| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.7 CrAccepted-AOC PLOT NO 5 SATHYAM GARDEN UYIRIYAL POONGA ROAD GORIMEDU SALEM 636 008 | SALEM | SALEM | TAMIL NADU | 636008 | ₹2.7 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹3.1 CrRejected-Finance 002 1 NATHAKADU SRI MAHALAKSHMI DYEING PRINTING MILLS CAMPUS BHAVANI MAIN ROAD ERODE 638004 | ERODE | ERODE | TAMIL NADU | 638004 | ₹3.1 Cr | L2 | Rejected-Finance L2 |
| 3 | L3₹3.5 CrRejected-Finance | ₹3.5 Cr | L3 | Rejected-Finance L3 |
| Sl No | Description | Qty | Unit | MANICKAVASAGAM L3 | Vidhyut Nirman Corporation L2 | RAJ ENGINEERING CONTRACTOR L1 |
|---|---|---|---|---|---|---|
| 1.00 | Clearing Heavy jungle and disposing off to a place away from the site as directed by the Engineer in charge including all labour charges, T&Ps etc., complete. | 3,750 | sqm | 10 ₹37,500 | 10 ₹37,500 | 3 ₹11,250 |
| 2.00 | Earthwork excavation for foundation with an initial lead of 10 m and lift of 2 m etc complete for in hard gravelly soil | 1,714 | m3 | 300 ₹5.1 L | 250 ₹4.3 L | 300 ₹5.1 L |
| 3.00 | Earthwork excavation for foundation with an initial lead of 10 m and lift of 2 m etc complete for In SDR (Not Requiring Blasting) | 429 | m3 | 350 ₹1.5 L | 250 ₹1.1 L | 300 ₹1.3 L |
| 4.00 | Laying of lime mortar in 1:2 ratio for foundation basement to increase the foundation stability including cost of materials, laying, consolidation etc., complete. | 274 | m3 | 3,250 ₹8.9 L | 3,000 ₹8.2 L | 2,400 ₹6.6 L |
| 5.00 | PCC 1:3:6 using 20 mm HBG metal for foundation including cost of cement without formwork all materials, labour, lead, lift etc. complete. | 148 | m3 | 8,000 ₹11.8 L | 6,800 ₹10.1 L | 5,000 ₹7.4 L |
| 6.00 | PCC 1:2:4 mix using 20 mm down graded HBG machine crushed metal for plinth foundation concrete, cost of all labour, materials, lead, lift, curing etc. complete as per standard specification. Without Form Work | 38 | m3 | 8,500 ₹3.2 L | 7,500 ₹2.9 L | 7,000 ₹2.7 L |
| 7.00 | PCC 1:2:4 mix using 20mm down graded HBG machine crushed metal for plinth foundation concrete, cost of all labour, materials, lead, lift, curing etc. complete as per standard specification. With Form Work | 5 | m3 | 12,750 ₹63,750 | 12,250 ₹61,250 | 10,000 ₹50,000 |
| 8.00 | RCC 1:1.5:3 using 12 to 20 mm machine crushed metal for Raft concrete without formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For raft concrete) | 75 | Cum | 12,000 ₹9 L | 11,000 ₹8.3 L | 9,000 ₹6.8 L |
| 9.00 | RCC 1:1.5:3 using 12 to 20mm machine crushed metal for Plinth concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Plinth concrete ) | 265 | Cum | 17,250 ₹45.7 L | 16,000 ₹42.4 L | 10,000 ₹26.5 L |
| 10.00 | RCC 1:1.5:3 using 12 to 20mm machine crushed metal for cable duct bottom slab concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Cable duct bottom raft ) | 53 | Cum | 13,500 ₹7.2 L | 12,500 ₹6.6 L | 10,000 ₹5.3 L |
Tender Value
Refer Docs
EMD Value
₹2.6 L
Closing Date
16 Dec 2025, 2:30 pmClosed
CE/TP-I/CNI
O/o the Chief Engineer/Transmission Projects I / Chennai, 3rd Floor , 110 KV GIS Substation building A-10, Guindy Industrial Estate, Guindy, Chennai -32
Providing Cable duct, Culvert, Transformer Structural plinth, RCC retaining wall, Metal spreading and filling the site with gravel and all allied civil works for the proposed New Elur 110/22 KV SS.
2025_EB_628522_1
TP1-130/2025-26 OF CE/TP-I/CNI
Open Tender
Civil Works
120 days
Elur
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2.6 L
10 Apr 2026
3 Dec 2025
17 Dec 2025
3 Dec 2025
16 Dec 2025
3 Dec 2025
Clearing Heavy jungle and disposing off to a place away from the site as directed by the Engineer in charge including all labour charges, T&Ps etc., complete.
Earthwork excavation for foundation with an initial lead of 10 m and lift of 2 m etc complete for in hard gravelly soil
Earthwork excavation for foundation with an initial lead of 10 m and lift of 2 m etc complete for In SDR (Not Requiring Blasting)
Laying of lime mortar in 1:2 ratio for foundation basement to increase the foundation stability including cost of materials, laying, consolidation etc., complete.
PCC 1:3:6 using 20 mm HBG metal for foundation including cost of cement without formwork all materials, labour, lead, lift etc. complete.
PCC 1:2:4 mix using 20 mm down graded HBG machine crushed metal for plinth foundation concrete, cost of all labour, materials, lead, lift, curing etc. complete as per standard specification. Without Form Work
PCC 1:2:4 mix using 20mm down graded HBG machine crushed metal for plinth foundation concrete, cost of all labour, materials, lead, lift, curing etc. complete as per standard specification. With Form Work
RCC 1:1.5:3 using 12 to 20 mm machine crushed metal for Raft concrete without formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For raft concrete)
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for Plinth concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Plinth concrete )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for cable duct bottom slab concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Cable duct bottom raft )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for cable duct Side wall concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Cable duct side wall )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for Culvert top slab concrete with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Culvert top slab )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for retaining wall heel slab with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Retaining wall heel slab )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for retaining wall stem wall with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Retaining wall concrete )
RCC 1:1.5:3 using 12 to 20mm machine crushed metal for precast cable duct slab with formwork including cost of all materials, labour lead, litf, curing, etc., complete. Excluding the cost of steel reinforcement ( For Pre cast cable duct slab )
Providing steel reinforcement using steel of grade Fe 500 for RCC works including cost of steel, binding wire and placing in postion of the steel reinforcement, including cost of all materials, lead, lift, etc., complete.
Plastering in cm 1:3, 12 mm thick for concrete work including cost of cement, all materials, labour, lead, lift etc., complete.
Plastering in cm 1:5, 12 mm thick for wing wall including cost of cement, all materials, labour, lead, lift etc., complete.
Colour washing 2 Coats over a base coat of primer using Exterior weather coat using Asian APEX or Equivalent of approved Brand,quality and colour for outer wall surfaces for all floors including cost of all labours to work at all levels cost of materials brushes scaffolding charges etc. complete complying with standard specification and as directed.
Supplying, fabrication, galvanizing and fixing of GI / MS angles of various sizes to be fixed in the cable duct to the required length including cost of all materials, labour,lead, lift etc., complete.
Refilling the excavated earth including all lead, lift etc, complete.
Removal of excess earth to a distance of 2.00 Km with all lead, lift etc., complete
Transporting and fixing of RCC cover slab from curing tank to working spot including cost of labour, lead, lift etc., complete.
Supplying and fixing readymade earth collars of size 60 cm inner dia with 30 cm height and shell thickness of 50 mm including cost of all materials,transport to site , labour, lead, lift, etc., complete., as per standard specification.
Supplying and fixing of 20 mm PVC bib cock including cost of all materials, etc., complete.
Providing and laying PVC high density pipe (10 kg. per cm2 ) including cost of all specials like coupling, bend etc., and including necessary earthwork and burrying , all material labour, etc., complete and as directed by the Engineer-in-charge at site.. For 20 mm dia
Providing and laying PVC high density pipe (10 kg. per cm2 ) including cost of all specials like coupling, bend etc., and including necessary earthwork and burrying , all material labour, etc., complete and as directed by the Engineer-in-charge at site.. For 32 mm dia
Providing and laying PVC high density pipe (10 kg. per cm2 ) including cost of all specials like coupling, bend etc., and including necessary earthwork and burrying , all material labour, etc., complete and as directed by the Engineer-in-charge at site.. For 40 mm dia
Providing and laying PVC high density pipe (10 kg. per cm2 ) for provide weep holes in the retaining wall including all material labour, etc., complete and as directed by the Engineer-in-charge at site.. For 50 mm dia
Providing pipe line for laying cable to breaker plinths with 110 mm dia PVC pipe 4 kg/cm2 including all specials and cost of all material, lead, lift, etc., complete as per standard specification and as directed by the Engineer-in-charge at site.
Providing and fixing wheel valve of 32 mm diameter of Gun metal made including cost of all materials, labour, lead and lift etc., complete and as directed by the Engineer-in-charge at site.
Providing and fixing wheel valve of 40 mm diameter of Gun metal made including cost of all materials, labour, lead and lift etc., complete and as directed by the Engineer-in-charge at site.
Fabrication, galvanizing and supply of foundation bolts of 20 mm dia including providing cleat at bottom and threading at top including cost of all materials, labour lead lift etc., complete.
Fabrication of Template and assembling in correct position for various equipment plinth and grouting the foundation bolts including cost of all materials, labour, lead, lift etc. complete.as directed by the dept. Engineer at site
Supplying and fixing of MS rails of size 90/120 lbs for transformer plinth at site including cost of all lead, lift, etc., complete.
Writing the name of sub station on wing wall over plasterd surface using approved colour and qualityenamel paint over a cost of primer including cost of all materials , lead,lift etc., complete
Supplying and spreading of both metal jelly and stone dust with metal jelly of size 12 mm to 20 mm to an average thickness of 10 cm and over 10 cm stone dust including cost of all materials lead, lift watering and levelling surface etc., complete.
Supply of NP3 Class RCC Pipe confirming to IS 458/2003 including cost of pipe as a finished work including all other incidental charges, testing charges including loading, unloading, transport and delivery in good condition at work site etc., complete, as directed by the Departmental Officers, as per standard specifications. 900 mm Dia
Hoisting and fixing of NP3 Class RCC Pipe and Collars in proper gradient including all labour charges and all other incidental charges etc., complete, as directed by the Departmental Officers, as per standard specifications. 900 mm dia
Supplying , filling & spreading of good quality gravel layer by layer with proper consolidation for including cost of all materials ,labour, lead., lift etc.Complete.
CGST in % (For Bidders inside TamilNadu)
SGST in % (For Bidders inside TamilNadu)
IGST in % (For Bidders outside TamilNadu)
stage.html
html • 0.04 MB
techsummary_751526.pdf
BOQ Comparative Chart
xlsx
finsummary_751526.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.95 MB
BOQ_751526.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid