Tender Value
₹8.3 Cr
EMD Value
₹19.4 L
Closing Date
28 Sept 2026, 3:00 pmDue tomorrow
Superintending Engineer 14 th Circle Rohru
Superintending Engineer 14 th Circle Rohru
SH C/o R/walls, B/walls, providind laying M/T, V-shape drain, X-drainage work, oridinary km stone 200 mm stone etc.) and five year maintenance
2026_CEHP_149616_1
SE-XIV-6165-6264DT16-09-26
Open Tender
Civil Works - Roads
Percentage
365 days
ROHRU
Please refer Tender documents.
15 documents required · 15 mandatory
₹10,000
₹19.4 L
23 Sept 2026
23 Sept 2026
28 Sept 2026
23 Sept 2026
28 Sept 2026
23 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in earthwork in hilly area all height and depths,in all kind of soil including saturated soil including saturated soil comprising of mixed soil,ordinary rock and hard rock.All work of rock cutting by blasting shall be carried out by taking all necessary precautions against soil erosion,damage to hill side,water pollition,etc.and to protect stability of hill side.Rock shall be excavated with chiseling and wedging out rock (where blasting is prohibited).All earth work in cutting/excavation,including rock excavation shall be carried out true to lines,grade,side slopes,width,camber,super-elevation and level as shown on the drawing or as directed by the Engineer-in-charge,in conformity with the requirement of technical specification for Rural Road,August,2004 and clause 16.2 of General Conditions for contract to achive designed formation width including hauling and stacking of material useful for construction at suitable sites and safe disposal of unsuitable cut materials in specified manner,trimming,filling of unevenness,blindage and finishing of the road to specified dimensions or as directed by the Engineer-in charge for smooth riding.The recovery of useful stone that is 4487.92 cum.( cubic Metre) in all cases,failing which recovery @ Rupees 170/= only(Rupees one hundred seventy only) per cubic meter shall be effected on pro rata basis.Any loss to the public and private property during the course of excavation shall be the absolute responsibility of the contractor,which shall have to be duly compensated by him in all cases. | 1,842 | Per cubic metre | 316.06 | ₹5,82,182.52 |
| 2 | Excavation in hilly area by Mechanical means i/c cutting and trimming of side slopes and disposing of excavated earth with a lift upto 1.50 m and leads upto 20m as per technical specification clause 1603.1 | 450 | Per cubic metre | 256.38 | ₹1,15,371 |
| 3 | Earth work in excavation for structures in all depths as per drawing and technical specification for rural roads August 2004 clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal in all lead and lift including dressing of sides and bottom and back filling in trenches with excavated Suitable materials. All work of rock cutting by blasting shall be carried out by taking all necessary precautions against soil erosion damage to hill side water pollution etc. and to protect stability of hill side rock shall be excavated with chiseling and wedging out rock(where blasting is prohibited).all earth work in cutting/excavation including rock excavation shall be carried out true to lines grades, side slopes, width, camber super elevation and level as shown on the drawings or as directed by the Engineer-in-Charge hauling and stacking of materials useful for construction at suitable sites and safe disposal of unsuitable cut materials in specified manner treaming filling of unevenness blind age and finishing of the road to specified dimension or as directed by the Engineer -in-Charge. | 1,000 | Per cubic metre | 496.31 | ₹4,96,310 |
| 4 | Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301 including hauling of materials in all leads,lifts as per entire satisfaction and direction of Engineer- in- charge. | 195.31 | Per cubic metre | 3,342.38 | ₹6,52,800.24 |
| 5 | Providing and laying concrete Mechanically mixed and vibrated P.C.C. M-10 nominal mix 1:3:6 (one cement : three sand: six graded stone aggregate 40mm forty millimeter) nominal size for plain /reinforced concrete in open foundations and plinths or similar works complete as per drawings and technical specification for rural roads August 2004 clause 802, 803, 1202 and 1203 and curing complete including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 100 | Per cubic meter. | 7,979.59 | ₹7,97,959 |
| 6 | Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 | 50 | NOS | 255.4 | ₹12,770 |
| 7 | Providing and laying filter media with granular crushed aggregate as per specification to a thickness of not less than 600 mm. (Six hundred millimeters) with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment wing wall return walls, to the full height compacted of firm condition complete as per drawing and technical specification rural roads August 2004 (Two thousand Four),clause 1204.3.8 (One thousand Two hundred Four point three point four) including hauling of materials in all leads and lifts as per entire satisfaction and direction of Engineer-in- Charge | 10 | Per cubic meter. | 1,695.7 | ₹16,957 |
| 8 | Providing and laying plain cement concrete mechanically mixed and vibrated PCC M-15 nominal mix 1:2.5:5 {(one cement: two and half sand: five graded hard stone aggregate 40 mm.(twenty millimeter) nominal size for plain concrete in foundations and plinths or similar works complete as per drawings and technical specification for rural roads August 2004 clause 802, 803, 1202 and 1203 and curing complete including the cost of form work and hauling of in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 60 | Per cubic meter. | 7,887.72 | ₹4,73,263.2 |
| 9 | Providing and laying reinforced cement concrete pipe NP2 900mm dia for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets Clause 1106. Including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 7.5 | RMT | 6,087.67 | ₹45,657.53 |
| 10 | Construction of subgrade and earthen shoulders with approved material obtained from burrow pits with all lifts and lead transporting to site spreading garding to required slope and compacted to meet reqiurement of table 300.2 with lead upto 1000 m as per technical specs. clause 303.1 Including the cost of form work and hauling of materials in all leads and lifts as per the entire satisfaction and direction of Engineer-in-Charge. | 4,275 | Per metric tonne. | 187.34 | ₹8,00,878.5 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.08 MB
DNIT450Final.pdf
Tender Documents • 1.51 MB
BOQ_235887.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .