GENERAL MANAGER, JHANJRA AREA
OFFICE OF THE GENERAL MANAGER, JHANJRA AREA, PO-LAUDOHA, BO, DIST. - PASCHIM BARDHAMAN, PIN-713385
Transportation, installation and necessary fabrication, commissioning and trial run including extension of one no 1000mm width, 1x90kW, 550V, Single drive belt conveyor along 78L from 8D to 19D for development of panel 7 in R VII seam at 3n4 incline
2023_ECL_282638_1
ECL/GM/JNR/EnM/e-TenderCell/ 23-24/015
Open Tender
Miscellaneous Works
Item Rate
60 days
JHANJRA UNDERGROUND
PLEASE REFER TO TENDER DOCUMENTS.
4 documents required · 4 mandatory
₹23,700
16 Sept 2023
30 Jun 2023
12 Jul 2023
30 Jun 2023
11 Jul 2023
1 Jul 2023
30 Jun 2023 - 7 Jul 2023
Amount
Transportation, installation, necessary fabrication commissioning & trial run including extension of one no. 1000mm width, 1x90kW, 550V, single drive belt conveyor along 78L from 8D to 19D for development of panel - 7 in RVII seam at 3&4 incline, J.P. Colliery.
Transportation of the 1000mm width, lx90kW, 550V Drive Head complete including gear box, motor(90kW/550V), base frame, couplings, bearing blocks, fencing etc from surface and llation at 78L/9D (R-VII) with necessary fabrication job.
Transportation of Discharge Unit complete with girders, strike plate, chute plates, scrappers etc from surface and installation at 78L/8D (R-VII) with necessary fabrication job.
Transportation of Loop Take Up Unit complete with motorized winch from surface and installation at 78L/(9D-10D) (R-VII) with necessary fabrication job.
Transportation of Tail End Unit complete with fencing from surface and installation at 78L/11D (R-VII) with necessary fabrication job
Transportation of 103.5mtr. 1000mm belt conveyor structure complete with stringer, foot stool, top bracket, top & bottom roller etc. from surface to 78L belt installation site and installation from 78L/8D to 78L/1 1D in R-VII seam.
Loading, transportation and unloading of one breaker(550 V/200A), starter(550V/90kW), LS unit from surface to 78L/9D(R-VII) with help of haulages & 60 mtr manually. (Distance- approx. 3800mtr.)
Transportation of 500mtr 3.3kV grade 70 sq.mm. PVCDWA cable from surface to 71L/6D(R- VID) with help of haulages. (Distance- approx. 3400mtr.)
Making of drive head base frame & tail end frame at site with ISMB-250.
Transportation of 230 mtr. 1000mm width PVC belting from surface to 78L belt installation site with help of haulages & 60mtr manually. (Distance- approx. 3800mtr.)
Laying, lapping, jointing & tensioning of this 230 mtr. 1000mm width PVC belting in proposed 78L belt.
Transportation of 400mtr belt sequence cable from surafce to 73L/7D(R-VII); then laying- placing them from 73L/8D starter to 78L/9D starter in R-VIl seam.
Transportation of pull cords with its cable, communication devices with its cable, signalling system (8-SWG GI wire, bobbin insulators & 3/8" X 3" MS Bolt-nut) from suarfce to 78L belt installation site with help of haulages for 103.5mtr. belt and laying-placing them from 78L/8D to 78L/11D in R-VII seam.
Testing, trial run, alignment & commissioning of this belt conveyor from 78L/8D to 78L/1 1D in R-VII seam.
Eight times extension of the proposed 78L belt conveyor from 78L/11D to 78L/19D for a length of 276 mtr. in R- VII seam of 3&4 Incline Unit, JPC.J.P. Colliery.
Ten times dismantling of tail end unit complete for Ten times belt extension of proposed 78L
times transportation and installation of tail end unit complete for ten times belt extension proposed 78L belt from 78L/11D (RVII) to 78L/21D(R-VII)
Transportation of 1000mm belt structures (i.e. foot stools, channels, brackets, top and bottom rollers etc.) for a length of 345mtr. from surface to belt extension site by haulages and installation them from 78L/1 ID to 78L21D in R-VIl seam during ten times belt extension. each time belt extension will be for a length of 34.5 meter.
Transportation of 552mtr. 1000mm PVC belting from surface through haulages & 60mtr. nanually to 78L(R-VII) belt extension site.
Laying, Lapping, Jointing & Tensioning of this 552mtr. 1000mm belting from 78L/11D to 78L/19D in R-VIl seam during eight times belt extension and trial run.
Transportation of pull cords with its cable, communication devices with its cable, signalling System (8-SWG GI wire, bobbin insulators & 3/8" X 3" MS Bolt-nut) for 276 mtr. belt from surface to 78L belt extension site and laying & fitting them during eight times belt extension.
Civil foundation works for installation of 1X90kW, 550V, 1000mm wide belt conveyer drive head, discharge unit, loop take-up unit and platform for ACB, Starter for 82L belt conveyor of 3&4 incline, JPC.
Recess cutting in stone
Cleaning of debris/Muck
Sand filling
Brickwork with flyash bricks in foundation & plinth in cement mortar 1:6
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plinth level :1:2:4 ( 1 cement : 2 coarse sand (zone III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
12 mm cement plaster of mix 1:6
Loading material into tub and loading at site
Roof heightening by drilling blasting in stone, cleaning, roof bolting including cost of drill rod, drill bit for installation of proposed 82L belt conveyor in R-VII seam of 3&4 incline under JPC.
Roof heightening by drilling blasting in stone including dressing, cleaning with cost of drill rod and drill bit.(Excluding cost of explosive & detonator)
Roof bolting including carrying of materials from surface to UG side, drilling, grouting & cost of drill rod and drill bit
Supply of materials
Supply of DA Cylinder
Supply of Oxygen Cylinder
Supply of HT NuttBolt of M20 X 75mm
Supply of HT Nutt+Bolt of M20 X 65mm
Supply of MS Nut+Bolt of 5/8" X 2"
Total impact of GST for the purpose of CTC
K R ENTERPRISE
N.K. ENTERPRISE
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .