| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹22.6 LAdmitted-Fee/PreQual/Technical/Finance | -10.30% | ₹22.6 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹25.2 L+₹2.6 L (11.5%)Admitted-Fee/PreQual/Technical/Finance AL NUAGAON GP BADAMBILA PO NAMAUZA PS AUL DIST KENDRAPARA PIN 754231 | KENDRAPARA | ODISHA | 754231 | +0.00% | ₹25.2 L+₹2.6 L (11.5%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L2₹25.2 L+₹2.6 L (11.5%)Admitted-Fee/PreQual/Technical/Finance AT HARIPUR ROAD P O BUXIBAZAR DIST CUTTACK | +0.00% | ₹25.2 L+₹2.6 L (11.5%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 4 | L2₹25.2 L+₹2.6 L (11.5%)Admitted-Fee/PreQual/Technical/Finance MAHANADI SOUTH DIVISION NO I CUTTACK | +0.00% | ₹25.2 L+₹2.6 L (11.5%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 5 | L2₹25.2 L+₹2.6 L (11.5%)Admitted-Fee/PreQual/Technical/Finance | +0.00% | ₹25.2 L+₹2.6 L (11.5%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹25.2 L
EMD Value
₹25,300
Closing Date
10 Jul 2026, 5:00 pmClosed
Executive Engineer,Div-II
Bikash Bhawan,Jagannath Lane,Badambadi-753012
Renovation of Mangalabag SUH at Mallha Sahi in Ward No.34.
2026_ORULB_131619_5
MC(CMC)CTC_Div-IINo15/2026-27
Open Tender
Civil Works - Others
Percentage
90 days
CMC
Please refer Tender documents.
2 documents required · 2 mandatory
₹7,080
₹25,300
Yes
16 Jul 2026
1 Jul 2026
15 Jul 2026
1 Jul 2026
10 Jul 2026
1 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling and removing 2.5 cm thick grading concrete from roof slab cleaning the surface lowering and removing the debris within 50m lead. | 170.35 | Sqm | 132.6 | ₹22,588.41 |
| 2 | Removing old lime or cement plaster from walls including raking out joints 12 mm deep and removing the debris within 50m lead | 311.35 | Sqm | 58.9 | ₹18,338.52 |
| 3 | Scrapping, cleaning old paint / distemper wall with scrapers and papering, washing soap or soda water etc complete. | 431.82 | Sqm | 5.12 | ₹2,210.92 |
| 4 | Scrapping, cleaning old paint / distemper wall with scrapers and papering, washing soap or soda water etc complete. | 146.41 | Sqm | 7.01 | ₹1,026.33 |
| 5 | Dismantling and removing 2.5 cm.thick artificial stone flooring including stacking the useful materials for reuse and removing the debris within 50m lead etc. Complete. | 11.38 | Sqm | 117.9 | ₹1,341.7 |
| 6 | Dismantling and removing old tiled flooring including removing the base coarse and stacking the useful materials for reuse and removing the debris within 50m lead | 258.6 | Sqm | 147.4 | ₹38,117.64 |
| 7 | Dismantling and removing old tiled cladding from walls including racking out joints 12mm deep and stacking the useful materials for reuse and removing the debris within 50m lead. | 156 | Sqm | 76.6 | ₹11,949.6 |
| 8 | Dismantling brick or stone masonry in lime or cement mortar under 3m. height including stacking the useful materials for reuse and removing the debris within 50m. Lead as per the direction of engineer in charge. | 3 | Cum | 1,137.3 | ₹3,411.9 |
| 9 | Earth work in all kinds of soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulder requiring blasting with all leads and lifts including dressing and leveling the bed sides up to required depth and depositing the excavated materials at places away from the work site with all leads and lifts, T&P for shoring shuttering dewatering if required etc. complete as per the drawing, designing including cost of all labour, T&P etc. as required for the work complete as directed by the Engineer-in-charge. | 43.5 | Cum | 306 | ₹13,311 |
| 10 | Supplying and filling the foundation and plinth with clean coarse river sand of approved quality from approved quarry, laying in layers not exceeding 150mm thick, watering and ramming including cost, conveyance royalty and taxes of all materials, cost of all labour, T&P etc. as per the direction of engineer in charge. | 10.1 | Cum | 541.4 | ₹5,468.14 |
stage.html
html • 0.03 MB
finance_599195.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.15 MB
BOQ_599195.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .