Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹3.0 Cr
EMD Value
₹6.1 L
Closing Date
8 Dec 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
Above/Below/Par
TECH SIG
17 conditions · 2 needing a document upload
: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less, where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderer shall submit requisite information as per Annexure-VIII given in tender document, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. As per Clause No. 10.2 of Tender Form (second Sheet) of Annex. I of Part-I of GCC-2022, with up to date correction slip.
If the tenderer submits/ upload Audited Balance sheet duly certified by a chartered accountant to fulfill the Standard Financial Criteria, the tenderer may also submit/ upload Form No. 26AS /16A along with the tender offer to certify the amount of contractual receipt.
(a) The tenderer must have successfully completed or substantially completed any of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii)One similar work each costing not less than the amount equal to 60% ofadvertised value of the tender. (b) (1) In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii)One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender.
Note for b(1): Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components. (b) (2) In such cases, what constitutes a component in a composite work shall be clearly pre-defined with estimated tender cost of it, as part of the tender documents without any ambiguity. (b) (3) To evaluate the technical eligibility of tenderer, only components of work as stipulated in tender documents for evaluation of technical eligibility, shall be considered. The scope of work covered in other remaining components shall be either executed by tenderer himself if he has work experience as mentioned in clause 7 of the Standard General Conditions of Contractor through subcontractor fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract or jointly i.e., partly himself and remaining through subcontractor, with prior approval of Chief Signal & Telecom Engineer in writing. However, if required in tender documents by way of Special Conditions, a formal agreement duly notarised, legally enforceable in the court of law, shall be executed by the main contractor with the subcontractor for the component(s) of work proposed to be executed by the subcontractor(s), and shall be submitted along with the offer for considering subletting of that scope of work towards fulfillment of technical eligibility. Such subcontractor must fulfill technical eligibility criteria as follows: The subcontractor shall have successfully completed at least one work similar to work proposed for subcontract, costing not less than 35% value of work to be subletted, in last 5 years, ending last day of month previous to the one in which tender is invited through a works contract. Note: for subletting of work costing up to Rs 50 lakh, no previous work experience of subcontractor shall be asked for by the Railway. In case after award of contract or during execution of work it becomes necessary for contractor to change subcontractor, the same shall be done with subcontractor(s) fulfilling the requirements as per clause 7 of the Standard General Conditions of Contract, with prior approval of Chief Signal & Telecom Engineer in writing.
Note: A work experience certificate from a private individual shall not be considered. However, in addition to work experience certificates issued by any Govt. Organization, work experience certificate issued by Public listed company having average annual turnover of Rs 500 crore and above in last 3 financial years excluding the current financial year, listed on National Stock Exchange or Bombay Stock Exchange, incorporated/registered at least 5 years prior to the date of closing of tender, shall also be considered provided the work experience certificate has been issued by a person authorized by the Public listed company to issue such certificates. In case tenderer submits work experience certificate issued by public listed company, the tenderer shall also submit along with work experience certificate, the relevant copy of work order, bill of quantities, bill wise details of payment received duly certified by Chartered Accountant, TDS certificates for all payments received and copy of final/last bill paid by company in support of above work experience certificate. As per Clause No. 10.1 of Tender Form (second Sheet) of Annex.I of Part-I of GCC-2022, with up to date correction slip
Defination of Similar Work :- Any RRI/PI/EI/MACLS Supply, Installation Testing, Commissioning Signalling work OR Any RRI/PI/EI/MACLS Alterations Signalling work OR Any CTC/TMS Work
16 conditions · 5 needing a document upload
The tenderer must opt for payment by letter of credit (LC) as per the Railway Board's letter no. 2018/CE-I/CT/9 dated 04.06.18.
Tenderers are required to quote their Permanent Account Number in the tender document.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
No garbage, dry leaves, paper, grass, bushes, or any other items shall be burnt. They shall only be disposed of at the nominated disposal point by prescribed methods, duly observing the Municipal Solid Wastes (Management and Handling) Rules, 2000 indicates under Schedule II- Management of Municipal Solid Wastes: Para I.I vii that Waste(garbage, dry leaves) shall not be burnt. Any violation of the provisions of the MSW rules,2000, attracts the penal provisions of the Environment(Protection) ACT,1986.CPCB and SPCBs have also issued various guidelines/orders against the practice of such open burning. If the contractor or anybody deployed by him for this work is found guilty of unregulated open burning of plastic, rubber, waste, and similar substances, a fine of Rs. 5000/- on each occasion shall be imposed in addition to the other rights and remedies available in the contract. The decision of the Engineerin-Charge shall be final and binding in this regard.
The EI alteration work is to be done at the GAMI, KSI, JKZ & STNL stations within the jurisdiction of SSE/Sig/BNW of the Bikaner Division. The EI alteration work is related to the provision of Track Machine Siding. The Mini-Plan of the GAMI, KSI, JKZ & STNL stations is attached to the document. EI OEM of KSI & JKZ stations - M/s SIEMENS RAIL AUTOMATION PVT LTD-BANGALORE. EI OEM of GAMI & STNL stations - M/s HITACHI RAIL STS INDIA PRIVATE LIMITED - BANGALORE.
machine siding at KSI, JKZ, GAMI & STNL stations under the Jurisdiction of SSE/Sig/BNW and shifting of S&T utilities for extension of existing TMS siding at various stations over Bikaner Division"
SnT-BKN-2026-27-25R~NWR
SnT-BKN-2026-27-25R
Open
Works - General
12 Months
Bikaner, Rajasthan
₹0
₹6.1 L
13 Nov 2026
13 Nov 2026
24 Nov 2026
202 items across 15 schedules · ₹2,03,14,362.43 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| manufacture and supply of Hot Architecture Electronic (EI) system complete as per specification No. RDSO/SPN/192/2019 Ver. 2 or latest, as technical requirement & tentative Signalling Plans & Diagrams. n i c Interlocking (EI) system consisting of Central Processing Interface Equipment/Relays per requirements, Dual operator Grade VDU panel (42" LED) Redundancy (Hot stand-by dual Normally one system online and system in standby mode), All Relays suitable for EI, cables and Jumper Industrial grade maintenance (32'' LED with UPS minimum 1 up), required power supply for EI equipments, Housing equipments and Relay Racks, screw less disconnecting type fixture mounting and accessories to make the EI system as per approved signaling The tenderer should furnish details of cards/ modules/ sub- connectors etc. for each Supply of 10% Essential spares equipments subject to minimum each type mainly consisting of cards/ module, interface relay wise detailed break up with quantity to be provided in annexure. (THIS ITEM SHALL BE ONLY FOR ALTERTION WORK IN EI) Inspection: RDSO charges: Borne by Railways terms:100% after Supply. | — | — | — | — | |
| 1 | with routes less than 100(Per be read as Per Vital Bit of | Per Unit | 80.00 | 87,987.65 | 70,39,012 |
| 2 | wiring, programming, and commissioning of EI supplied as per supply item no. 1.7 above of Chapter 1 of this including transportation from depot to site. The works and for installation, wiring, testing commissioning, grouting, cutting of walls, refilling of the same, re- required CC/ masonry works, placing/ laying of insulated casing-capping/ cable trays/ pipes / Cables, termination of with lugs/ connectors, painting,/ are to be provided/ done by the for the equipments supplied no. 7 of Chapter 1 of SOR. This the networking of built in EI loggers of all the stations to the system to any other places desired by Engineer-in-charge. ITEM SHALL BE USED ONLY FOR WORK IN EXISTING EI) Note: shall be comply to RDSO Advisory Note No dtd. 28.08.2014. wiring, programming, and commissioning of Operator Hot stand-by with Redundancy. Equipments/cards/Modules required stand-by with Redundancy shall supplied & Installed by the Note:- This also includes of Two nos. of composite & printer table (Godrej work table) and one no Godrej make chair model PCH7001. of indoor/ PIJF cables in room on relays, tag blocks, CT per approved wiring diagram alterations/ modifications as at site. Soldering to be done at termination. Dressing/ lacing shall be done neatly with help thread / plastic self lock strip size. The tools/ equipments/ simulation boards required for shall be supplied / fabricated by This includes replacement of cards/ LEDs/ equipments going during testing. Necessary supply boards with required plugs, sockets, surge & protection boxes shall be and installed by the contractor. supply shall be arranged by In case supplies are required extended, from Power room / relay then same shall be extended by contractor with his own materials 1X16 sq mm wires, cables, lugs, pipes, insulated ladders etc. ST/LT testing, Factory Acceptance (FAT) & Square Sheet testing should be fault free while to Railways, otherwise necessary action can be taken Engineer-in-charge. Inspection: Inspection charges: None terms: 100% after | Job | 4.00 | 5,42,784.93 | 21,71,139.72 |
| 3 | of work station note book as per Specifications . It also includes of Laser Printer (Only branded). workstation should be capable of the system in case of any in yard interlocking in future. Specifications should be with the tender document by authority. Inspection: Inspection charges: None terms: 100% after supply | Station | 1.00 | 86,892.73 | 86,892.73 |
| 4 | preparation & supply of in computer print copies and tracing in AUTO CAD FORMAT for Interlocking at each station. completion of the work, the drawings incorporating details are to be supplied as Technical Specifications given in document (upto 6 Line). The specifications are as per 1.13 of SOR. Inspection: Inspection charges: None terms: 100% after execution | Station | 4.00 | 1,75,967.35 | 7,03,869.4 |
| 5 | of SWR literature in english associated mid-section gate with all corrections as approved SWRD & approved SIP. For technical corrections, editing, correction etc. are to be out and one rough print to be railways for approval before as required for final processing sanction. This also includes of maintenance cards in provided by Rly. Inspection: Inspection charges: None terms:100% after execution. | Station | 4.00 | 3,598.62 | 14,394.48 |
| 6 | of Station Working Rules english to hindi and framing out in form (or similar software )as per Rly practice. The required SWR in will be provided by the and has been covered in item no. 1.21 of Chapter 1 SOR. Inspection: Consignee charges: None Payment after execution. | Station | 4.00 | 4,478.18 | 17,912.72 |
| 7 | photocopies & binding of the literature in English/hindi/Diglot per Railway practice. Inspection: Inspection charges: None terms:100% after execution. | Set | 24.00 | 178.52 | 4,284.48 |
| 8 | Addition/alteration in existing relay room It includes supply of PVC indoor Railway signallingcable @40<45@Core/40-Core) of (1/0.6) per RDSO Spec.No.IRS/S-76/89 or latest) for wiring room and SM's/Panel room room to DP in SM office for block This also includes supply of jumper wires of multi 16/.2 mm, tinned in all colours as Specn.No.IRS-S-76/89(Amnd.2 This item will include bringing power supplies from power room respective bus bars on relay racks 10/6 sqmm copper flexible wire instructions of engineer incharge. will include wiring between and relay room if required. will be done as per standard of North Western Railway with & threading. The item supply & wiring of tag block, bases(G-Type and ND Type) other related material required complete indoor wiring in relay room.Inspection: ConsigneeInspection NonePayment terms:100% commissioning. | Per Relay | 110.00 | 524.1 | 57,651 |
| Schedule total | ₹1,00,95,156.53 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
EITAN300702.11.2012.pdf
ATTACHMENT
EITAN301210.08.2016.pdf
ATTACHMENT
EITANoncybersecurity.pdf
ATTACHMENT
Mini-PlanSTNL.pdf
ATTACHMENT
Mini-PlanKSI.pdf
ATTACHMENT
Mini-PlanJKZ.pdf
ATTACHMENT
GAMIPlan.pdf
ATTACHMENT
25R.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .