Loading…
Loading…
Tender Value
₹56.1 L
EMD Value
₹70,100
Closing Date
17 Aug 2026, 11:30 am
STAFF OFFICER CIVIL NAGPUR AREA
OFFICE OF THE AREA GENERAL MANAGER NAGPUR AREA PO KASTURBA NAGAR JARIPATKA NAGPUR 440014
Development and maintenance of existing ETP including heightening of Washing Ramp and making of Settling Tank, Sludge Drying Shed and repairing of ETP at BOCM and SOCM under Bhanegaon Singhori Sub Area of Nagpur Area. (For 24 Months)
2026_WCL_362748_1
na3250-civ-e-tender 28-2026-27
Open Tender
Civil Works - Others
Percentage
820 days
BHANEGAON SINGHORI SUB AREA
AS PER NIT
5 documents required · 5 mandatory
₹70,100
30 Jul 2026
30 Jul 2026
18 Aug 2026
30 Jul 2026
17 Aug 2026
31 Jul 2026
30 Jul 2026 - 10 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50m and lift up to 1.5m,disposed earth to be levelled and neatly dressed. All kinds of soil | 122 | Cum | 136.95 | ₹16,707.9 |
| 2 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete | 30.5 | Cum | 2,191.15 | ₹66,830.08 |
| 3 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.All kinds of soil | 13 | Cum | 99.3 | ₹1,290.9 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | 18 | Cum | 6,309.15 | ₹1,13,564.7 |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size de rived from natural sources) | 25 | Cum | 7,974.6 | ₹1,99,365 |
| 6 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor five level excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size | 52.1 | Cum | 9,394.95 | ₹4,89,476.9 |
| 7 | Reinforced cement concrete work in beams, suspended foors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources). | 2.1 | Cum | 9,906 | ₹20,802.6 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level -Hot rolled deformed bars | 7,896 | Kg | 95.25 | ₹7,52,094 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete. | 30 | Sqm | 306.9 | ₹9,207 |
| 10 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | 23 | Sqm | 577.2 | ₹13,275.6 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.99 MB
BOQ_375672.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].