Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹2.4 LAccepted-Finance | 1 | Accepted-Finance L1 | |
| 2 | 2₹2.9 L+₹50,626.40 (21.4%)Accepted-Finance | 2 | Accepted-Finance L2 | |
| 3 | 3₹2.9 L+₹54,443.25 (23.1%)Accepted-Finance | 3 | Accepted-Finance L3 |
Tender Value
₹2.8 L
EMD Value
₹5,638
Closing Date
1 Aug 2022, 12:00 pmClosed
Executive Engineer
O/o the Executive Engineer, Construction Division, APWD, Campbell Bay
Providing Barbed Wire Fencing to the land allotted in favour of A and N Police Radio, Campbell Bay
2022_APWD_6749_1
DB-Quot/CD/CB/2022-23/1093
Open Tender
Civil Works - Others
Item Rate
60 days
CD, APWD, Campbell Bay
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹5,638
8 Aug 2022
25 Jul 2022
3 Aug 2022
25 Jul 2022
1 Aug 2022
25 Jul 2022
25 Jul 2022 - 28 Jul 2022
Amount
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil.
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources: 6 graded stone aggregate 40 mm nominal size derived from natural sources).
1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources).
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, ifnishing and reinforcement- All work up to plinth level :
1:1.5:3 (1 cement: 1.5 coarse sand (zone-III) derived from natural sources: 3 graded stone aggregate 20 mm nominal size derived from natural sources).
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement
1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources).
Centering and shuttering including strutting, propping etc. and removal of form for
Foundations, footings, bases of columns, etc. for mass concrete
Columns, Pillars, Piers, Abutments, Posts and Struts
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.
In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works
12 mm cement plaster of mix :
1:4 (1 cement: 4 fine sand)
Finishing walls with water proofing cement paint of required shade :
New work (Two or more coats applied @ 3.84 kg/10 sqm)
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :
Two or more coats on new work
Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to give an even shade :
Two or more coats on new work
Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used.
With G.I. barbed wire
Supplying at site Angle iron post & strut of required size including bottom to be split and bent at right angle in opposite direction for 10 cm length and drilling holes upto 10 mm dia. etc. complete.
Zakir Hussain
M/S G S GREWAL
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .