km etc all complete as the direction of engineer in charge. (AS PER PWD SOR 2020 /231( a). | 150 | CUM | 195.1 | ₹29,265 |
| 4 | Supply of 45 to 63 mm gauge stone ballast with stacking for measurment etc all complete as per the direction of engineer in charge.RMR | 91 | CUM | 2,096.2 | ₹1,90,754.2 |
| 5 | Supply of 22.4 to 53 mm gauge stone ballast with stacking for measurment etc all complete as per the direction of engineer in charge.RMR | 91 | CUM | 2,151.2 | ₹1,95,759.2 |
| 6 | Supply of Screeing material with stacking for measurment etc all complete as per the direction of engineer in charge.RMR | 32.76 | CUM | 2,050.2 | ₹67,164.55 |
| 7 | Consolidation of stone aggregates of 45-63 mm/22.4-53mm size to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2/3 as per Technical Specification Clause 405.(SOR 2022 SI. N. 20.02 ITEM N. 752) | 182 | CUM | 690 | ₹1,25,580 |
| 8 | Providing and applying tack coat with bitumen VG - 10 grade using bitumen pressure distributor at the rate of .30 kg per sqm on the prepared granular surface treated with primer & cleaned with hydraulic broom as per technical specification clause 503. | 1,000 | SQM | 21.7 | ₹21,700 |
| 9 | Providing and laying dense graded bituminous macdam with HMP producing an average output of 75 tonnes per hour using crushed aggregates from approved quarry of specified grading, premixed with bituminous binder (VG-30) @ 4.5 per cent by weight of total mix and filler,transporting the hot mix to work site,laying with a hydrostatic paver finisher to the required grade, level alignment,rolling with smooth wheeled. vibratory and tandem rollers to achieve the desired compaction (Ref. to Mort&HSpecification no. 507 ) Adjustment for bitumen shall be done as per job mix formula and e-in-c latter No 2651 Dt 27-07-12 for proper completion of work as per direction of engineer-in-cgarge including all labour,T&P,taxes , labour cess etc. complete. | 50 | CUM | 14,199 | ₹7,09,950 |
| 10 | Providing and applying tack coat with bitumen VG - 10 grade using bitumen pressure distributor at the rate of .30 kg per sqm on the prepared granular surface treated with primer & cleaned with hydraulic broom as per technical specification clause 503. | 3,000 | SQM | 16.7 | ₹50,100 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.44 MB
BOQ_2254488.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .