Tender ID
Tender Value
₹38.5 L
EMD Value
₹76,940
Closing Date
4 Apr 2026, 6:00 pmClosed
Executice officer
Municipal Board Pahari
Renovation and Construction Work for the Old (Hospital) Building of the Municipality Office
2026_DLB_548453_1
Enit35Mirman 2025-26
Open Tender
Civil Works
Percentage
60 days
Pahari
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
EXECUTICE OFFICER
₹76,940
Yes
4 Apr 2026
25 Mar 2026
7 Apr 2026
25 Mar 2026
4 Apr 2026
25 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-incharge.3.1.1 In cement mortar | 32.4 | CUM | 462.5 | ₹14,985 |
| 2 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. 4.10.1 In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. 4.10.1.1 Depth upto 1.5 m | 48.6 | CUM | 229.5 | ₹11,153.7 |
| 3 | Random rubble dry stone Kharanja (soling) under floor. | 10.8 | CUM | 2,270 | ₹24,516 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level 1:4:8 (1 Cement : 4 fine/ coarse sand : 8 graded stone aggregate 40 mm nominal size). | 15.4 | CUM | 4,575 | ₹70,455 |
| 5 | Random rubble masonry with hard stone in foundation and plinth : 25.1.1 Cement mortar 1:6 (1 cement : 6 coarse sand) | 48.6 | CUM | 4,860 | ₹2,36,196 |
| 6 | Reinforcement for R.C.C. work at all levels including straightening,cutting, bending, placing in position and binding all complete.Hot rolled deformed bars | 800 | kg | 83.3 | ₹66,640 |
| 7 | Centring and shuttering with plywood or steel sheet upto two stories( each story of height upto 3.5 metre from floor level) includingstrutting, propping etc. and removal of form for :
22.1.1 Foundations, footings, bases of columns, etc. for mass concrete. | 27.6 | SQM | 236.5 | ₹6,527.4 |
| 8 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement - All work upto plinth level :1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20
mm nominal size) | 6.21 | CUM | 6,340 | ₹39,371.4 |
| 9 | Extra for random rubble masonry with hard stone in superstructure above plinth level and upto two stories. | 48.6 | CUM | 5,830 | ₹2,83,338 |
| 10 | Cement plastering including T&P, scaffolding, material and complete labour, including cost of water, curing, racking of joints etc. with 20 mm cement plaster of mix : including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar 1:4 (1 cement : 4 fine/ coarse sand) | 716 | SQM | 315.5 | ₹2,25,898 |
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.10 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.63 MB
BOQ_977798.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .