Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹80.2 LAccepted-Finance | L1 | Accepted-Finance Accepted | |
| 2 | L2₹87.4 L+₹7.2 L (8.96%)Accepted-Finance 248 1 CHHEDIPURWA STATION ROAD BEHIND GURU NANAK SCHOOL GONDA UTTAR PRADESH 271001 | GONDA | UTTAR PRADESH | 271001 | L2 | Accepted-Finance Accepted | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹83.0 L
EMD Value
₹83,000
Closing Date
25 Aug 2023, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
se edc
sonbhadra
System strengthning (changing of damaged ABC)
2023_PVVNV_825985_1
66/edc(so)/2023-24
Open Tender
Electrical Works
Item Rate
90 days
sonbhadra
Pleased Ref Tender Doc.
2 documents required · 2 mandatory
₹3,540
SE EDC SONEBHADRA Bank A/c No.089105000853
₹83,000
4 Oct 2023
2 Aug 2023
26 Aug 2023
2 Aug 2023
25 Aug 2023
2 Aug 2023
Centralized Materials of following materials as per RESSPO/PuVVNL norms at the work site provided by Store Centar Robertsganj
ST pole 11 Mtr Long
PCC Pole 8.5 Mtr Long
ACSR Weasel conductor
ACSR Dog conductor
11 K.V. Pin Insulator With pin
11 K.V. Disc Insulator T&C Type 4500 Kg. With Fitting
Top Channel MS 125x65x2240 mm Long
M.S. Channel 125x65x1300 mm (T-off)
M.S.Channel Dropper 100x50x6mm 2028 mm Long
11 kv V Type X-arm
Stay Complete
Earthing Complete
LT AB Cable ( 1x120+1x95 +1X16)
LT AB Cable ( 1x95+1x70 +1X16)
3 PH Distribution box
Piercinig cable connector of size 120/95
Decenterlized Material Provided by Contractor
Cross Arm Holding Clamp With Nut & Bolt
F- Bracket With Nut & Bolt
Top, T- Off & Cross Brassing Asngle Clamp With Nut & Bolt
Nut & Bolt per of all size
Clamp for LT Etc.
Suspension clamp for LT with I hook
Dead end clamp for LT with I hook
Work of following material as per Respo/Puvvnl norms at the work site.
Erection of single support ST/PCC pole for construction of 11 KV line including digging of pit, fitting of all accessories, back filling of earth , Grouting of the Poles & others required work.
Earthing of Poles
Stay Complete
Stringing & sagging of 3 phase 11 KV line upto proper sag including laying of ACSR weasel Conductor, binding with insulators & jumpering.
Stringing & sagging of 3 phase 11 KV line upto proper sag including laying of Dog weasel Conductor, binding with insulators & jumpering.
Installation of 11 K.V. Pin Insulator With pin
Installation of 11 K.V. Disc Insulator T&C Type 4500 Kg. With Fitting
Installation of Top Channel MS 125x65x2240 mm Long
Installation of M.S. Channel 125x65x1300 mm (T-off)
Installation of M.S.Channel Dropper 100x50x6mm 2028 mm Long
Installation of 11 kv V Type X-arm
Installation of LT AB Cable ( 1x120+1x95 +1X16)
Installation of LT AB Cable ( 1x95+1x70 +1X16)
Installation of 3 PH Distribution box
Installation of Piercinig cable connector of size 120/95
M/S SMM INFRATECH PVT Ltd
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .