| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.6 LAccepted-Finance | ₹14.6 L | L1 | Accepted-Finance L1 |
| 2 | L2₹14.7 L+₹16,739 (1.15%)Rejected-Finance | ₹14.7 L+₹16,739 (1.15%) | L2 | Rejected-Finance L2 |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
Tender Value
₹15 L
EMD Value
₹15,000
Closing Date
18 Apr 2025, 3:00 pmClosed
BDO (VP) MINJUR BLOCK
MINJUR BLOCK OFFICE
IMPROVEMENT TO SAMUTHUVA BURIAL GROUND (SHED, COMPOUND WALL 77M AND APPROACH CC ROAD 60M ) IN ERI COLONY AT KOLUR PANCHAYAT
2025_RDTN_540895_22
2666/2024/A7
Open Tender
Civil Works - Buildings
Item Rate
180 days
MINJUR
CLASS V as per GO 109 RD
5 documents required · 5 mandatory
₹0
₹15,000
Yes
23 Apr 2025
8 Apr 2025
18 Apr 2025
8 Apr 2025
18 Apr 2025
8 Apr 2025
Amount
1. IMPROVEMENT TO SAMUTHUVA BURIAL GROUND (SHED, COMPOUND WALL 77M & APPROACH CC ROAD 60M ) IN ERI COLONY @ KOLUR PANCHAYAT IN MINJUR PANCHAYAT UNION UNDER AGAMT -II /2025 - 2026/ RD/TVLR/MJR22
Clearing the Light jungle with uprooting and disposing of the same as directed by the Engineer in charge of the works as per technical
Earth work excavation for foundation in all soils and sub - soils etc., complete as per SS 20B
Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
RCC 1:1.5:3 Mix using 20mm HBG metal including cost and conveyance and all labour charges and materials charges completed..
Sub Structure
Super Structure
Supply and errecting for centering including cost and conveyance and labour charges with materials charges with MS sheet completed
Sub Structure
Super Structure
Supply and Fabrication of steel including cost and conveyance of all materials to site and all labour charges for placing in position etc,..completed..
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Special ceiling plastering and finishing the exposed surface of all RCC items of work such as slabs, beams, sunshades, facia, canopy slab, staircase waist slab, landing slab etc., with Cement Mortar 1:3 (One Cement and Three M.Sand) 10mm thick including hacking the surfaces, providing cement mortar nosing, beading for sunshades, staircases, steps, landing slabs and curing, etc., in all floors complying with standard specification and as directed by the departmental officers
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
Cement Concrete 1:2:4 (One cement, Two M.sand, Four Hard Broken stone) using 20 mm guage machine broken hard broken granite stone jelly including cost conveyance and all labour charges etc. complete.
COMPOUND WALL
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Supply and Fabrication of steel including cost and conveyance of all materials to site and all labour charges for placing in position etc,..completed..
Supply and errecting for centering including cost and conveyance and labour charges with materials charges with MS sheet completed
Sub Structure
Super Structure
RCC 1:1.5:3 Mix (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three M.Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Painting two coats of newly plastered wall surface with ready mixed plastic emulsion paint of first class quality and of approved colour over a priming coat including thorough scrapping, clean removal of dirt, and including necessary plaster of paris putty, wherever required etc., complete complying with standard specification.
CC ROAD
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Towards centering chargers for all labour charges etc
Plain Cement Concrete 1:3:6 (one cement, three M.Sand and six hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Plain Cement Concrete 1:2:4 using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers.
Supply and Fixing of Bitumen pad for Expansion joint including cost and conveyance of all materials to site and all labor charges etc., completed.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
PRAKASH-CONTRACTOR (BID ID -1304011)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .