| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.0 CrAdmitted-Finance | ₹1.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.1 Cr+₹5.9 L (5.75%)Admitted-Finance | ₹1.1 Cr+₹5.9 L (5.75%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | J.Santhanam L1 | jayashree construction L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum | 1,575.8 | M3 | 76 ₹1,19,760.8 Lowest | 80.37 ₹1,26,647.05 |
| 2.00 | Removal of Excavated Excess Earth away from the site to 2K.M including loading and transportation charges etc, complete as per standard specification. For 1M3 | 945.48 | M3 | 67.15 ₹63,488.98 Lowest | 71.01 ₹67,139.6 |
| 3.00 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 308 | M3 | 4,983.7 ₹15,34,979.6 Lowest | 5,270.26 ₹16,23,240.93 |
| 4.00 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | 86.2 | M2 | 292.63 ₹25,224.71 Lowest | 309.46 ₹26,675.13 |
| 5.00 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - | 355.6 | M3 | 6,986.2 ₹24,84,292.72 Lowest | 7,387.91 ₹26,27,139.55 |
| 6.00 | Supply and fixing of 12mm thick Bitumen Pad to the required depth of good quality. The rate shall inclusive of all charges such as labour charges, cutting charges etc, complete as per standard specification | 89.1 | M2 | 479 ₹42,678.9 Lowest | 506.54 ₹45,132.94 |
| 7.00 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 432.4 | M3 | 1,959 ₹8,47,071.6 Lowest | 2,071.64 ₹8,95,778.22 |
| 8.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications | 5,764 | M2 | 78 ₹4,49,592 Lowest | 82.48 ₹4,75,443.54 |
| 9.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications | 5,764 | M2 | 17.3 ₹99,717.2 Lowest | 18.29 ₹1,05,450.94 |
| 10.00 | Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications. | 288.3 | M3 | 9,884 ₹28,49,557.2 Lowest | 10,452.33 ₹30,13,406.74 |
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
20 Jan 2023, 3:00 pmClosed
THE COMMISSIONER
AVADI CITY MUNICIPAL CORPORATION AVADI CHENNAI-54
Restoration of CC and BT Road at Westgopalapuram Main Road 4th (A) Cross Street , West Gopalapuram Main Road 4Th (B) Cross Street, Westgopalapuram Main Road 6Th Cross Street, Ramanujam Main Street, Rajaram Street, Anna Nagar 9Th Street
2023_MAWS_281373_1
Roc No 6383/2022/E1-7
Open Tender
Civil Works
Fixed-rate
90 days
Zone 4
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1.3 L
23 Jan 2023
12 Jan 2023
20 Jan 2023
12 Jan 2023
20 Jan 2023
12 Jan 2023
Amount
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum
Removal of Excavated Excess Earth away from the site to 2K.M including loading and transportation charges etc, complete as per standard specification. For 1M3
Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and Eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38
Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers -
Supply and fixing of 12mm thick Bitumen Pad to the required depth of good quality. The rate shall inclusive of all charges such as labour charges, cutting charges etc, complete as per standard specification
Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications
Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications.
Providing and laying Bituminous concrete to 30mm thick using 0.13 cum of 19.00-9.50 mm graded metal and 0.17 cum of 9.50-2.36 mm graded metal and 0.26 cum of 2.36 mm & below metal by adding theshredded plastic 10% of Bitumen quantity 5.03Kg (50.30x10%=5.03kg) shredded plastic waste over the aggregate heated to 170 degree celcious in the central hot mix plant, mixed well with 45.27 kgs of hot bitumen VG30 Bitumen (160 degree celcious) 60/70 grade for premixing per 10 sqm to lay 30mm complacted thick of bituminious concrete including the cost of materials and conveyance of all materials to CMP site, heating the bitumen and agregates to the required temperature and mixing the minimum required Temperature in central hot mix plant 20-30 tonnes capacity conveying the mix by tipper trucks to paver site, spreading the mix in required temperature for uniform thickness of 30mm with mechanical paver ( Hydrostatic Paver finisher with sensor control ) to the specified grades and cross sections and consolidated by 80-100 KN Vibratory Roller / Pneumatic roller to there required density etc., inclduing labour for loading bitumen in to bitumen tank and metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks paver finisher /9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plants required, including all other incidental charges etc., complete as per specification using CMP clause 507 of MORTH REV -5 specifications. and IRC SP 098 for palstic waste usage
jayashree construction
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.34 MB
BID-7.pdf
Tender Documents • 1.01 MB
BOQ_334320.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .