| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹18.8 LAccepted-AOC MAHANADI SOUTH DIVISION NO I CUTTACK | ₹18.8 L | L1 | Accepted-AOC Work order has been issued |
| 2 | L2₹21.1 LRejected-Finance | ₹21.1 L | L2 | Rejected-Finance Non-Responsive due to L2 Bidder |
| 3 | L3₹23.4 LRejected-Finance AT AT PO BASANDARA P S BIRIDI DIST JAGATSINGHPUR ODISHA | BHADRAK | ODISHA | 756121 | ₹23.4 L | L3 | Rejected-Finance Non-Responsive due to L3 Bidder |
| 4 | L3₹23.4 LRejected-Finance | ₹23.4 L | L3 | Rejected-Finance Non-Responsive due to L3 Bidder |
| 5 | L3₹23.4 LRejected-Finance | ₹23.4 L | L3 | Rejected-Finance Non-Responsive due to L3 Bidder |
Tender Value
₹23.4 L
EMD Value
₹23,500
Closing Date
16 Mar 2026, 5:30 pmClosed
Block Development Officer
O/o the Panchayat Samiti, Raghunathpur
Construction of office building with market complex for GPLF at Tarikunda
2026_PRBRP_126707_1
NOTICE NO.BDO-RPS-03 OF 2025-26
Open Tender
Civil Works - Buildings
Percentage
180 days
Raghunathur
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹23,500
Yes
7 Aug 2026
27 Feb 2026
17 Mar 2026
27 Feb 2026
16 Mar 2026
27 Feb 2026
27 Feb 2026 - 12 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0_) | Earth work in excavation of foundation in all kinds of soil including dressing and levelling the foundation bed and depositing the excavated materials clear of work site with all leads, lifts, delifts and dewatering & shoring including removing bushes, stumps and any other foreign materials from the working area as well as from the foundation trenches with cost of all labour, T&P, hire and running charges of all machineries, labour cess etc. complete in all respects as per specification and direction of the Engineer-in-Charge. | - | One Cum | - | - |
| 0_) | Filling in foundation & plinth with sand well watered to saturated condition in 23.20cm thick layers wtih watering & ramming including all cost, carriage, royalty, taxes of materials with all labour charges cess etc. complete as per the direction of the Engineer-in-Charge. | - | One Cum | - | - |
| 0_) | Cement Concrete (1:3:6) with 40mm size hard granite crusher broken metal confirming to relevant BIS specifications with all cost, conveyance, royalty of all materials T&P, cess including scaffolding, walkways & properly mixing, hoisting & placing concrete to desired workability & curing for recommended period etc. complete as per the direction of the Engineer-in-Charge. | - | One Cum | - | - |
| 0_) | Brick work with Fly ash Bricks masonry in dimensional tolerance ±8 percent in cement motar (1.6) in foundation & plinth moulding & similar such type of work with all necessary projections using K.B bricks 9"/10" size having a crushing strength of 87kg / sqcm with splays cutting circular moulding chamfering & cerbelling watering & after immersing the bricks in water for six hours before using etc. complete including all cost of materials conveyance, royalty and all other taxes including watering and curring etc. complete as per the direction of the Engineer-in-Charge. | - | One Cum | - | - |
| 0_) | Brick work with Fly ash Bricks masonry in dimensional tolerance ±8 percent in cement motar (1.6) in supersrtructure moulding & similar such type of work with all necessary projections using K.B bricks 9"/10" size having a crushing strength of 87kg / sqcm with splays cutting circular moulding chamfering & cerbelling watering & after immersing the bricks in water for six hours before using etc. complete including all cost of materials conveyance, royalty and all other taxes including watering and curring etc. complete as per the direction of the Engineer-in-Charge. | - | One Cum | - | - |
| 0_) | Cement Concrete M-20 with 20mm and downgraded size hard granite crusher broken chips for PCC / RCC work confirming to relevant BIS specifications for all materials including scaffolding, walkways & properly mixing, hoisting & laying with desired workability with all cost, conveyance, royalty of all materials, T&P labour charges, cess etc. complete including curring for recommended period as per the direction of the Engineer-in-Charge. (Column Base) | - | One Cum | - | - |
| 0.9_) | Plinth beam | - | One Cum | - | - |
| 0.0_) | Columns and Beams | - | One Cum | - | - |
| 0.9_) | Lintel | - | One Cum | - | - |
| 0.0_) | Roof Slab / Chajja | - | One Cum | - | - |
stage.html
html • 0.07 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
BID.pdf
Tender Documents • 19.73 MB
BOQ_583379.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].