| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹38.1 LAccepted-Finance | ₹38.1 L | L1 | Accepted-Finance lowest bidder |
| 2 | L2₹38.2 LRejected-Finance | ₹38.2 L | L2 | Rejected-Finance high |
| Sl No | Description | Qty | Unit | J NARAYANAN L1 | N SHILPA L2 |
|---|---|---|---|---|---|
| 1.00CONSTRUCTION OF 0.7 MT CAPACITY MICRO COMPOSITE CENTRE (MCC ) ,SHREADDING SHED AND STORAGE SHED AT PERIYAR NAGAR H/O KAGGUCHI | |||||
| 2.00 | Earth work excavation for foundation in hard stiff clay sand slit full depth including all etc complete complying with standard specification | 52.65 | cum | 369 ₹19,427.85 Lowest | 375 ₹19,743.75 |
| 3.00 | Providing Granular sub base using grade 1 materials of table 400-1 of morth with minimum CBR 30 spreading in un iform layer with mortor grader on prepared surface ,mix in by place method at OMC and compacting with vibratory roller | 19.97 | cum | 5,179 ₹1,03,424.63 Lowest | 5,185 ₹1,03,544.45 |
| 4.00 | Supply and filling foundation basement with filling sand layer of not more than 15cm thick | 2.7 | cum | 2,626 ₹7,090.2 Lowest | 2,630 ₹7,101 |
| 5.00 | Cement concrete 1:4:8 mix using 40mm gauge HBG metal for foundation including all etc complete complying with standard specification | 16.92 | cum | 7,541 ₹1,27,593.72 Lowest | 7,545 ₹1,27,661.4 |
| 6.00 | Providing Granolithic floor finish pattern of 25mm thick with pcc 1:2:4 using 10 to 12mm thick including all etc complete | 94.39 | cum | 213 ₹20,105.07 Lowest | 215 ₹20,293.85 |
| 7.00 | Supply and erecting steel centeringincluding necessary supports for plane surface for RCC work column pedestal plinth beam stairs including all etc complete | 105.47 | sqm | 1,474 ₹1,55,462.78 Lowest | 1,480 ₹1,56,095.6 |
| 8.00 | Reinforced cement concrete 1:1.5:3 using 20mm HBG jelly for all RCC work including all etc., complete complying with standar specification | 18.08 | cum | 12,047 ₹2,17,809.76 Lowest | 12,050 ₹2,17,864 |
| 9.00 | Supplying fabricating and placing the position of mild steel for all reinforced cement concrete work including all etc., complete complying with standard specification | 1.51 | MT | 1,06,371 ₹1,60,620.21 Lowest | 1,06,375 ₹1,60,626.25 |
| 10.00 | Brickwork in cement mortar 1:5 mix using country bricks ground of size 8 3/4 x 4 1/4 x2 3/4 including curing etc., complete complying with standard specification | 15.21 | CUM | 7,720 ₹1,17,421.2 Lowest | 7,725 ₹1,17,497.25 |
Tender Value
₹38.4 L
EMD Value
₹38,420
Closing Date
2 Mar 2026, 3:00 pmClosed
BLOCK DEVELOPEMENT OFFICER VP
BLOC DEVELOPEMENT OFFICE , UDHAGAI
CONSTRUCTION OF MCC BUILDING SHREDDING UNIT AND STORAGE SHED AT PERIYAR NAGAR KAGGUCHI
2026_RDTN_666233_1
MCC BUILDING KAGGUCHI PERIYAR NAGAR
Open Tender
Civil Works - Others
Fixed-rate
90 days
PANCHAYAT UNION UDHAGAI
AS PER TENDER NOTICE
3 documents required · 3 mandatory
₹0
₹38,420
Yes
BLOC DEVELOPEMENT OFFICE
7 Jul 2026
25 Feb 2026
2 Mar 2026
25 Feb 2026
2 Mar 2026
25 Feb 2026
26 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | CONSTRUCTION OF 0.7 MT CAPACITY MICRO COMPOSITE CENTRE (MCC ) ,SHREADDING SHED AND STORAGE SHED AT PERIYAR NAGAR H/O KAGGUCHI | - | - | - | - |
| 2 | Earth work excavation for foundation in hard stiff clay sand slit full depth including all etc complete complying with standard specification | 52.65 | cum | - | - |
| 3 | Providing Granular sub base using grade 1 materials of table 400-1 of morth with minimum CBR 30 spreading in un iform layer with mortor grader on prepared surface ,mix in by place method at OMC and compacting with vibratory roller | 19.97 | cum | - | - |
| 4 | Supply and filling foundation basement with filling sand layer of not more than 15cm thick | 2.7 | cum | - | - |
| 5 | Cement concrete 1:4:8 mix using 40mm gauge HBG metal for foundation including all etc complete complying with standard specification | 16.92 | cum | - | - |
| 6 | Providing Granolithic floor finish pattern of 25mm thick with pcc 1:2:4 using 10 to 12mm thick including all etc complete | 94.39 | cum | - | - |
| 7 | Supply and erecting steel centeringincluding necessary supports for plane surface for RCC work column pedestal plinth beam stairs including all etc complete | 105.47 | sqm | - | - |
| 8 | Reinforced cement concrete 1:1.5:3 using 20mm HBG jelly for all RCC work including all etc., complete complying with standar specification | 18.08 | cum | - | - |
| 9 | Supplying fabricating and placing the position of mild steel for all reinforced cement concrete work including all etc., complete complying with standard specification | 1.51 | MT | - | - |
| 10 | Brickwork in cement mortar 1:5 mix using country bricks ground of size 8 3/4 x 4 1/4 x2 3/4 including curing etc., complete complying with standard specification | 15.21 | CUM | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.01 MB
BOQ_800264.xls
BOQ • 0.31 MB
PRICEBID.pdf
Additional Documents • 0.55 MB
TECHBID.pdf
Tender Documents • 0.89 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].