| 1 | L1₹26.4 LAccepted-AOC KONARK LANE PO ORIENT COLLIERY BRAJRAJNAGAR DIST JHARSUGUDA ODISHA 768233 | BRAJRAJNAGAR | JHARSUGUDA | ODISHA | 768233 | ₹26.4 L | L1 | Accepted-AOC L-1 Bidder |
| 2 | L-2₹27.0 L+₹63,822.94 (2.42%)Rejected-Finance AT PO RAMPUR COLLIERY PS BRAJRAJNAGAR DIST JHARSUGUDA ODISHA 768216 | BRAJRAJNAGAR | JHARSUGUDA | ODISHA | 768216 | ₹27.0 L+₹63,822.94 (2.42%) | L-2 | Rejected-Finance L-2 Bidder |
| 3 | L-3₹28.5 L+₹2.2 L (8.26%)Rejected-Finance AT ABHAYPUR PO ORIENT COLLIERY BRAJRAJNAGAR DIST JHARSUGUDA ODISHA 768216 | BRAJRAJNAGAR | JHARSUGUDA | ODISHA | 768216 | ₹28.5 L+₹2.2 L (8.26%) | L-3 | Rejected-Finance L-3 Bidder |
Tender Value
₹38.4 L
EMD Value
₹48,100
Closing Date
3 Mar 2026, 5:00 pmClosed
STAFF OFFICER(C),IB VALLEY AREA
SO(C), IB VALLEY AREA, MCL AT PO BRAJRAJNAGAR DIST JHARSUGUDA ODISHA. MOB NO9438493165
Renovation of Officers club Re-Joice Inn at Hiltop Colony of SOCP under Ib valley Area
2026_MCL_353633_1
MCL/GM/IBV/SOC/2025-26/68 dt. 19.02.2026
Open Tender
Civil Works - Others
Percentage
120 days
SOCP, IB Valley Area, MCL, Brajrajnagar
Please refer Tender documents.
3 documents required · 3 mandatory
₹48,100
5 Jul 2026
19 Feb 2026
5 Mar 2026
20 Feb 2026
3 Mar 2026
20 Feb 2026
20 Feb 2026 - 24 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. | 39.84 | cum | 217 | ₹8,645.28 |
| - | Brickwork with Fly Ash Brick (230x115x75 mm size) bricks of class designation 10 in foundation and plinth in: Brickwork with Fly Ash Brick (230x115x75 mm size)bricks of class designation 10 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) | 42.38 | cum | 5,457.4 | ₹2,31,286.79 |
| - | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4(1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20mm nominal size derived from natural sources) | 6.08 | cum | 6,048.05 | ₹36,741.9 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | 72.9 | sqm | 675.8 | ₹49,265.82 |
| - | Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50mm including strengthening with 2mm dia wire or nuts, bolts and washers asr equired complete as per the direction of Engineer-in-charge. Made of G.I. wire of dia 4 mm | 249 | sqm | 790.6 | ₹1,96,859.4 |
| - | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 2,619 | kg | 124 | ₹3,24,756 |
| - | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : Two or more coats on new work | 110.8 | sqm | 114.65 | ₹12,703.22 |
| - | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement :3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20mm nominal size derived from natural sources) | 52.61 | cum | 5,359.15 | ₹2,81,918.09 |
| - | Providing and laying 60mm thick factory made cement concrete interlocking paver block of M-30 grade made by block making machine with strong vibratory compaction, of approved size, design & shape, laid in required colour and pattern over and including 50mm thick compacted bed of coarse sand, filling the joints with lines and etc.all complete as per the direction of Engineer-in-charge. | 701.4 | sqm | 851.7 | ₹5,97,382.38 |
| - | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | 669.45 | sqm | 32.2 | ₹21,556.33 |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.49 MB
Tendernotice_2.pdf
PDF • 1.39 MB
BOQ_366443.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .