Tender Value
₹33.7 L
EMD Value
₹3.4 L
Closing Date
17 Aug 2026, 5:00 pm
EO NPP BIJNOR
O/O EO NPP BIJNOR
Construction Work and installation of Wet Waste Processing (Pit Composting) Unit of 05 TPD capacity at Solid Waste Management Processing At Village Salempur Mathana Urf Puranpur in Nagar Palika Parishad Land .
2026_DOLBU_1172973_1
133/ET-NPPB/2026-27
Open Tender
Solid Waste Management
Percentage
180 days
EO NPP BIJNOR
PLEASE PREFER TENDER DOCUMENT
2 documents required · 2 mandatory
₹854
EO NPP BIJNOR
₹3.4 L
28 Jul 2026
28 Jul 2026
18 Aug 2026
28 Jul 2026
17 Aug 2026
28 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Surface Dressing of ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m. All kinds of soil. | 700.07 | Sqm | 12 | ₹8,400.84 |
| 2 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in-Charge 2.1.1. All kinds of soil. | 120.17 | Cum | 156 | ₹18,746.52 |
| 3 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5KM also including ramming and watering of the earth in layers not exceeding 20cm in trenches, plinth, sides of foundation etc. complete | 61.08 | cum. | 103 | ₹6,291.24 |
| 4 | Providing & Laying of C.C. in 1:6:12 with c/s and 40 mm G.S.B. in foundation of Floor i/c all labour ,materials and T&P etc. | 76.13 | Cum. | 4,630 | ₹3,52,481.9 |
| 5 | R.C.C. work in column 1:2:4 with cement , coarse sand, 20 mm gauge stone grit I/c all complete | 44.99 | Cum. | 7,340 | ₹3,30,208.54 |
| 6 | M150 Brick Work in 1:6 c/s mortar in sub-structure i/c all labour & T&P etc. | 75.86 | Cum. | 6,562 | ₹4,97,793.32 |
| 7 | 12 mm thk Internal Plaster in 1:3 with c/s mortar in wall i/c all materials, labour & T&P etc. S.I-586 | 1,081.48 | Sqm. | 242 | ₹2,61,718.16 |
| 8 | Providing & laying steelbars including cutting binding, placing and complete in all respect | 35.32 | Qtl | 6,500 | ₹2,29,548.92 |
| 9 | Mild steel or iron work in heavy size such as trusses, build up gates record racks, roof work, gates etc wrought to required from including drilling holes riveting or welding where necessary and their fixing required for proper completion of the work. | 55 | Qtl | 7,500 | ₹4,12,500 |
| 10 | Mild steel or iron work of small size and sections such as holding down bolts, hold fast, tie rods, grating etc,(when not included in an overall rates) wrought to required shape as necessary for bending etc including supply of steel and its wastage including cost of bolts, nuts if required, welding, grinding and making holes as required for completion of work but | 12 | Qtl | 9,715 | ₹1,16,580 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.01 MB
BOQ_2202706.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].