| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹79.6 CrAccepted-AOC 74 T N H B COLONY NEAR BALAMURUGAN TEMPLE MADURAI 625017 | MADURAI | TAMIL NADU | 625017 | ₹79.6 Cr Quoted ₹85.4 Cr | L1 | Accepted-AOC Your tender for the above work is accepted for Rs.79,63,15,737.00 |
| 2 | L2₹87.5 CrRejected-Finance P AND C TOWERS 2ND FLOOR 140 PERUNDURAI ROAD ERODE 638 011 | ERODE | TAMIL NADU | 638011 | ₹87.5 Cr | L2 | Rejected-Finance Among the two bidders, the highest rate quoted by PandC Projects Private Limited |
Tender Value
₹78.1 Cr
EMD Value
₹39.2 L
Closing Date
20 Jul 2023, 3:30 pmClosed
Superintending Engineer
O/o. the Superintending Engineer, WRD., Palar Basin Circle, Chennai-600005
Construction of Open Channel and Cut and Cover channel in Thanikachalam Nagar Drain in Madhavaram and Ayanavaram Taluk of Chennai District.
2023_WRD_335563_1
e-Tender Notice No.02 PBC / 2023-24 / Dt.27.06.202
Open Tender
Civil Works
546 days
Chennai
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹39.2 L
12 Oct 2023
4 Jul 2023
21 Jul 2023
4 Jul 2023
20 Jul 2023
4 Jul 2023
Amount
Dismantling, Clearing away and carefully stacking materials useful for re - use for any thickness of walls of stone masonry in cement mortar walls under 3 M high - etc complete complying with standard specifications and as directed by the departmental officers
Dismantling, clearing away and carefully stacking materials useful for re-use for any thickness of Reinforced cement concrete et by using machineries complete complying with standard specifications and as directed by the departmental officers
Earth Work narrow excavation for foundation in all soils and sub soils and to full depth as may be directed by the Departmental Officers except hard rock requiring blasting including shoring, strutting and baling out of water wherever necessary and refilling the sides of foundation with excavated soil in layers not exceeding 15 cm thick, well rammed and consolidated and depositing including all initial leads and initial lifts, etc., complete complying with standard specifications and as directed by the departmental officers.
Supplying and spreading of river sand - gravel mix ratio of 1 : 1 for 15 cm thick over the top of bund and other places as required at site of work including watering and consolidation using power roller, etc, complete complying with standard specifications and as directed by the departmental officers.
Supplying and laying of ready mix for the M15 grade of concrete having characteristic strength not less than specified in the IS 456-2000 using ordinary prtland cement wth minimum cement content 240Kg/cum confirming to IS 8112.Coarse aggregate having a specific gravity 2.60 using 20mm down graed hard blue granite broken stone jelly and fine aggregate without fly ash as per IS 383 - 1970 (2007) with suitable water cmenet artio not less than 0.45 and not exceeding 0.50 of water quality confirming to IS456 - 2000 including use of plasticizer of approved make & dosage of required grade at all locations and levels with specified high workablity as per IS 1199 - 1959 (2004). The initial & final setting time confirming IS 12269 -1987(2004) with maximum temperature of concrete at the time of placing should not exceed 32° C. The admixtures affecting the quality and strength of the concrete should not be used and should confirm IS 9103 - 1979 [ usual admixture - Air entraining and water reducing].Including the cost of hire charges for pump and pumping charges to the required locations and levels as sepcified by the Engineer in charge ,laying, compacting, consolidation by uinsg vibrators, finishing, watering, curing,testing charges as per IS 456-2000 ,4031- (part 3&6) / 1988(2005) &(part2) / 1999(2004) and 516 / 1959(2004),4926-1976 (1990), mix design details to be got approved before commencement of the work adopting pour card system and other OK cards. Excluding the cost of form works, centering, shuttering and cost of reinforcement grills placed in position etc, complete cpmplying with standard specifications and as directed by the departmental officers. (PCC Work)
Supplying and laying of ready mix for the RCC M30 grade of concrete having characteristic strength not less than specified in the IS 456-2000 using ordinary prtland cement wth minimum cement content 300Kg/cum confirming to IS 8112.Coarse aggregate having a specific gravity 2.60 using 20mm down graed hard blue granite broken stone jelly and fine aggregate without fly ash as per IS 383 - 1970 (2007) with suitable water cmenet artio not less than 0.45 and not exceeding 0.50 of water quality confirming to IS456 - 2000 including use of plasticizer of approved make & dosage of required grade at all locations and levels with specified high workablity as per IS 1199 - 1959 (2004). The initial & final setting time confirming IS 12269 -1987(2004) with maximum temperature of concrete at the time of placing should not exceed 32° C. The admixtures affecting the quality and strength of the concrete should not be used and should confirm IS 9103 - 1979 [ usual admixture - Air entraining and water reducing].Including the cost of hire charges for pump and pumping charges to the required locations and levels as sepcified by the Engineer in charge ,laying, compacting, consolidation by uinsg vibrators, finishing, watering, curing,testing charges as per IS 456-2000 ,4031- (part 3&6) / 1988(2005) &(part2) / 1999(2004) and 516 / 1959(2004),4926-1976 (1990), mix design details to be got approved before commencement of the work adopting pour card system and other OK cards. Excluding the cost of form works, centering, shuttering and cost of reinforcement grills placed in position etc, complete cpmplying with standard specifications and as directed by the departmental officers.
Supplying and erecting centring for vertical plain / RCC concrete walls of supply channel, retaining wall etc follwing height with necessary supports, all cross bracing with mild steel size of 90 cm x 60 cm and gauge BG 10 stiffened with welded mild steel sheet angles of size 25 mm x 25 mm x 3 mm for bearing laid silver Oak / Country wood joist of size 7.50 cm x 5.0 cm spaced @ about 90 cm C / C and supported by Casurina props of 10 cm to 13 cm spaced @ 75 cm C / C, etc., complete complying with standard specifications and as directed by the departmental officers (Vertical centering)
0 to 0.90m height
0 to 2.70 or 3.0m height
Supplying and erecting centering for sides and soffits and strutting upto 3.0 m height for plane surfaces such as RCC works etc, with all cross bracing with mild steel size of 90 cm x 60 cm and gauge BG 10 stiffened with welded mild steel sheet angles of size 25 mm x 25 mm x 3 mm for bearing laid silver Oak / Country wood joist of size 10 cm x 6.5 cm spaced @ about 90 cm C / C and supported by Casurina props of 10 cm to 13 cm spaced @ 75 cm C / C, and removing the same without any damages etc., complete complying with standard specifications and as directed by the departmental officers. (Horizontal centering)
Supplying, fabricating and placing in position of Mild Steel or Ribbed Tor Steel for all RCC works as per design & drawing given including cost of steel, binding wire and labour charges for cutting, bending, laying in position and tying with binding wire, etc. complete complying with standard specifications and as directed by the departmental officers
Conveying the excavated surplus earth with a lead of 10KMMR of by using tippers including loading, unloading, dumping in low lying areas spreading and leveling as shown by the departmental officers, etc., complete complying with standard specifications and as directed by the departmental officers.
Shoring, and Strutting with sheet piles of size width 400 mm x height of 5m x thickness of 9mm as per IS 2314-1986 by driving on both sides of the trench from Ground Level up to the required depth and connecting the above sheet piles by horizontal strutting with sheet piles at an interval of 1.0m, fixing the sheet piles by connecting the horizontal strutting with casurina poles of 8cm to 10cm dia at 1.50m interval and including removing the sheet piles after the pipelines are laid, jointed, tested, and stackingit safely for other uses. It includes the cost of sheet piles and casurina poles including labour charge for erecting the sheet piles, driving the sheet piles, removing the sheet piles, fixing casurina poles,etc., complete and all other incidental charges for the depths. 0 to 4 m
Supplying, providing and fixing chain link fencing 2"x2" using 10 guage Galvanised iron wire mesh of size 2.0 x1.50 metre over existing RCC Wall which is stiffened by horizontal MS flats (double flats) of size 30mm width x 6mm and fixed to MS ISA 75x75x8 mm of height 2.00 m c/c and fixed on the wall by concrete PCC M15 using 20mm of size 0.30m x0.30m x0.15m and welded to angles at site as directed by the department officer and drawing. The rates including welding, fixing, painting, labour charges for drilling RCC Wall work, concreting, ramming, consolidation, compacting, watering, curing etc complete complying with standard specifications and as directed by the departmental officers
Supplying and laying of ready mix for PCC M 30 grade of concrete having charaterstic strength not less than specified in the IS 456 - 2000 using Ordinary portland cement with minimum cement content of 300 Kg / cum confirming to IS 8112. Coarse aggregates having a specific gravity of 2.60 using 20 mm down graded hard blue granite broken stone jelly and fine aggregate without flyash as per IS 383 - 1970 ( 2007 ) with suitable water cement ratio not less than 0.45 and not exceeding 0.50 of water quality confirming to IS 456 - 2000 including use of plasticizer of approved make & dosage of required grade at all locations and levels with specified high workability as per IS 1199 - 1959 ( 2004 ). The initial & final setting time confirming IS 12269 - 1987 ( 2004 ) with maximum temperature of concrete at the time of placing should not exceed 32 0 C. The admixtures affecting the quality and strength of the concrete should not be used and should confirm IS 9103 - 1979 [ usual admixture - Air entraining & water reducing ].including the cost of hire charges for pump and pumping charges to the required locations & levels as specified by the Engineer - in - charge,. laying, compacting, consolidation by using vibrators,finishing, watering, curing, testing charges as per IS 456 - 2000, 4031 - ( Part 3 & 6 ) / 1988 ( 2005 ) & ( Part 2 ) / 1999 ( 2004 ) and 516 / 1959 ( 2004 ), 4926 - 1976 ( 1990 ), mix design details to be got approved before commencement of the work adopting pour card system and other OK cards. Excluding the cost of form works, centering and shuttering placed in position etc, complete complying with standard specifications and as directed by the departmental officers. (PCC work at site)
Supplying and Fixing of Man holes (SFRC) of 600 mm X 600mm all labours, tranportation, other necesssary equipment which is essential for fixing at site etc.,omplete, complying with standard specifications and as directed by the departmental officers of work.
Dewatering using 10HP diesel pumpset with suction and delivery pipe for required length as per the site conditions including cost of fuel and crew charges including Transportation etc and directed by the Departmental officers
Providing and laying Tack Coat over Dry Lean Cement Concrete surface using 3.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc. complete as perClause 503 of MORTH Rev-5
Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5
Providing and laying Bituminous Concrete to 30/40 mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36 mm and 0.26 cum of 2.36 mm and below and with 50.30 Kgs of VG 30 bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site , spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver at site etc , including hire charges and fuel charges for 20-30 ton CMP with bitumen boiler, tipper trucks, Paver Finisher, vibratory rollers and all other tools and plant required , including fuel and all other incidental charges etc., complete as per specification using CMP as per Clause 507 MoRTH Rev-5.
GST 18% IN FIGURES
PandC Projects Private Limited
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid