| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.7 LAccepted-AOC | L1 | Accepted-AOC Agreement With L1 | |
| 2 | L2₹14.8 L+₹9,601.96 (0.65%)Rejected-Finance | L2 | Rejected-Finance Agreement With L1 | |
| 3 | L3₹15.9 L+₹1.3 L (8.52%)Rejected-Finance | L3 | Rejected-Finance Agreement With L1 | |
| 4 | Rejected-Technical | - | Rejected-Technical Reject |
| Sl No | Description | Qty | Unit | VK CONSTRUCTION L1 | M/S SHREE JEE CONSTRUCTIONS L3 | KISAAN EICHER TRACTORS L2 |
|---|---|---|---|---|---|---|
| 1.00 | Dismantling reinforced cement concrete including stacking of material, labour, T&P etc. complete. | 4.16 | CuM. | 630 ₹2,620.8 | 50 ₹208 Lowest | 520 ₹2,163.2 |
| 2.00 | Dismantling brick work or stone work and cement concrete incement mortar & including stacking of materialas material, labour, T&P etc. complete. | 8.01 | CuM. | 500 ₹4,005 | 50 ₹400.5 Lowest | 450 ₹3,604.5 |
| 3.00 | Earth work in foundation in all types of soil including all lift and all lead and including filling, watering and ramming excavated earth into the trenches or into the space between the structure and the sides of foundation trenches or into the plinth with removal and disposal of surplus earth as directed by the Engineer-in-charge. | 111.74 | CuM. | 50 ₹5,587 Lowest | 50 ₹5,587 Lowest | 80 ₹8,939.2 |
| 4.00 | Providing & laying C.C. 1:2:4(M-15) with cement, coarse sand & aggregate (25mm to 10mm) i/c all cost of material, labour T&P etc complete (Per CuM.) | 21.21 | CuM. | 5,600 ₹1,18,776 | 4,500 ₹95,445 | 4,000 ₹84,840 Lowest |
| 5.00 | Providing & laying C.C. 1:1.5:3(M-20) with cement, coarse sand & aggregate (25mm to 10mm) i/c all cost of material, labour T&P etc complete (Per CuM.) | 52.45 | CuM. | 5,800 ₹3,04,210 | 7,000 ₹3,67,150 | 5,400 ₹2,83,230 Lowest |
| 6.00 | Providing & laying R.C.C. 1:1:2 (M-25) with cement, coarse sand & aggregate (25mm to 10mm) and also excluding centering and shuttering and reinforcement i/c all cost of material, labour T&P etc complete (Per CuM.) | 69.39 | CuM. | 7,050 ₹4,89,199.5 | 7,000 ₹4,85,730 Lowest | 7,000 ₹4,85,730 Lowest |
| 7.00 | Providing & laying 1st class (M-150) brick work with 1:4 cement mortar using cement and coarse snad including cost of all material, T&P & labours complete (Per CuM.) | 13.59 | CuM. | 4,300 ₹58,437 | 5,500 ₹74,745 | 4,000 ₹54,360 Lowest |
| 8.00 | Providing Cement pointing (Flush) on brick masonary in 1:2 Cement Mortar including cost of all material, T&P & labours complete( per SqM.) | 52.34 | SqM. | 50 ₹2,617 Lowest | 100 ₹5,234 | 80 ₹4,187.2 |
| 9.00 | Centering and shuttering for RCC/RB work including cost of centering & shuttering up to 3.0m height. including cost of all material, T&P & labours complete( per SqM.) | 147.11 | SqM. | 250 ₹36,777.5 Lowest | 700 ₹1,02,977 | 680 ₹1,00,034.8 |
| 10.00 | Supplying & Laying TMT Steel bar Reinforcement (Fe 550D) including removing of rust, cutting, binding with 24BWG wire, bending, placing with proper overlapping providing chair i/c all cost of material, labour, T&P etc. complete (per M.T.) | 5.48 | M.T. | 66,000 ₹3,61,680 | 76,000 ₹4,16,480 | 65,000 ₹3,56,200 Lowest |
Tender Value
₹20.1 L
EMD Value
₹40,280
Closing Date
14 Oct 2026, 11:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Executive Engineer
OFFICE OF THE EXECUTIVE ENGINEER ANOOPSHAHAR BRANCH DIVISION GANGA CANAL MEERUT
TN-08/EE/2026-27 Reconstruction of the damaged bridge (box culvert) located at Km 4.785 of Bahadurgarh Rajwaha. LOT-06
2026_UPIDC_1192818_6
TN-08/E.E/2026-27
Open Tender
Civil Works
Piece-work
90 days
As Per NIT
As per NIT and TD
3 documents required · 3 mandatory
₹944
₹40,280
6 Nov 2026
5 Oct 2026
14 Oct 2026
5 Oct 2026
14 Oct 2026
5 Oct 2026
90 days
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling reinforced cement concrete including stacking of material, labour, T&P etc. complete. | 4.16 | CuM. | - | - |
| 2 | Dismantling brick work or stone work and cement concrete incement mortar & including stacking of materialas material, labour, T&P etc. complete. | 8.01 | CuM. | - | - |
| 3 | Earth work in foundation in all types of soil including all lift and all lead and including filling, watering and ramming excavated earth into the trenches or into the space between the structure and the sides of foundation trenches or into the plinth with removal and disposal of surplus earth as directed by the Engineer-in-charge. | 111.74 | CuM. | - | - |
| 4 | Providing & laying C.C. 1:2:4(M-15) with cement, coarse sand & aggregate (25mm to 10mm) i/c all cost of material, labour T&P etc complete (Per CuM.) | 21.21 | CuM. | - | - |
| 5 | Providing & laying C.C. 1:1.5:3(M-20) with cement, coarse sand & aggregate (25mm to 10mm) i/c all cost of material, labour T&P etc complete (Per CuM.) | 52.45 | CuM. | - | - |
| 6 | Providing & laying R.C.C. 1:1:2 (M-25) with cement, coarse sand & aggregate (25mm to 10mm) and also excluding centering and shuttering and reinforcement i/c all cost of material, labour T&P etc complete (Per CuM.) | 69.39 | CuM. | - | - |
| 7 | Providing & laying 1st class (M-150) brick work with 1:4 cement mortar using cement and coarse snad including cost of all material, T&P & labours complete (Per CuM.) | 13.59 | CuM. | - | - |
| 8 | Providing Cement pointing (Flush) on brick masonary in 1:2 Cement Mortar including cost of all material, T&P & labours complete( per SqM.) | 52.34 | SqM. | - | - |
| 9 | Centering and shuttering for RCC/RB work including cost of centering & shuttering up to 3.0m height. including cost of all material, T&P & labours complete( per SqM.) | 147.11 | SqM. | - | - |
| 10 | Supplying & Laying TMT Steel bar Reinforcement (Fe 550D) including removing of rust, cutting, binding with 24BWG wire, bending, placing with proper overlapping providing chair i/c all cost of material, labour, T&P etc. complete (per M.T.) | 5.48 | M.T. | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.18 MB
Tendernotice_2.pdf
PDF • 1.99 MB
BOQ_2251492.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .